SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Cal) 445

IN THE HIGH COURT AT CALCUTTA
Arijit Banerjee, Om Narayan Rai, JJ.
State of West Bengal & Anr. – Petitioners
Versus
CAB Engineers Pvt. Ltd.- Respondents
FMA 2795 of 2013
Decided On : 25-08-2025

Advocates Appeared:
For the Appellant : Mr. Swapan Banerjee, Adv., Mr. Suman Sengupta, Adv., Mr. Sambuddha Dutta, Adv., Mr. Diptendu Narayan Banerjee, Adv.
For the Respondent: Mr. Sakya Sen, Sr. Adv., Mr. Sabyasachi Sen, Adv., Ms. Pallavi Chatterjee, Adv.

The court confirmed the validity of the Arbitrator's findings regarding excess work claims and the correct application of interest, highlighting that overlapping interest claims were erroneous.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Modification of arbitral award - Appeal against order modifying award of Rs.33,52,590/- for additional works executed beyond 10% of original estimated work dismissed - Arbitrator's findings are plausible and grounded in contract provisions. (Paras 1, 36)

(B) Claim entitled to payment based on schedule of rates - Claim No. 9 for interest found redundant as it overlaps with Claim No. 8; award modified accordingly. (Paras 28, 30)

(C) Delay in payment of RA bills results in entitlement to interest under Claim No. 8 - Interest awarded appropriately based on contract conditions and delays acknowledged. (Paras 26, 27)

Facts of the case:
The appellants challenged a civil court's order that modified an arbitral award to favor the respondent's claims relating to additional payment for work on an irrigation scheme; specifically, payments for excess work and interest on delayed dues.

Findings of Court:
The appeal was dismissed as the learned court’s order modifying parts of the arbitral award was upheld, confirming the Arbitrator’s calculations for additional work and the reasoning given therein.

Issues: The main issues revolved around the legality of the award, the claim for excess payment for additional work, and the appropriateness of claimed interest amounts.

Ratio Decidendi: The court confirmed that the findings made by the Arbitrator were supported by the evidence and contract provisions, noting that the claim for interest under Claim No. 9 was incorrect due to overlap with Claim No. 8.

Result: Appeal dismissed.

JUDGMENT :

Om Narayan Rai, J.

1. This appeal under Section 37 of the Arbitration and Conciliation Act, 1996 (hereinafter ‘the said Act of 1996’) lays challenge to an order dated April 29, 2009 passed by the learned Civil Judge (Senior Division), Purulia, whereby the appellants’ application under Section 34 of the said Act of 1996 (which was registered as Misc. Case No. 05 of 2006) was disposed of by modifying the arbitral award dated January 31, 2006 that had been impugned in the said application under Section 34 of the said Act of 1996.

FACTS:

2. Briefly summed up, the facts of the case, insofar as they are relevant for the present appeal, are as follows:

a. The appellants had floated a tender for completion of “Remaining works of Dam, Dyke and Spillway in connection with the Extension of Bandhu Irrigation Scheme, in P.S. Arsa, District Purulia”.

b. The respondent participated in the tender process and emerged successful. Thereafter the contract for the aforesaid work was awarded to the respondent.

c. Disputes and differences arose between the parties relating to the execution of the aforesaid work awarded to the respondent by the appellants. In terms of the arbitration clause contained in the relevant agreement governing the parties, an Arbitrator was appointed and the disputes that had arisen between the parties were referred to the Arbitrator for adjudication.

d. The respondent herein filed its statement of claim, laying as many as nine distinct claims which are as follows:

“CLAIM NO. 1
Amount payable as per final bill prepared by the Department but not yet passed for payment or paid--Rs.3,90,768/-
CLAIM NO. 2
Amount payable against security deposit lying with the department --Rs.1,00,000/-
CLAIM NO. 3
Amount payable due to loss suffered in flush flood during 25th & 26th September, 1992 for being an Act of God.--Rs.14,82,880/-
CLAIM NO. 4
Additional amount payable on A/C of excess/additional works executed beyond (+) 10% of original estimated work provided in the tender (i.e. work beyond normal variation limit) all as per instruction and direction of Engineer-in-Charge.--Rs.63,45,996/-
CLAIM NO. 5
a)Compensation on account of damages and losses suffered due to various breaches of contract by the department infructuous expenditure incurred due to repeated suspension of work for reasons attributable to the departmentRs. 11,65,005/-
b)Increase in cost of work due to rise in prices of labours and materials for all works executed in the over-run period, for reasons attributable to the department.Rs. 22,62,190/-
c)Additional/extra On-site expenses incurred due to prolongation of work by more than 13 months. (Claimed 7 months only considering excess work)Rs. 3,67,850/-
d)Additional/extra cost involved due to detention of heavy plants and machineries due to prolongation of work by more than 13 months. Rs. 20,35,833/-
(Claimed 7 months only considering excess work)
e)Additional/Extra Off-site (H.O.) Expenses incurred due to prolongation of work more than 13 months. (Claimed 7 months only)Rs. 1,00,000/-
f)Additional Guarding expenses incurred to pacify local unrest of land losers-cum-villagers by engagement as extra alleged security staffs all as per approval and knowledge of Engineer-in-Charge.Rs. 3,60,000/-
(16 Guards @ Rs. 750/- P.M. from November ’91 to April ’94)
g)Extended stay compensation and/or loss of profit earning capacity being retained longer in the contract without any corresponding monetary benefit and without being free to move elsewhere to earn the normal profit, which he otherwise might do.Rs. 5,46,700/-
CLAIM NO. 6
Repair and maintenance of old village Road and approach road, being badly damaged by September, 1992 flood (movement of all vehicles including Govt. vehicles were stopped by the villagers), repaired on instruction of Engineer- in-Charge by supplying, laying & consolidating, boulders (where necessary), 40mm down stone metal and morrum including mechanical compaction. L.SRs.8,50,000/-
CLAIM NO. 7
Amount payable on A/C of differ

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top