SUPREME COURT OF INDIA
SANJIV KHANNA, M.M. SUNDRESH, JJ.
Batliboi Environmental Engineers Limited – Appellant
Versus
Hindustan Petroleum Corporation Limited And Another – Respondents
Civil Appeal No. 1968 of 2012
Decided on : 21-09-2023
Fact of the Case:
The case involved an employee who claimed that she was discriminated against by her employer due to her pregnancy.Finding of the Court:
The court found that the employer had treated the employee less favorably due to her pregnancy, which constituted direct discrimination.Ratio Decidendi:
The court relied on the provisions of the Equality Act 2010, specifically Sections 13 and 39, to establish that the burden of proof had shifted to the employer to prove that there was no discrimination. The court also considered the employee's protected characteristic (pregnancy) and the unfavorable treatment she received. Final Decision: The court ruled in favor of the employee, finding the employer liable for direct discrimination based on the employee's pregnancy.JUDGMENT :
SANJIV KHANNA, J.
This appeal by way of special leave by Batliboi Environmental Engineers Limited1[For short, BEEL] takes exception to the judgment dated 02.11.2007, whereby the Division Bench of the High Court of Judicature at Bombay allowed the appeal2[Appeal No. 227 of 2001 in Arbitration Petition No. 280 of 1999.] filed by Hindustan Petroleum Corporation Limited3[For short, HPCL.] under Section 37 of the Arbitration and Conciliation Act, 19964[For short, A&C Act.], and thereby has set aside the arbitral award dated 23.03.1999.
2. On acceptance of tender and in terms of the letter of intent dated 27.02.1992, HPCL had awarded to BEEL the turnkey contract for detailed engineering including civil and structural design, supply and erection, testing and commissioning of 23 MLD capacity Sewage Water Reclamation Plant in Mahul Refinery area. The contract value was Rs.574.35 lakhs. The contract period was 18 months from the date of letter of intent, and accordingly the work was to be completed by 28.08.1993. There was delay in completion. On written requests/applications made by BEEL, the time for completion was extended on two occasions. Three revisions were also issued by HPCL. The last revision dated 20.09.1994 had extended the period for completion from 26.09.1994 by 10 months beginning from the date on which approval of electrical items was accorded by HPCL. BEEL carried on the work till 30.03.1996. Thereafter, BEEL abandoned the work. It is an accepted position that as on 30.03.1996, 80% of the work was complete.
3. On 04.07.1996, BEEL made a formal claim to HPCL for breach of contract on account of delay in execution, causing extra expenses and losses. By the letter dated 16.05.1997, BEEL sought an advance payment of Rs.50 lakhs to enable them to resume work, and simultaneously expressed its desire to resolve the dispute through conciliation. BEEL by the same letter also invoked the arbitration clause in the contract, if the proposal as given by BEEL was unacceptable to HPCL. HPCL by the letter dated 05.05.1997 refused to make payment, and relying on the terms of the contract had impressed upon BEEL to resume and complete the remaining work, even if the matter was to proceed for arbitration. BEEL did not agree and resume work.
4. The General Manager (Project), Mahul Refinery, HPCL, appointed Mr. K. Narayanan as the sole arbitrator to adjudicate upon the disputes and differences in the execution of the contract. Claim was filed by BEEL and reply/counter claim was filed by HPCL, to which rejoinder with supporting documents and sur-rejoinders were filed. In all about 14 hearings were held before the arbitral tribunal between the period 12.03.1998 and 07.01.1999 and oral arguments were addressed. Ocular evidence was not led. The learned arbitrator had conducted a site inspection on 24.12.1997.
5. The arbitral award dated 23.03.1999, substantially allows the Claims Nos. 1, 2, and 4 of the BEEL. The relevant portion of the award dealing with the claims of the BEEL, reads:
“A. Claims of the Claimants:
Claim No.1 – Compensation for loss of Overhead and profit and also profitability: Rs.3,38,38,460.00
The claim is forwards loss of Overheads and profit/profitability calculated on the basis of 48 months delay as of 27.08.1997. The Claimants have considered 10% of the Contract value towards Overheads and another 10% towards profit/profitability to arrive at the above figure, after taking into account the same percentages from the payments already received by them.
My finding is that the Owner Respondents are fully responsible for the huge delay that occurred by not taking proper and timely action in removing the various impediments and obstacles that stood in the way of completing the project in the given span of 18 months. The party had been tied down to a project, which was allowed to drift aimlessly, with the owner-respondent
Clauses in contracts that prohibit claims for damages are against public policy and void under Section 23 of the Indian Contract Act, 1872, as they undermine the sanctity of contracts.
(1) Setting aside arbitral award – Claim for damages, whether general or special, cannot as a matter of course result in an award without proof of claimant having suffered injury.(2) Binding Preceden....
(1) Appeal against modified arbitral award – Merits of award are only to be gone into, if award is demonstrated to be contrary to public policy of India.(2) Arbitral proceedings are per se not compar....
The judicial review under Section 34 of the Arbitration and Conciliation Act is restricted to issues of patent illegality, ensuring that arbitrator's findings are not disturbed unless they fundamenta....
Arbitral awards set aside partly for patent illegality where head office overhead claims lack evidentiary support like unverified CA certificates without witness testimony, despite upholding other pr....
The main legal point established in the judgment is the narrow scope of interference with an Arbitral Award under Section 34 of the Act, 1996, and the emphasis on reasonableness, natural justice, and....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.