SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2025 Supreme(Cal) 610

IN THE HIGH COURT AT CALCUTTA
SHAMPA SARKAR, J.
Kamini Ferrous Limited - Appellant
Vs.
Om Shiv Mangalam Builders Private Limited & Anr. - Respondent
A.P - 43 of 2024
Decided On : 06-08-2025

Advocates:
Advocate Appeared:
For the Appellant : Mr. Rudraman Bhattacharyya, Sr. Adv. Ms. Amrita Panja Moulick, Adv. Mr. Sourajit Dasgupta, Adv. Mr. Akash Munshi, Adv. Mr. Siddharth Banerjee, Adv. Ms. Shivangi Agarwal, Adv.
For the Respondent: Mr. Aritra Basu, Adv. Mr. Ritoban Sarkar, Adv. Mr. Arka Banerjee, Adv. Ms. Surabita Biswas, Adv.

The court recognized that arbitration agreements are binding and disputes regarding time-bar claims should be determined by the arbitrator, given the circumstances of the parties' ongoing negotiations.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 11(6) - Dispute arising out of development agreement for sale of flats - Respondents failed to deliver the flats by deadline - Application filed for appointment of arbitrator after 10 years - Claim was alleged to be time-barred but dispute deemed referable to arbitration for determination. (Paras 1, 9, 12, 15)

(B) Limitation - Issue of time-bar in arbitration claims could be determined by the arbitrator, not the court at the referral stage - Delay in invoking arbitration was not sufficient to reject the application outright. (Paras 13, 14)

(C) Contract Performance - Time is not of the essence in construction contracts - There could be an implicit extension of time inferred from parties' conduct. (Paras 4, 12)

Facts of the case:
The petitioner entered into a development agreement for flats in 2012, with a deadline for possession in December 2013; no possession was delivered, and the respondents later offered a refund of investments with penalties, indicating inability to perform.

Findings of Court:
The letter issued by respondents indicated ongoing negotiations about completion and refund, flashing an active contract.

Issues: The primary issue concerned the invocation of arbitration despite a long delay and whether such claims were time-barred.

Ratio Decidendi: The court stated that while limitation issues are significant, the arbitrator is better positioned to evaluate them in context of the claims and ongoing negotiations.

Result: The application for arbitration was allowed.

Table of Content
1. arbitration clause outlined in agreement. (Para 1)
2. details of transaction and failure to perform. (Para 2 , 3)
3. debate on validity of arbitration agreement. (Para 4 , 7)
4. extension of time inferred from conduct. (Para 5)
5. limitation issues and claim timeliness. (Para 6 , 8)
6. court's analysis of arbitration agreement's implications. (Para 9 , 10 , 12)
7. guidance on limitation under section 11. (Para 11 , 13 , 14)
8. ruling on application and arbitration process. (Para 15)
9. appointment of arbitrator and conclusive order. (Para 16)

JUDGMENT :

Shampa Sarkar, J.

1. This is an application under section 11(6) of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the said Act). The arbitration clause is contained in the agreement dated April 13, 2012. Clause 14 of the said agreement provides that any dispute or difference between the parties, relating to or arising out of the said agreement or any act, deed or proceeding done or to be done in pursuance of the said agreement, shall be referred to arbitration in accordance with the provisions of the Arbitration and Conciliation Act, 1996. The arbitration shall be held at Kolkata and shall be in English language.

2. Mr. Rudraman Bhattacharya, learned senior Advocate for the petitioner submitted that the respondent no. 1 was a Company. The respondent no. 2 was the Director of the respondent no. 1. The respondents entered into a development agreement with the petitioner. A sum of Rs. 1 crore was the total consideration payable for two flats on the third floor of the proposed building along with two car parking spaces, as described in the Schedule of the said agreement. Although, the payment was made on April 13, 2012, no formal agreement was executed on the date of payment. The development agreement was executed on April 13, 2012. According to the agreement, the respondents were required to deliver the aforesaid flats and the parking spaces to the petitioner, within December 2013. The time for performance of the agreement was extended from time to time, as the respondents were unable to obtain the sanction plan from the concerned Municipal Corporation. The petitioner allegedly called upon the respondents on various occasions to either execute a deed of sale and deliver the possession of the two flats along with the car parking spaces or refund the entire consideration. It was contended that, the respondent no. 2 assured the petitioner that, the issue would be resolved. By a letter dated 15th December, 2020, the respondents informed the petitioner that they had decided to sell the land on which the project was to be constructed and return the due of Rs. 1 crore which had been advanced by the petitioner, along with Rs. 25 lakhs, as penalty. The petitioner was requested to provide the copy of the original agreement, so that the same could be handed over to the land buyer. Further request was made that, upon receipt of full payment of Rs. 1.25 crores, the petitioner should cancel the agreement dated April 13, 2012 and be a confirming party to the sale of the land.

3. In spite of offering to refund the money with penalty, the respondents neither prepared any deed of sale to third party buyers nor did the respondents refund the money as indicated in the aforementioned letter. Although, no progress had been made in the area of construction, the balance sheet of the respondent no. 1 continuously showed that the work was in progress. The Director of the petitioner received information from reliable sources and also came across copies of the balance sheet of the company of the respondent. Upon perusal of such documents, the petitioner became apprehensive that, the rightful claim of the petitioner would be denied and defeated in a clandestine manner. From the balance sheet for the financial year 2021 – 2022, it appeared that payment of Rs. 1.25 crores was made by the respondent no. 2 to the respondent no. 1, as advance against property. Part of the amount was

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top