IN THE HIGH COURT OF JAMMU AND KASHMIR AND LADAKH AT SRINAGAR
Tashi Rabstan, A.C.J.
M/s Shah & Company through its Proprietor Shafiq Ahmad Shah - Petitioner
Versus
Jammu & Kashmir Power Development Corporation, through its Managing Director and ors. - Respondents
Arb P No.8 of 2023
Decided On : 10-09-2024
JUDGMENT :
Tashi Rabstan, A.C.J.
1. The instant petition has been filed by the petitioner seeking appointment of an arbitrator by invoking Section 11(6) of the Arbitration and Conciliation Act, 1996 (for short the 'Act')
2. The case set up by the petitioner is that being a Contractor he executed the work Construction of Junction Structure RD (-17) to 100 M of Sumbal Link Channel of USHP-II Kangan on the strength of the allotment letter bearing No.USHP-II/CE/7-Works of 1989 dated 17.06.1989. It is stated that the work was required to be completed within one year i.e. till 31.10.1990 but due to militancy activities and non-cooperation of the department in providing the requisite drawings and the material in time, the work got delayed and was completed on 31.08.2000. It is further stated that after completion of the work, final bill for an amount of Rs.49,37,599/- was submitted in the month of March, 2006, out of which an amount of Rs.27297/- was paid to the petitioner and the balance amount was assured to be released in favour of the petitioner shortly. It is stated that the respondents having failed to release the balance amount in favour of the petitioner, the petitioner through his counsel issued a legal notice dated 01.01.2011 to the respondents. It is stated that respondents having failed to act in the matter, the petitioner again, through his counsel, approached the respondents and issued another legal notice dated 25.01.2022 for release of the legitimate payment and reference of the dispute to arbitrator but the respondents failed to release the same and thus, a dispute is alleged to have arisen between the parties. The petitioner has further submitted that till date neither the payment has been released in his favour nor any arbitrator, as was sought to be appointed in the matter, has been appointed by the respondents in terms of Clause 54 of the agreement entered between the parties.
3. On notice of the petition to the respondents, the respondents appeared and filed their objections. In the objections, amongst other grounds, the respondents have disputed the claim of the petitioner on the ground that the claim raised by the petitioner is time barred. It is stated that final payment on account of the work done along with necessary escalation was made to the contractor in terms of the conditions of the contract agreement. It is further submitted that the defect liability period as per the conditions of the contract agreement was one year from the date of completion of the work and since the work was completed on 31.08.2000, therefore, the said period has expired on 31.08.2001. The allegation of the petitioner that completion of the work got delayed because of the non- cooperation of the respondents is refuted by the respondents and it is stated that all the necessary drawings and material was provided to the petitioner in line with the conditions of the contract agreement. It is stated that though there was a huge delay in completion of the work but the same was adjusted by giving extension in time from time to time without imposing any penalty and the work got completed on 31.08.2000. The respondents submit that since all the due payment to the petitioner has been made, thus there exists no dispute between the parties. It has accordingly been prayed that the petition may be dismissed.
4. In rebuttal, the petitioner has filed his response to the objections filed by the respondents and it has been pleaded therein that the respondents are admitting that only the last payment of Rs.28439/- and Rs.11477/- was paid in the month of March, 2006 against the work done and escalation and not the final payment and the same is stated to be still pending with the respondents. It has further been submitted that the plea taken by the respondents that notice of existence of any dispute is to be served within 30 days of the expiry of the defect liability period, has no relevance for the reason that during the said period there was no dispute a
Geo Miller & Co. Pvt. Ltd. v. Chairman, Rajasthan Vidyut Utpadan Nigam Ltd.
B and T AG v. Ministry of Defence
M/s Arif Azim Co. Ltd. v. M/s Aptech Ltd.
Jaguar Overseas Ltd v. J&K state Power Development Corporation
The Limitation Act, 1963 applies to arbitration claims; an application for an arbitrator appointment must be made within three years from when the right to apply accrues, otherwise, it is time-barred....
The Arbitration and Conciliation Act requires strict adherence to limitation periods for the appointment of arbitrators; delays exceeding three years render petitions ex-facie time-barred.
Arbitration requests must be filed within three years of the cause of action; failure to act in time bars subsequent petitions.
(1) Appointment of Arbitrator – Limitation – There is a fine distinction between plea that claims raised are barred by limitation and plea that application for appointment of Arbitrator is barred by ....
The main legal point established in the judgment is that the limitation for filing an application under Section 11 of the Arbitration Act arises upon the failure to make the appointment of the arbitr....
The main legal point established in the judgment is the application of the Limitation Act, 1963 to arbitration proceedings and the significance of acknowledging claims to extend the period of limitat....
The main legal principle established is that the Court should not reject an application for appointment of an arbitrator at the threshold unless the claim is manifestly, ex-facie and hopelessly time-....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.