SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2024 Supreme(J&K) 419

IN THE HIGH COURT OF JAMMU AND KASHMIR AND LADAKH AT SRINAGAR
Tashi Rabstan, A.C.J.
M/s Shah & Company through its Proprietor Shafiq Ahmad Shah - Petitioner
Versus
Jammu & Kashmir Power Development Corporation, through its Managing Director and ors. - Respondents
Arb P No.8 of 2023
Decided On : 10-09-2024

Advocates Appeared:
For the Petitioner:Mr. M. A. Chashoo, Advocate.
For the Respondent: Mr. Alla-ud-Din Ganai, AAG.

The Limitation Act, 1963 applies to arbitration claims; an application for an arbitrator appointment must be made within three years from when the right to apply accrues, otherwise, it is time-barred.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 11(6) - Limitation Act, 1963 - Claim for arbitration appointment filed after significant delay - Legal notice for arbitration served over five years post-final bill submission - Claim deemed ex-facie barred by limitation, aligned with Supreme Court precedent. (Paras 1, 15, 19)

(B) Limitation - Time period for seeking appointment of arbitrator under Section 11(6) is three years from the date when the right to apply accrues, as per Article 137 of the Limitation Act. Mere exchanges or negotiations do not extend limitation. (Paras 18, 20)

Facts of the case:
The petitioner, a contractor, alleged non-payment by the respondent for work completed in 2000, with the final bill submitted in 2006 and legal notices issued in 2011 and 2022. The delay in seeking arbitration was over 12 years.

Findings of Court:
The Court found the petition ex-facie time-barred, noting that notices and delays do not extend the limitation period.

Issues: Whether the claim was time-barred; if so, could an arbitrator be appointed?

Ratio Decidendi: The court emphasized the importance of the limitation period for arbitration requests, stating that the claim raised was significantly delayed, thus barred.

Result: Petition dismissed as time-barred.

JUDGMENT :

Tashi Rabstan, A.C.J.

1. The instant petition has been filed by the petitioner seeking appointment of an arbitrator by invoking Section 11(6) of the Arbitration and Conciliation Act, 1996 (for short the 'Act')

2. The case set up by the petitioner is that being a Contractor he executed the work Construction of Junction Structure RD (-17) to 100 M of Sumbal Link Channel of USHP-II Kangan on the strength of the allotment letter bearing No.USHP-II/CE/7-Works of 1989 dated 17.06.1989. It is stated that the work was required to be completed within one year i.e. till 31.10.1990 but due to militancy activities and non-cooperation of the department in providing the requisite drawings and the material in time, the work got delayed and was completed on 31.08.2000. It is further stated that after completion of the work, final bill for an amount of Rs.49,37,599/- was submitted in the month of March, 2006, out of which an amount of Rs.27297/- was paid to the petitioner and the balance amount was assured to be released in favour of the petitioner shortly. It is stated that the respondents having failed to release the balance amount in favour of the petitioner, the petitioner through his counsel issued a legal notice dated 01.01.2011 to the respondents. It is stated that respondents having failed to act in the matter, the petitioner again, through his counsel, approached the respondents and issued another legal notice dated 25.01.2022 for release of the legitimate payment and reference of the dispute to arbitrator but the respondents failed to release the same and thus, a dispute is alleged to have arisen between the parties. The petitioner has further submitted that till date neither the payment has been released in his favour nor any arbitrator, as was sought to be appointed in the matter, has been appointed by the respondents in terms of Clause 54 of the agreement entered between the parties.

3. On notice of the petition to the respondents, the respondents appeared and filed their objections. In the objections, amongst other grounds, the respondents have disputed the claim of the petitioner on the ground that the claim raised by the petitioner is time barred. It is stated that final payment on account of the work done along with necessary escalation was made to the contractor in terms of the conditions of the contract agreement. It is further submitted that the defect liability period as per the conditions of the contract agreement was one year from the date of completion of the work and since the work was completed on 31.08.2000, therefore, the said period has expired on 31.08.2001. The allegation of the petitioner that completion of the work got delayed because of the non- cooperation of the respondents is refuted by the respondents and it is stated that all the necessary drawings and material was provided to the petitioner in line with the conditions of the contract agreement. It is stated that though there was a huge delay in completion of the work but the same was adjusted by giving extension in time from time to time without imposing any penalty and the work got completed on 31.08.2000. The respondents submit that since all the due payment to the petitioner has been made, thus there exists no dispute between the parties. It has accordingly been prayed that the petition may be dismissed.

4. In rebuttal, the petitioner has filed his response to the objections filed by the respondents and it has been pleaded therein that the respondents are admitting that only the last payment of Rs.28439/- and Rs.11477/- was paid in the month of March, 2006 against the work done and escalation and not the final payment and the same is stated to be still pending with the respondents. It has further been submitted that the plea taken by the respondents that notice of existence of any dispute is to be served within 30 days of the expiry of the defect liability period, has no relevance for the reason that during the said period there was no dispute a

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top