IN THE HIGH COURT OF CHHATTISGARH AT BILASPUR
Goutam Bhaduri, Radhakishan Agrawal, JJ.
Municipal Corporation Bilaspur Through Commissioner, Bilaspur Chhattisgarh - Appellant
Vs.
Meinhardt Singapore Pvt. Ltd. - Respondent
ARBA No.38 of 2018
Decided On : 28-09-2022
Arbitration - Municipal Corporation - Arbitration and Conciliation Act, 1996, Commercial Courts Act, 2015 - Section 37 - Section 13(2) - Chhattisgarh Municipal Corporation Act, 1956 - UIDSSMT - JNNURM - Planning and Designing for Execution of Storm Drainage Water System - [NIT/EOI, Contract Agreement, Inspection Report, Preliminary Design Report, Draft Detailed Project Report, Consultancy Charges, Final Project Approval, Ministry of Urban Development, JNNURM Directorate, Government of India, State Level Sanctioning Committee, National Building Construction Corporation Ltd., Central Government, State Government, Municipal Corporation, Urban Infrastructure Development Scheme for Small and Middle Towns, State Urban Development Agency, Supreme Court Decisions, Commercial Court Decision, Arbitrator Decision]
Fact of the Case:
The appellant, Municipal Corporation, Bilaspur, issued a NIT/EOI for planning and designing the Storm Drainage Water System. The respondent submitted a bid, which was accepted, and a contract was executed. Dispute arose when the respondent claimed consultancy charges at 1.18% of the total project cost, which was refused by the appellant. The matter was referred to the Sole Arbitrator, who allowed the claim. The appellant challenged the award before the Commercial Court, which was dismissed, leading to the current appeal.
Finding of the Court:
The Court found that the Arbitrator's decision was based on a deemed approval of the project by the Central Government, which was not the case. The Court held that the Arbitrator's finding was based on no evidence and was a patent illegality. The Court set aside the arbitral award and the Commercial Court's decision.
Issues: The issues revolved around the scope of the consultant's services, approval of the final project cost, and the authority of the Arbitrator to decide within the terms of the contract.
Ratio Decidendi: The Court held that the Arbitrator's decision must be within the terms of the contract and based on evidence. The Court also emphasized that the approval of the final project cost by the Central Government was crucial and could not be presumed.
Final Decision: The Court allowed the appeal, set aside the arbitral award and the Commercial Court's decision, and made no order as to costs.
JUDGMENT :
The following judgment of the Court is delivered by Goutam Bhaduri, J.
1. The instant appeal under Section 37 of the Arbitration and Conciliation Act, 1996 (henceforth ‘the Act, 1996’) read with Section 13(2) of the Commercial Courts Act, 2015 (henceforth ‘the Act, 2015’) preferred against the order dated 3-11-2018 passed by the Commercial Court, Raipur, in MJC No.7/18 wherein the application filed by the appellant herein under Section 34 of the Act, 1996 was dismissed.
2. The appellant-Municipal Corporation, Bilaspur, incorporated under the provisions of the Chhattisgarh Municipal Corporation Act, 1956 (henceforth ‘the Act, 1956’) issued a NIT/EOI (Notice Inviting Tender/Expression of Interest) to carry out the work of planning and designing for execution of Storm Drainage Water System for Bilaspur City on 15-7-2010 under the UIDSSMT (Urban Infrastructure Development Scheme for Small and Middle Towns), a project of the Government of India, which is a component of JNNURM (Jawaharlal Nehru National Urban Renewal Mission).
3. Pursuant to the said NIT/EOI, the respondent herein submitted its bid, which was accepted by the appellant and contract agreement dated 24-1-2011 was executed between the parties and the work order was issued on 27-1-2011 in favour of the respondent for executing the work. The payment of consultancy fees was 1.18% of the total project cost. Initially the cost of the project was Rs.44.28 lacs and it was agreed that actual fees would be worked out based on the agreed percentage of the total final cost of the project.
4. The respondent submitted the Inspection Report, Preliminary Design Report and Draft Detailed Project Report (DPR) as a part of execution of work and the payment was made by the appellant for above work as per the payment schedule. After approval of final DPR, the respondent claimed Rs.4,07,03,583/- being 1.18% of total cost project of Rs.333.93 crores. The said claim was refused by the appellant and, as such, the dispute was referred to the Sole Arbitrator for adjudication.
5. The respondent raised its claim for consultancy charges at the rate of 1.18% of the total project cost i.e. Rs.333.93 crores as per clause 4(C) of the contract agreement before the Sole Arbitrator. The learned Sole Arbitrator after considering the submission, evidence adduced and documents, allowed the claim of the respondent herein and passed the award to the tune of Rs.4,07,03,583/-. It has also been observed by the Sole Arbitrator that in case the award amount is not paid within a period of three months from 7-2-2018 it would carry interest at the rate of 9% per annum on the awarded amount from the date of expiry of three months.
6. Being aggrieved by the said award, the appellant Corporation challenged the same before the learned Commercial Court under the provisions of Section 34 of the Act, 1996. The same has been dismissed by the Commercial Court by the impugned order. Hence, this appeal.
7. Learned counsel appearing for the appellant would submit that
- the Arbitrator travelled beyond the Terms of Reference (ToR) as was envisaged under the NIT/EOI;
- the Arbitrator only considered the Pre DPR activities, but the Post DPR which contained the Surveys, Investigation, Data Collection and providing Implementation Support Post DPR to BMC, was also part of contract;
- the expertise of the consultant/respondent was not only limited to passing of the project but extended even after the final project is approved while implementation of the project;
- the Arbitrator was required to arbitrate within the terms of the contract and he had no power apart from what the parties have given to him under the contract;
- the post DPR activities which were required to be performed by the respondent was not considered;
- the Arbitration Tribunal has failed to deal with the post DPR part, therefore, misdirected itself to decide the issu
AI
The main legal point established in the judgment is that an Arbitrator's decision must be within the terms of the contract and based on evidence. The approval of the final project cost by the Central....
A claim must have a cause of action; without final approval from relevant authorities, the claim is premature.
Arbitral awards are not appealed against but assessed for public policy adherence; courts cannot rectify mere errors of fact.
Section 34 of the Arbitration and Conciliation Act provides a limited window of challenge to an arbitral award, and a violation of a statute, not tied to public policy or public interest, cannot serv....
The arbitration agreement's validity is independent of stamp duty on the substantive contract, and courts have limited grounds for interfering with arbitral awards under Section 34 of the Arbitration....
The court affirmed that judicial interference in arbitral awards is limited, focusing on the necessity of cogent reasoning and adherence to public policy.
The arbitration agreement's validity is independent of stamp duty issues, and courts have limited grounds for interfering with arbitral awards.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.