HIGH COURT OF CHHATTISGARH AT BILASPUR
SANJAY S. AGRAWAL, RADHAKISHAN AGRAWAL
Municipal Corporation Bilaspur Through Commissioner, Municipal Corporation Bilaspur - Appellant
Versus
Meinhardt Singapore Pte. Ltd. (India Branch) Having Its Corporate - Respondent
Arbitration Appeal No. 38 of 2018
Decided on : 06-03-2025
(A) Arbitration and Conciliation Act, 1996 - Section 37 - Commercial Courts Act, 2015 - Section 13(2) - Appeal against rejection of application under Section 34 of the Arbitration Act - Dispute regarding consultancy fees for project work - The Arbitrator awarded Rs.4,07,03,583/- to the claimant, which was challenged by the appellant on grounds of exceeding Terms of Reference and lack of approval from the Ministry of Urban Development. (Paras 1, 6, 29)
(B) Cause of Action - The court emphasized that every action must have a cause of action, and if absent, the claim is premature. (Paras 25, 26, 28)
Facts of the case:
The appellant issued a tender for consultancy on a storm drainage project, which was accepted by the respondent. Disputes arose over the consultancy fee after the project cost increased significantly.
Findings of Court:
The court found that the claim was premature due to lack of final approval from the relevant authorities.
Issues: The main issues were whether the Arbitrator exceeded his authority and whether the claim was premature due to lack of cause of action.
Ratio Decidendi: The court ruled that the absence of final approval from the Ministry rendered the claim premature, emphasizing the necessity of a cause of action for legal proceedings.
Result: Appeal allowed.
| Table of Content |
|---|
| 1. appeal against arbitration award (Para 1) |
| 2. tender issued for consultancy (Para 2 , 3) |
| 3. claim for consultancy fee (Para 4 , 5 , 6) |
| 4. respondent's defense of claim (Para 7 , 8) |
| 5. court's review of evidence (Para 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18 , 19 , 20 , 21 , 22 , 23 , 24 , 25 , 26 , 27) |
| 6. finding on cause of action (Para 28) |
| 7. appeal outcome (Para 29) |
Judgment :
(Sanjay S. Agrawal, J.)
1) The instant appeal under Section 37 of the Arbitration and Conciliation Act, 1996 (henceforth ‘the Act, 1996’) read with Section 13(2) of the Commercial Courts Act, 2015 (henceforth ‘the Act, 2015’) has been preferred against the order dated 03-11-2018 passed by the Commercial Court (District Level), Raipur, in MJC No.7/18, wherein the application filed by the appellant herein under Section 34 of the Act, 1996 was rejected.
2) The appellant-Municipal Corporation, Bilaspur, incorporated under the provisions of the Chhattisgarh Municipal Corporation Act, 1956 (henceforth ‘the Act, 1956’) issued a NIT/EOI (Notice Inviting Tender/ Expression of Interest) to carry out the work of planning and designing for execution of Storm Drainage Water System for Bilaspur City on 15-7-2010 under the UIDSSMT (Urban Infrastructure Development Scheme for Small and Medium Towns), a project of the Government of India, which is a component of JNNURM (Jawaharlal Nehru National Urban Renewal Mission).
3) Pursuant to the said NIT/EOI, the respondent/claimant herein submitted its bid, which was accepted by the appellant/ Corporation and contract agreement dated 24-01-2011 was executed between the parties and the work order was issued on 27-01-2011 in favour of the respondent/claimant for executing the work. The payment of consultancy fee was @ 1.18% of the total project cost. Initially the cost of the project was Rs.37.53 crores and it was agreed that actual fees would be worked out based on the agreed percentage of the total final cost of the project.
4) The respondent/claimant submitted the Inception Report, Preliminary Design Report and Draft Detailed Project Report (DPR) as a part of execution of work and the payment was made by the appellant/Corporation for above work as per the payment schedule. After approval of final DPR, the respondent/claimant claimed Rs.4,07,03,583/- being 1.18% of total cost project of Rs.333.93 crores. The said claim was refused by the appellant/Corporation and, as such, the dispute was referred to the Sole Arbitrator for adjudication, who was appointed under sub-section (6) of Section 11 of the Act, 1996 by this Court vide order dated 27.01.2017 in ARBA No.67/2016.
5) The respondent/claimant raised its claim for consultancy charges at the rate of 1.18% of the total project cost, i.e. Rs.333.93 crores as per clause 4(C) of the contract agreement before the Sole Arbitrator. The learned Sole Arbitrator after considering the submission advanced, evidence adduced and documents produced, allowed the claim of the respondent herein and passed an award to the tune of Rs.4,07,03,583/- (Rs. Four Crores Seven Lacs Three Thousand Five Hundred Eighty Three only). It has also been observed by the Sole Arbitrator that in case, the award amount is not paid within a period of three months from 07-02-2018, it would carry interest at the rate of 9% per annum on the awarded amount from the date of expiry of three months. The relevant observation made in this regard at paragraph 31 reads as under :-
“31. In the result, an award for a total sum of Rs.4,07,03,583/-(Rupees Four Crores Seven Lakhs Three Thousand Five Hundred Eighty Three only) is passed in favour of the claimant and against the respondent. The respondent is allowed three months time from today i.e. 07.02.2018 for satisfying the award. In case the award amount is not paid within that period then the respondent shall be liable to pay simple interest @ 9% per annum on the awarded amount from the date of expiry of three months till date of realization. Parties shall bear the






Kusum Ingots & Alloys Ltd. vs. Union of India
A claim must have a cause of action; without final approval from relevant authorities, the claim is premature.
The main legal point established in the judgment is that an Arbitrator's decision must be within the terms of the contract and based on evidence. The approval of the final project cost by the Central....
Section 34 of the Arbitration and Conciliation Act provides a limited window of challenge to an arbitral award, and a violation of a statute, not tied to public policy or public interest, cannot serv....
Arbitral awards are not appealed against but assessed for public policy adherence; courts cannot rectify mere errors of fact.
Judicial review in administrative actions, particularly in tender matters, is limited to preventing arbitrariness and ensuring compliance with law, not to adjudicate contractual disputes.
The absence of a concluded contract precludes the invocation of arbitration under the Arbitration and Conciliation Act, affirming the need for absolute acceptance in contract formation.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.