IN THE HIGH COURT OF CHHATTISGARH AT BILASPUR
RAMESH SINHA, RAVINDRA KUMAR AGRAWAL, JJ.
M/S ZEPHYR-VEPL-KCL (JV) - Petitioner
Versus
South Eastern Coalfields Limited & Ors. - Respondents
WPC No. 2661 of 2021
Decided On : 24-11-2023
Contract Termination - Joint Venture Agreement - NIT No.SECL/BSP/CMC/e-Tender/407 - Clause 6.1, 9.2 of General Terms and Conditions - Section 56 of the Contract Act
Fact of the Case:
The petitioner, a joint venture company, participated in a tender issued by SECL. After being awarded the work, the petitioner failed to commence work within the stipulated time and did not submit the required Performance Security Deposit (PSD). The respondent issued a show cause notice and subsequently terminated the contract, forfeited the Earnest Money Deposit (EMD), and imposed a ban and penalty.
Finding of the Court:
The court found that the contract was concluded upon the award of work and that the petitioner's failure to comply with the terms and conditions of the tender and the contract justified the respondent's actions. The court dismissed the writ petition, upholding the termination of the contract and the penalties imposed.
Issues: The key issues were the conclusion of the contract, the petitioner's non-compliance with the tender and contract terms, and the validity of the respondent's actions in terminating the contract and imposing penalties.
Ratio Decidendi: The court held that the contract was concluded upon the award of work, and the petitioner's failure to commence work and submit the required PSD constituted a breach of the contract terms. The court also found that the respondent's actions were justified and in accordance with the terms and conditions of the contract.
Final Decision: The writ petition was dismissed, affirming the termination of the contract, forfeiture of EMD, imposition of a ban and penalty.
ORDER :
Ramesh Sinha, J.
1. Heard Dr. N.K. Shukla, learned Senior Advocate assisted by Mr. Arjit Tiwari, learned counsel for the petitioner. Also heard Ms. Astha Shukla, learned counsel for the respondents.
2. By way of this writ petition the petitioner has prayed for following reliefs:-
10.2 The Hon’ble Court may further kindly be pleased to direct that the order of termination of contract issued by the respondents on 19.06.2021 (Annexure P-7) is quashed.
10.3 The Hon’ble Court may also kindly be pleased to direct the respondents to allow the petitioner to comply the requirements of the contract so that a concluded contract comes into existence and the petitioner be able to commence the work as per the provisions of the NIT, as the petitioner is still interested to commence the work.
10.4 Cost of the petition may also be granted to the petitioner.
10.5 Any other relief which this Hon’ble Court deems fit and proper may also kindly be granted to the petitioner, in the interest of justice.”
3. Brief facts of the case are that, the petitioner is a joint venture company which has been incorporated in order to respond to the notice inviting tender issued by the SECL on 28.06.2020 for "Hiring of HEMM for excavating all kinds of strata / overburden / insitu loading into Tippers, Transportation and unloading of excavated materials & silt, dumping, dozing, scrapping / removal of all bands, preparation / maintenance of haul road, water sprinkling and spreading of material at the site shown in the plan and as per directives of the Management / Engineer in charge of Amlai OC Expansion, Sohagpur Area for Total Quantity: 3,72,98,290 Cum (23,26,609.00Cum-Soft Soil + 3,43,64,912.00Cum-Hard Strata + 6,06,769.00 Cum-Re-handling), Minimum QPD: 25547 Cum, Period: 1460 days". This e-tender notice has been identified by bearing NIT No.SECL/BSP/CMC/e-Tender/407 dated 28.06.2020. Pursuant to the notice inviting tender, the petitioner constituted a joint venture partnership. It is submitted that this joint venture agreement was inconformity with the requirement which is made in the tender notice.
4. The petitioner along with other competitors submitted their bids and the tender evaluation committee found that the bid submitted by the petitioner is lowest (L-1) and therefore on 27.10.2020, the respondents issued letter of intent. It is respectfully submitted that the awarded value of the work was Rs.239,38,18,394.10 including GST @ 18%. Duration for completion of contract work is 1460 days and at the time of submission of bid, the bidder is required to deposit Rs.50 lakhs towards earnest money. The petitioner deposited Rs.50 lakhs towards earnest money. According to the terms and conditions of the notice inviting tender, the successful bidder is required to submit performance guarantee. It is further submitted that even in the letter of intent, it is mentioned that the work shall commence only after submission of performance security and additional performance security, if any.
5. The notice inviting tender is divided in several parts and in one of the parts under the caption of "Instructions to Bidders", there is a provision for performance security/ security deposit at serial No./clause 24. The NIT have several parts and one of the parts is general terms and conditions. Some of the definitions are given in clause 1 under the caption of "Definitions". "Contract" is defined in sub-clause (viii) of clause 1 which says that the 'contract' shall mean the notice inviting Bid, the Bid as accepted by the company and the formal agreement executed between the company and the contractor together with the documents referred to therein including work order, general terms and conditions, special terms and conditions, Additional terms and conditions etc., if any, schedule o
South Eastern Coalfields Limited and others v. S. Kumar’s Associates AKM (JV)
Dresser Rand S.A. v. Bindal Agro Chem Ltd. And Another
Unissi (India) Private Limited v. Post Graduate Institute of Medical Education and Research
Govind Rubber Limited v. Louis Dreyfus Commodities Asia Private Limited
The court emphasized the importance of adhering to contractual procedures and the validity of penalties for non-performance, reinforcing the authority's right to terminate contracts under specified c....
Termination of contract and debarment of a contractor must be in accordance with the terms of the contract and the principles of natural justice, and the work in question must have a public character....
Government Contract – A Letter of Intent (LoL) merely indicates party’s intention to enter into a contract with other party in future and is not intended to bind either party ultimately to enter into....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.