SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2023 Supreme(Raj) 722

IN THE HIGH COURT OF JUDICATURE FOR RAJASTHAN AT JODHPUR
NUPUR BHATI, J.
M/s. Ummed Construction Company, Through Its Proprietor Ummed Bishnoi S/o Shri Teja Ram Ji Bishnoi – Appellant
Versus
State Of Rajasthan – Respondent
S.B. Civil Writ Petition No. 1842 of 2020
Decided on : 11-09-2023

Advocates:
Advocate Appeared:
For the Appellant : Mr. Sajjan Singh Rathore
For the Respondent: Mr. Pankaj Sharma, Mr. Rishi Soni

Headnote:

Constitution of India, 1950 - Article 226, 299 - Bidder - Formal agreement was not executed - By an appropriate writ, order or directions, any NIT if already issued or issued during pendency of writ petition in pursuance to Order for getting remaining work done at risk and cost of petitioner company may kindly be quashed and set aside – Held, Respondents while issuing several notices to petitioner-company placed on record as Annexure-5, granted petitioner various opportunities to complete said work despite fact that period of two months had elapsed way back in month of ‘February, 2019’, but petitioner-company neither respondent any of notices, nor completed said work - This fact also cannot be ignored that respondents had also brought to notice of petitioner-company that upon non-completion of said work, people residing therein, were facing grave hardship, as a regular water supply could be made available, but petitioner-company did not bother and chose not to complete allotted work - Writ petition dismissed.

JUDGMENT :

1. The instant writ petition has been filed by the petitioner-M/s. Ummed Construction Company, through its Proprietor Ummed Bishnoi, under Article 226 of the Constitution of India with the following prayers:-

    “A. By an appropriate writ, order, or directions, the order dated 07.01.2020 (Annex.9), recovery notice dated 28.01.2020 (Annex.11) and any notice, order or communication already passed or passed during pendency of the writ petition in pursuance to the order dated 07.01.2020 (Annex.9) may kindly be quashed and set aside.

B. By an appropriate writ, order or directions, any NIT if already issued or issued during the pendency of the writ petition in pursuance to the Order dated 07.01.2020 (Annex.9) for getting the remaining work done at the risk and cost of the petitioner company may kindly be quashed and set aside.

C. By an appropriate writ, order or directions, the respondents may kindly be directed to execute the agreement/contract in pursuance to the work order dated 15.12.2018 (Annex.2) and also to make available the lay out plans for the awarded work.

D. By an appropriate writ, order or directions, the respondents may kindly be restrained from taking any action against the petitioner company for stopping the work, awarded in pursuance to the order dated 15.12.2018 (Annex.2).”

2. With the consent of learned counsel representing the parties, the matter is heard finally and is being decided today itself.

3. Brief facts of the case are that the petitioner, a proprietor firm, applied in the NIT No.2018-2019/128 for the work of ‘Providing Laying Jointing and Commissioning of various sizes HDPE Pipeline, other allied works under UWSS Sirohi against Old and Polluted Pipe Line.’ The petitioner-company being the lowest bidder, was issued the work order dated 15.12.2018 with a condition that the petitioner-company should execute the formal agreement with a non-judicial stamp of Rs.12,180/-on receipt of this letter and further that the date of commencement of the work will be the date of issuance of the order i.e. 15.12.2018 and the date of completion was the date after two months from the date of commencement, meaning thereby that the petitioner-company was required to complete the said work within a period of two months.

4. In the work order, it was also mentioned that the work is to be started within ten days of the passing of the order or else, it will be get done from the other party at the risk and cost of the petitioner-company. The petitioner-company immediately contacted the office of the respondent-Executive Engineer for execution of formal agreement, but due to unavoidable circumstances and the occupation of the office in some other work, formal agreement was not executed.

5. The petitioner-company started working in pursuance of the work order dated 15.12.2018. The formal agreement was not executed even after about one and a half month and therefore, the petitioner-company stopped the work and requested the respondent to execute the formal agreement.

6. The respondents issued communication dated 07.02.2019 and 14.02.2019 (Annexure-3) to the petitioner-company to complete the work. The petitioner approached the respondents and requested them to execute the formal agreement in order to start the work but no action whatsoever was taken in this regard.

The petitioner-company made a communication dated 12.04.2019 (Annexure-4) to the respondents that the rates which are being reserved are not proper and therefore, the work order may be cancelled. The petitioner-company again started the work upon the assurance of the respondents that soon, the agreement would be executed but when the agreement was not executed, the petitioner-company again stopped the work on 14.06.2019.

7. The petitioner-company was issued several notices dated 16.09.2019, 19.09.2019, 14.10.2019 and 22.10.2019 (Annexure-5), mentioning in it that the pet

      Click Here to Read the rest of this document
      1
      2
      3
      4
      5
      6
      7
      8
      9
      10
      11
      SupremeToday Portrait Ad
      supreme today icon
      logo-black

      An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

      Please visit our Training & Support
      Center or Contact Us for assistance

      qr

      Scan Me!

      India’s Legal research and Law Firm App, Download now!

      For Daily Legal Updates, Join us on :

      whatsapp-icon Back to top