SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2023 Supreme(Cal) 1040

IN THE HIGH COURT AT CALCUTTA
SABYASACHI BHATTACHARYYA, J.

Pearl Corporation - Petitioner
Versus
West Bengal Police Housing and Infrastructure Development Corporation Ltd. (WBPHIDCL) and Others – Respondents
WPO No. 2335 of 2022
Decided On : 05-07-2023

Advocates Appeared:
For the Petitioner: Mr. Tapas Dutta, Mr. M. Halder.
For the Respondents: Mr. Kishore Datta, Mr. Sayan Sinha, Mr. Adil Naseer, Mr. Steven S. Biswas, Mr. Soham Kumar.

Termination of contract and debarment of a contractor must be in accordance with the terms of the contract and the principles of natural justice, and the work in question must have a public character to be justiciable in a judicial review.

Headnote:

CONTRACT TERMINATION - DEBARMENT - MALA FIDE ACTION - NATURAL JUSTICE - CONTRACTUAL PROVISIONS - JUDICIAL REVIEW - PUBLIC CHARACTER OF WORK - DAMAGES:

Fact of the Case:

Petitioner challenges termination of contract and debarment from participating in respondent's contracts for two years, alleging mala fide and arbitrary action, lack of opportunity of hearing, and violation of natural justice.

Finding of the Court:

1. Termination of contract was de hors the contract, as it was effected under Clause 2D, which does not provide for termination, but only for imposition of compensation. 2. Termination was also in violation of natural justice, as it was done before the expiry of the extended completion date. 3. Debarment was also de hors the contract, as it was not done under the relevant provisions of the contract and without giving the petitioner an opportunity of hearing.

Issues: 1. Whether the termination of contract and debarment were mala fide and arbitrary? 2. Whether the termination and debarment violated natural justice? 3. Whether the termination and debarment were de hors the contract? 4. Whether the work in question had a public character, making the termination and debarment justiciable in a judicial review?

Ratio Decidendi: 1. The termination of contract was de hors the contract, as it was effected under a provision that did not provide for termination, but only for imposition of compensation. 2. The termination was also in violation of natural justice, as it was done before the expiry of the extended completion date. 3. The debarment was also de hors the contract, as it was not done under the relevant provisions of the contract and without giving the petitioner an opportunity of hearing. 4. The work in question had a public character, as the respondent authorities discharged public duties, and the basic amenities pertaining to the work were essentially and integrally in public interest.

Final Decision: 1. The termination of contract and debarment were set aside. 2. The petitioner was allowed to participate in future procurement processes, undeterred by the impugned communication. 3. The petitioner was at liberty to approach the competent civil court claiming appropriate damages for the illegal termination. 4. The commencement of the limitation period for filing such suit was deemed to start from the date of the order.

JUDGMENT :

The Court:- 1. The petitioner has challenged the termination of the petitioner and debarment from participating in the respondent’s contracts for two years.

2. Learned counsel for the petitioner submits that the respondents have acted mala fide and arbitrarily. During pendency of a previous writ petition by the petitioner, against the alleged mala fide action of the respondent’s, the respondents terminated the petitioner’s contract. The previous writ petition thus became infructuous and the same was withdrawn with liberty to file a fresh writ petition on the subsequent cause of action. Accordingly, the present writ petition was filed but during the pendency of the same, the remaining work has been given to a third party.

3. It is argued that the petitioner had substantially done the work under the contract between the parties and, if another extension was given, it would have completed the entire work.

4. It is argued that the petitioner was granted extension twice. As such, time was not the essence of the contract even as per the conduct of the respondents.

5. It is next argued that the termination of contract by the respondents was de hors the contract entered into between the parties.

6. Learned counsel places reliance on Clause 2D of the Conditions of Contract which contemplates that the contractor shall be liable to pay compensation if, during review of progress of work as per sub-clause C of Clause 2, it is found that the progress is falling behind schedule as given in the Approved Work Programme, and after the respondents intimating the contractor to expedite the work to achieve the progress.

7. Under sub-clause C, it is submitted that the contractor is to ensure good progress during the execution of the work in all cases in which the time allowed for any work exceeds one month after the Approved Work Programme. In the event of any shortfall in performance measured against the said programme, a penalty has been stipulated in the said Clause.

8. It is argued that the stipulation in the contract speaks about levy of compensation on the petitioner and, as per Clause 3, if the liability to pay compensation amounts to the whole of his security deposit, only then the question of termination of contract arises.

9. In the absence of any such allegation, the termination is bad.

10. It is further argued that, in any event, since the petitioner was on the verge of completion of the work, it would be beneficial for all concerned if the petitioner was given a further opportunity to complete the work, instead of awarding the balance work to a third party.

11. It is argued that although extension of time was given till June 4, 2022, before the expiry of the same, that is, on March 29, 2022, the termination was effected.

12. Hence, the said termination is vitiated due to violation of the principles of natural justice as well as is in contravention of law and the contract between the parties.

13. No proper reason of termination was given by the respondents. Further, it is argued by the petitioner that no opportunity of hearing was given to the petitioner, nor was any show-cause notice issued prior to blacklisting the petitioner. Hence, the termination and the blacklisting ought to be set aside.

14. Learned counsel for the petitioner places reliance on a judgment of the Supreme Court reported at (2018) 6 SCC 157 [Madhya Pradesh Power Management Company Limited Vs. Renew Clean Energy Private Limited and another]. Placing particular reliance on paragraphs 13 and 14 of the same, it is argued that if the contract permits imposition of penalty, the contractor is liable to pay penalty. But the action of termination of the contract was held arbitrary and to have been rightly set aside by the High Court in the said case. Accordingly, in the said case, the Supreme Court awarded penalty and set aside the termination.

15. Learned senior counsel appearing for the respondent-Authorities controverts the petitioner’s submissions and argues th

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top