IN THE HIGH COURT OF CHHATTISGARH AT BILASPUR
GOUTAM BHADURI, RADHAKISHAN AGRAWAL, JJ.
Manish Sharma - Appellant
Versus
Chhattisgarh Housing Board and Ors. - Respondents
MA No. 186 of 2023, MA No. 12 of 2024
Decided On : 03-04-2024
(A) Real Estate (Regulation and Development) Act, 2016 - Sections 18 and 71 - Chhattisgarh Real Estate (Regulation and Development) Rules, 2017 - Rule 17 - Allotment of house - Allottee entitled to refund of amount deposited for superstructure due to failure of promoter to deliver habitable possession - Interest awarded at 10.70% per annum from date of deposit. (Paras 19, 25, 26)
(B) Jurisdiction of RERA - Tribunal exceeded its jurisdiction by framing new issues not pleaded by parties, causing prejudice. (Paras 3, 18)
Facts of the case:
The allottee was allotted a house but found it in dilapidated condition upon taking possession. After multiple complaints and a legal notice, the allottee withdrew from the project and sought a refund. The RERA ordered partial refund and rectification of defects, leading to appeals by both parties.
Findings of Court:
The court held that the allottee is entitled to a full refund of Rs. 36,53,434/- with interest at 10.70% per annum due to the promoter's failure to deliver a habitable house. The Tribunal's order was beyond the pleadings of the parties.
Issues: Whether the court can frame new issues in its judgment that may prejudice the parties?
Ratio Decidendi: The court ruled that the allottee's right to withdraw from the project under Section 18 of the RERA Act was valid, and the Tribunal's findings exceeded the pleadings, thus affecting the rights of the parties.
Result: Appeal by the allottee allowed; appeal by the promoter dismissed.
JUDGMENT :
(Goutam Bhaduri, J.)
Since both the appeals are against the order dated 18-10-2023 passed by the Chhattisgarh Real Estate Appellate Tribunal, Raipur, (henceforth 'the Tribunal') in Appeal No.62 of 2022 arising out of order dated 23-12-2020 passed by the Real Estate Regulatory Authority, Raipur (henceforth 'the RERA') in case No.M-PRO-2020-01048 they are being heard and decided together by this common judgment.
2. MA No. 12 of 2024 is preferred by the Chhattisgarh Housing Board whereas MA No. 186 of 2023 is preferred by Manish Sharma.
3. After hearing the parties, the following question emerges for consideration :
4. (i) Brief facts of the case are that on 10/05/2011 Manish Sharma (henceforth 'the allottee') was allotted a house bearing No.Peepal-I/170 in the scheme of the Chhattisgarh Housing Board (henceforth 'the Board') namely; Peepal-I. Subsequently, on the request of allottee, the house bearing No.Peepal-I/166 was allotted for which extra amount of Rs. 10,000/- was paid as transfer fees. The last installment was demanded on 4-3-2015 and, as such, the total amount of Rs. 36,53,434/- was deposited by the allottee. Subsequently, the lease deed was executed after four years of allotment on 24-9-2015. The allottee was given the possession letter on 23-11-2015. When the allottee went for taking possession of the house, he found that the house was in dilapidated condition, as such, frequent e-mails were sent on different date for rectifying the defects. The Estate Officer of the Board asked the Executive Engineer to rectify the defects and, in turn, inform it to the Board. Thereafter, to the Estate Officer of the Board again e-mail dated 26/11/2015, 2/12/2015, 3/12/2015 & 19/07/2019 were sent. When nothing had transpired, the allottee eventually sent an e-mail dated 20/08/2019 to the Executive Engineer. Thereafter, legal notice was issued by the allottee and lastly a complaint before the RERA was filed on 26-5-2020.
(iii) Subsequently, the order was passed by the RERA on 23-12-2020 wherein it was partly allowed and the amount of Rs. 17,152/- as interest was directed to be returned on payment of advance lease rent and adjustment of advance lease amount computing the lease period from the date of handing over of possession and further the Board was directed to rectify the entire defect and handover possession of the house to the allottee.
(iv) Against the order, the allottee preferred an appeal before the Tribunal wherein the Tribunal by its order dated 18-10-2023 has directed to pay interest at the rate of 10.70% per annum for every month of delay on the amount of Rs. 36,53,500/- from 1-1-2016 till handing over of the possession of the house to the allottee. Aggrieved by such order, both the Board and the Allottee are before this Court.
5. Learned counsel appearing for the Board would submit that once the lease deed having been executed, no return of amount can be ordered for unless the lease is surrendered. He would further submit that as per Sections 18 & 71 of the Real Estate (Regulation and Development) Act, 2016 (henceforth 'the RERA Act') in order to adjudicate the quantum of compensation it is to be decided by the competent authority under the Act, not below the rank of District Judge. He would also submit that since the allottee sought for refund of entire amount that could not be done because lease was existing and
The allottee is entitled to a full refund for the house due to the promoter's failure to deliver a habitable property, with interest at 10.70% per annum.
The judgment established the unconditional right of the allottee to seek refund and the application of promissory estoppel in enforcing promises made by the promoter.
Allottees possess an unqualified right under section 18 of the Act to withdraw from the project and demand refunds if possession is not delivered in accordance with the agreement, emphasizing timely ....
The distinction between refund of amount and compensation under the 2016 Act, and the power of the Regulatory Authority and the Adjudicating Officer to decide such matters.
Private settlements cannot override statutory obligations established by the Real Estate (Regulation and Development) Act, 2016; agreements executed under duress or unfair terms are void.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.