IN THE HIGH COURT OF JUDICATURE AT BOMBAY
M. M. SATHAYE, J.
Linker Shelter Pvt. Ltd. C/o. Paranjape Scheme Construction Limited - Appellant
Versus
Charmaine Chougule - Respondent
Second Appeal No. 391 of 2025 With Interim Application No. 10454 of 2024, SECOND APPEAL NO. 392 OF 2025 WITH INTERIM APPLICATION NO. 3601 OF 2024, SECOND APPEAL NO. 393 OF 2025 WITH INTERIM APPLICATION NO. 12371 OF 2024 WITH SECOND APPEAL NO. 394 OF 2025 WITH INTERIM APPLICATION NO. 13186 OF 2024
Decided on : 18-07-2025
| Table of Content |
|---|
| 1. common case details and refund ordered. (Para 1 , 4) |
| 2. arguments on possession and right to refund. (Para 5 , 6) |
| 3. interpretation of rera provisions. (Para 10 , 18) |
| 4. unqualified right to refund explained. (Para 11 , 12 , 14 , 15) |
| 5. legal provisions relevant to refunds and possession. (Para 19) |
| 6. court's reasoning on the time frame for withdrawal. (Para 32) |
| 7. final order for refund and claims. (Para 36) |
JUDGMENT :
M. M. SATHAYE, J.
1. These four Second Appeals are arising out of common Judgment and Order 30/01/2024 passed by Maharashtra Real Estate Appellate Tribunal, Mumbai (‘the Appellate Tribunal’ for short) in Appeal Nos. AT001000000053706 of 2022, AT001000000053684 of 2022, AT001000000053692 of 2022 and AT001000000053686 of 2022. The Appellant is a common developer. The Respondents are Complainants/Allottees in respect of flat nos. 4E-502, 4H-302, 4C-104 and 4E-504 in project Aaryavarta at Mahale Farm, Off Mumbai-Agra Road, Nashik – 422 009. By the said impugned Order, the common order dated 17/02/2022 passed in 4 complaints filed by Respondent allottees, was set aside and the Appellant/promoter was directed to refund to the Respondents all the amounts including amounts paid for taxes, registration fees etc. with interest from the date of receipt of the amount. It was directed that if there is failure to pay the said amount, the Appellant/Promoter will pay interest on the total outstanding amount as on 29/02/2024 till realization. Charge of this amount is continued on the respective flats till the amounts are refunded.
2. In this judgment, the Real Estate (Regulation and Development) Act, 2016 is referred to as ‘the said Act’. Completion Certificate is referred to as ‘CC’. Occupation Certificate is referred to as ‘OC’. Maharashtra Real Estate Regulatory Authority, Mumbai is referred to as ‘MahaRERA’.
3. By earlier order dated 19/06/2025, following two questions of law were framed by this Court and parties were heard on the said questions of law. Learned counsel for both sides have filed compilation of documents and referred to them. Considering the issues involved, the appeals are admitted on following substantial questions of law and heard finally by consent of parties.
“(A) ‘Whether the allottee, under section 18 of Real Estate (Regulation And Development) Act, 2016, has an unqualified right to withdraw from the project to mean that he can choose to decide withdrawal from project after whatever time he decides at his own will, when possession of a flat/apartment/plot/building with Occupation Certificate is already offered?
(B) Also it needs to be considered whether the possession being offered by the developer alongwith Occupation Certificate (with reference to section 19(10) of the said Act) can only be possession without any litigation over the subject property ?”
4. Few facts necessary for disposal of these Appeals, are as under:
(a) In January 2013 and October 2013 the said 4 flats were agreed to be sold by Appellant in favour of respective Respondents.
(b) The date promised for handing over possession was 31/12/2017.
(c) The Respondents paid various amounts under the agreement to the Appellant.
(d) Some time in 2013, an ex-parte injunction order was passed by this Court and it was served upon the Appellant/Developer in a litigation filed by 3rd party.
(e) By letters dated 22/05/2013, 12/07/2013 and 23/12/2015, the Appellant/Developer informed various developments in the pending litigation to the Respondents/allottees.
(f) Appellant/Developer on 16/02/2016 informed the Respondents that the decision of the Court has come in favour of the Developer.
(g) On 11/07/2018, Occupancy Certificate (‘Occupation Certificate’ or ‘OC’) for the building in which said flats are situated was obtained.
(h) By first letter dated 21/12/2018 the Appellant/Developer specifically informed the Respondents/Allottees that since OC has been obtained, possession of the suit flats can be given and the Respondents/allottees were called upon t
Newtech Promoters & Developers Pvt. Ltd. Vs. State of U.P. & Ors.
Allottees possess an unqualified right under section 18 of the Act to withdraw from the project and demand refunds if possession is not delivered in accordance with the agreement, emphasizing timely ....
The allottee is entitled to a full refund for the house due to the promoter's failure to deliver a habitable property, with interest at 10.70% per annum.
The judgment established the unconditional right of the allottee to seek refund and the application of promissory estoppel in enforcing promises made by the promoter.
Private settlements cannot override statutory obligations established by the Real Estate (Regulation and Development) Act, 2016; agreements executed under duress or unfair terms are void.
The central legal point established in the judgment is that even a promoter who has not received any consideration from an allottee is liable to give a refund with interest under Section 18 of the Re....
Projects receiving partial occupancy certificates prior to enactment are exempt from certain provisions of Real Estate (Regulation and Development) Act.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.