IN THE HIGH COURT OF CHHATTISGARH AT BILASPUR
Goutam Bhaduri, Radhakishan Agrawal, JJ.
Chief Executive Officer, Raipur Development Authority - Appellant
Versus
Anup Kumar Sahu S/o Shri Sewak Ram Sahu - Respondent
MA No. 96 of 2023
Decided On : 17-01-2024
Real Estate - Allotment Dispute - Real Estate (Regulation and Development) Act, 2016, Section 31, Section 58 - The judgment discussed the provisions of Section 18(1)(a) and Section 19(4) of the Act, 2016, Chhattisgarh Real Estate (Regulation and Development) Rules, 2017, and Section 2(za) defining interest. The court also referred to the principle of promissory estoppel and its application in the case.
Fact of the Case:
The respondent filed an application before RERA, Raipur, stating non-receipt of possession of a house despite depositing the amount. The appellant, RDA, attributed the delay to material price increase and pending litigation. RERA dismissed the application, citing delay and non-payment by the allottee. The appellate tribunal directed the return of the deposited amount with interest. The appellant appealed under Section 58 of the Act, 2016.
Finding of the Court:
The court found that the allottee's right to seek refund is unconditional, not dependent on contingencies. It also applied the principle of promissory estoppel, holding the RDA bound by its promise to deliver the house within a reasonable time.
Issues: The issues revolved around delay in possession, increased price demand, and the applicability of Section 18(1)(a) and Section 19(4) of the Act, 2016, along with the Chhattisgarh Real Estate (Regulation and Development) Rules, 2017.
Ratio Decidendi: The court emphasized the unconditional right of the allottee to seek refund and the application of promissory estoppel in enforcing the promise made by the RDA. It also considered the timelines for refund and the rate of interest payable by the promoter to the allottee.
Final Decision: The appeal was dismissed, and the court directed the return of the deposited amount to the allottee.
JUDGMENT :
Goutam Bhaduri, J.
Heard.
1. The present appeal is filed under Section 58 of the Real Estate (Regulation and Development) Act, 2016 (hereinafter referred to as 'the Act, 2016') whereby the order dated 07/03/2023 passed by the Chhattisgarh Real Estate Appellate Tribunal, Raipur, C.G. is under challenge.
2. (I) The facts of the case, in brief, are that the respondent had filed an application before the RERA, Raipur under Section 31 of the Act, 2016 that he was allotted a 2-BHK Duplex Row House bearing House No.C-36A/01 in Section 10 of Kamal Vihar Project, Raipur for an amount of Rs.18,25,000/- on 10/06/2016. The allottee deposited an amount of Rs.18,21,250/- uptill 31/10/2017 but even after four years of filing the application before the RERA, he did not get the possession of the said house. It was further stated that the promoter RDA, by letter dated 27/08/2020 asked the allottee/respondent to deposit an amount of Rs.23,33,963.88/- wherein the GST amount was also shown.
(II) It was the case of the allottee that at the time of purchase of the house though it was stated that it was a tentative price and the actual increase may inflate to 2-3% and demand of GST was not part of the condition but the amount was claimed with an inflated price to the extent of 35% instead of 1-2%. The allottee, therefore, requested to allot the house with an increase of 2% and in alternate requested that he may be allotted a plot in another project known as Indraprastha-2 on the price which was prevailing in the year 2016. It was further stated that if such conditions are not palatable or the RDA was not willing to perform, the entire return of the deposited amount was claimed for.
3. Non-applicant/appellant RDA stated that the allotment of the house was of 10/06/2016 for an amount of Rs.18,25,000/-. Thereafter, because of the increase in material price in the intervening period, by letter dated 27/08/2020 the increased price was asked for. They further stated that the payment of GST was already in the knowledge of the allottee and the increase of price was according to the market rate which was prevailing. It was further stated that they did not have any other plot available for allotment at the prevailing rate of 2016. The delay was attributed for the reason that certain litigation was pending before the National Green Tribunal and the Supreme Court. Thereafter Assembly election followed. Consequently, no development could be carried out in the project and further they stated that till June, 2019 regular development was carried out and they sought for extension of the project time to the State Government. The RDA further stated that if the allottee does not want to purchase the house as per the rules, they are ready to return the amount after the deduction and prays for dismissal of the application.
4. The RERA by order dated 02/01/2021 dismissed the application and held that the increased price would depend on the facts situation of each case and further increase in the price cannot be automatically accepted since there was no agreement executed and it cannot be culled out from the facts that what was the last date for handing over the possession. The learned RERA further observed that according to the declaration filed before the RERA, the project was to be completed by 31/03/2019 and the extension of such time was sought for, which was pending. The RERA further observed that since the allottee failed to deposit the amount he was called upon to deposit by 11/09/2020 and the proceedings were pending before the National Green Tribunal and the Supreme Court from 2013 to 2019 and certain orders were passed as such the delay caused was reasonable and since the allottee himself failed to pay the increased amount, no relief can be granted.
5. Being aggrieved by such order, the allottee preferred an appeal before the C.G. Real Estate Appellate Tribunal, Raipur. The appellate Tribunal by its order dated 07/03/2023 which is under challenge herein direct
Manuelsons Hotels Private Limited Versus State of Kerala and others (2016) 6 SCC 766
The judgment established the unconditional right of the allottee to seek refund and the application of promissory estoppel in enforcing promises made by the promoter.
Refund of advance amount – When major defects are pointed out it is not expected that allottee would be compelled to take house in dilapidated condition which is not habitable, by forfeiting his righ....
The central legal point established in the judgment is the entitlement of the allottee to a refund of the amount deposited for the superstructure/house under the provisions of the RERA Act, emphasizi....
The allottee is entitled to a full refund for the house due to the promoter's failure to deliver a habitable property, with interest at 10.70% per annum.
The Real Estate Regulation and Development Act applies to ongoing projects and governs existing agreements. Prescribed interest rates do not override the Act's provisions.
The main legal point established is that the Real Estate Regulation & Development Act, 2016 operates retrospectively, and the levy of interest for delay is compensatory in nature, aligning with the r....
Private settlements cannot override statutory obligations established by the Real Estate (Regulation and Development) Act, 2016; agreements executed under duress or unfair terms are void.
Section 37 provides that K-RERA for the purpose of discharging its functions under the provisions of Act or Rules or Regulations can issue directions from time to time to promoters allottees or real ....
The Real Estate (Regulation and Development) Act, 2016 provides distinct remedies for refund and compensation, and the unqualified right of an allottee to get a refund of the amount deposited with th....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.