High Court Of Delhi
M.L.MAHAJAN - Appellant
Versus
DELHI DEVELOPMENT AUTHORITY - Respondent
Decided On : 04/24/2002
( 1 ) IN this appeal M/s. M. L. Mahajan (hereinafter referred as the Contractor) has assailed the judgment of the learned Single Judge dated 20/07/1990 whereby the award of a sum of Rs. 2,21,600. 00 in respect of Claim No. 20 (which was for a total sum of rs. 4,60,000/-) had been set aside. This Claim was lodged on account of the alleged rise in the market price beyond the stipulated date of completion. The appellant/contractor has prayed that the Award dated 15. 9. 87, in respect of Claim No. 20, be made rule of the court and that interest thereon at the rate of 18% per annum from the date of the Award till the date of the payment be also granted along with costs. The facts in brief are that the Contractor was awarded the work of construction of 40 MIG/lig and 20 Janata Houses at dilshad Garden, Group A, Pocket II, Delhi, vide letter dated 25. 3. 1977. Thereafter an Agreement bearing No. 6/hd/xix/76-77 dated 31. 3. 1977 was executed between the parties. The work was to commence on 4. 4. 1977 and was to be completed by 3. 8. 1978, i. e. 16 months. As it transpired, the project was completed as late as in august 1980, i. e. after a delay of approximately 24 months.
( 2 ) THE Contractor invoked arbitration by his letter dated 29. 9. 1982. After one year, the Engineer member of the DDA appointed Shri R. L. Hans, S. E. DDA, as the Arbitrator who however, resigned in December, 1985. Thereafter, the Engineer Member, DDA, in terms of his letter dated 9. 1. 1986, appointed Shri G. R. Hingorani, Chief Engineer, DDA, as the Arbitrator and referred to him the 24 Claims raised by the Contractor. The Arbitrator made and published his Award on 15. 9. 1987. He disallowed the Claims 3,6,7,9 to 18, 21 to 24. In other words, out of 24 Claims only seven were allowed in varying amounts. Under Claim No. 1 an amount of Rs. 54,279. 00 was awarded, although Rs. 1,20,000. 00 was claimed; under Claim No. 2, for the release of Bank guarantee, was allowed; under Claim No. 4 an amount of rs. 8250/- was awarded against the claim of rs. 16,500/-; under Claim No. 5, an amount of Rs. 5,380. 00 was awarded against the claim of Rs. 45,000. 00; under claim No. 8 an amount of Rs. 3,938. 00 was awarded against rs. 4000/-; under Claim No. 19 a sum of Rs. 9000. 00 was awarded for keeping the Bank Guarantee alive beyond the stipulated date of completion. Interest at the rate of 18% was awarded from 29. 9. 1982 upto the date of payment or decree whichever was earlier. As has already been indicated above, in this Appeal the Contractor has only prayed for the restoration of the sum of Rs. 2,21,600. 00 awarded in Claim No. 20 i. e. "on account of rise in the market price beyond the stipulated date of completion. "
( 3 ) THE Arbitrator has dealt with Claim No. 20 in the following words :
"claim No. 20 for Rs. 4,60,000. 00 on account of rise in market price beyond stipulated date of completion. The work was started on 4. 4. 1977 and stipulated date of completion was 3. 8. 1978. The claimant has stated that the completion was delayed mainly on account of respondents delays in (a) giving decisions and designs. (b) issuing cement. As regards (a) he referred to ex. C-18,19,20,21,22,23 and 46 none of which were controverted by the respondent. As regards (b), he referred to Ex. C-24,25,18,26 none of which were controverted. In fact the respondent has admitted (C-27) that materials are being supplied as and when available in D. D. A. Stores. As the work has been delayed due to defaults of D. D. A. the contractor is entitled to compensation due to rise in prices for which he had claimed 10% extra in 1978 (C-49 ). He has now claimed 20% extra on the basis of increase in C. P. W. D. cost index of buildings from 100 (1-10-1976) TO 157 (On 10. 4. 1980 ). The value of work done after 3. 8. 1978 was as under : 247. htm from the above it is clear that the Arbitrator s finding was that the delay was due to the default of the DDA. These are findings of fact which would normal
REFERRED TO : Om Parkash Baldev Krishan, New Delhi V. Union of India and another
Des Raj and Sons V. Union of India
Rawla Construction Co. Vs. UOI.
Metro Electric Co. New Delhi V. DDA
Rawla Construction Co. V. Union of India
Hyderabad Municipal Corporation V. M.Krishnaswami Mudaliar and another
Uttam Singh Duggal and Co. V. Union of India
Villayati Ram Mittal V. Union of India
Himachal Pradesh Nagar Vikas Pradhikaran V. Aggarwal and Co.
SupremeToday
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.