1998 Supreme(Del) 417

High Court Of Delhi
KOCHHAR CONSTRUCTION WORKS - Appellant
Versus
DELHI DEVELOPMENT AUTHORITY - Respondent
Suit 2039 of 1994
Decided On : 05/22/1998

Advocates Appeared:
R.Rajappa, V.K.Sharma

Headnote:Arbitration Act, 1940 - Section 30 & 33 — Award in excess of jurisdiction — Permissibility — The arbitrator being a creator of agreement must operate within the four corners of agreement.

       Held :

       It is axiomatic that the arbitrator being creature of the agreement must operate within the four comers of the agreement and cannot travel beyond it. The arbitrator had to follow the limits set for him and the court can find that he exceeded his jurisdiction on proof of such excess. There are two different and distinct grounds involved in many such cases. One is the error apparent on the face of the record and the other is that the arbitrator exceeded his jurisdiction. In the latter case, the courts can look into the arbitration agreement but in the former, it cannot, unless the agreement was incorporated or recited in the award.

       In case the arbitrator is acting within the four comers of the agreement and does not exceed his jurisdiction he may himself judge the quality as well as quantity of the evidence and he may also act upon certain estimates about the market value based on his experience who would know and have means of knowing about the market rates. To this extent the Court is supposed to accept and respect his views irrespective of the fact that whether he has disclosed the rates or not in the award.

       Section 30 & 33 — Reasoned award — Detailed revision — Necessity of — Arbitrator is not expected to right a detailed Judgment and the Court cannot prove into his thought process to discover a mistake not apparent on the face of award.

       A reasoned award must disclose some intelligible reasons dealing with substantial points raised before the arbitrator as well as intimating some nexus between the material on record and the conclusions arrived at by the arbitrator to indicate trend of thought process, mental meanderings need not be referred to nor he is required to give detailed reasons as judges do. "Die question of sufficiency or lack of sufficiency of reasons depends on facts of the particular case. As regards giving actual calculations incoming to the conclusion of awarding a certain amount there appears some light conflict in the opinions but a slight in depth study indicates that there may be none.

       Even an arbitrator commits a mistake either in law or fact but such mistake does not appear on the face of the award or in a document appended to or incorporated in it so as to form part of it, the award would neither be remediad nor set aside notwithstanding the mistake

       If the arbitrator decides a dispute which is beyond the scope of reference or beyond the subject matter of the reference or he makes an award disregarding the team of the agreement or terms of the contract, it would be a jurisdictional error beyond the scope of reference and he cannot clothe himself to decide conclusively that dispute as it is an error of jurisdiction which is to be ultimately decided by the court. In the matter of challenge to the award, if there are two distinct and different grounds, namely that there is an error apparent on the face of the record and that the ar-bitrator has exceeded his jurisdiction. The arbitrator, while deciding the admitted dispute, in the latter case, the court can look into the arbitration agreement but under the former it cannot do so unless particular point or clause of the agreement was incorporated or cited in the award or evidence was made part of the agreement. In the case of jurisdictional error, "...there is no embargo on the power of the court to admit the contract into the evidence and to consider whether or not the umpire had exceeded the jurisdiction because of nature of the dispute is something which has to be determined, outside the award, whatever might be said about in the award or by the arbitrator. In the case of non-speaking award, it is not open to the court to go into the merits. Only in a speaking award, the court can look into the reasoning in the award and correct wrong proposition of law or error of law. It is not open to court to probe the mental process of the arbitrator and speculate when no reasons have been given by the arbitrator as to what impelled the arbitrator to arrive at his conclusion. But in case pf exceeding the jurisdiction, the court, with reference to the terms of contract/arbitration agreement, would consider whether or not the arbitrator/umpire has exceeded his jurisdiction in awarding or refusing to award the sum of money awarded or omitted a consolidated lump sum."

S. N. Kapoor, J.

( 1 ) THE petitioner M/s Kochhar Construction Works filed a petition under Sections 14, 17 and 29 of the Arbitration Act, 1940 for filing the award given by Shri K. K. Reddy dated 29th August 1994 and making it rule of the court.

( 2 ) DELHI Development Authority, the respondent filed objection against the award vide IA 1858/95.

( 3 ) RELEVANT facts in brief are as follows: The petitioner entered into a contract with the respondent No. 1 for the work of construction of 84 LIG DUS at D-1/c Janak Puri, New Delhi vide agreement No. 73/ee/hdvii/81-82. Certain disputes arose and in terms of the arbitration clause, the matter was REFERRED TO to Shri K. K. Reddy who gave the award.

( 4 ) THE award is being challenged by the objectors DDA basically on the ground that learned Arbitrator has only indicated conclusions reached by him and failed to give any reasons or to disclose his thought process or the basis for awarding various amounts in respect of claim No. 1 (items 2,3 and 4) and claim Nos. 8, 9 and 10

( 5 ) BEFORE proceeding further and considering individual claims, the relevant part of clause 25 of the agreement is being reproduced for proper appreciation. It reads as under:

IN all cases where the amount of claim in dispute is Rs. 50,000. 00 (Rupees fifty thousand) and above, the arbitrator will give reasons for the award. "

( 6 ) THIS very clause as well as similar clauses came to be interpreted time and again in numerous cases as REFERRED TO to by learned counsel for parties. Learned counsel for the petitioner relies upon following judgments:

1. Kochhar Construction Works Vs. Delhi Development Authority, Suit No. 2009/94 decided on 5th February 1996.

2. Naraindas R. Israni Vs. Union of India, 1993 (1) ALR 233.

3. Goa Daman and Diu Housing Board Vs. Ramakant V. P. Darvotkar, AIR 1991 SC 2089.

4. MCD Vs. Jagan Nath Ashok Kumar and Anr. , AIR 1987 SC 2316.

( 7 ) LEARNED counsel for the objector relies upon:

1. Ashok Ohri Vs. DDA, 1997 (1) ALR 181 2. NDR Isarani Vs. Delhi Development Authority, Suit No. 2501a/87 decided on 28th January 1992. 3. College of Vocational Studies Vs. S. S. Jaitley, AIR 1987 Del 134. 4. M/s Anant Raj Agencies Vs. DDA, Suit No. 2341a/86 decided on 13th July 1989. 5. New India Civil Erectors (P) Ltd. Vs. ONGC, JT 1997 (2) SC 633 = (1997) 11 SCC 75.

( 8 ) DECIDING arbitration matters sometimes may amount to walking on razor s edge as would be evident herein after. There is a duty cast on the court that the court should not unnecessarily try to find fault with the award and should lean to a limited extent in favour of upholding the award and at the same time it is the duty of the court to ensure that the arbitrator does not exceed the limit set by the arbitration agreement.

( 9 ) IT is axiomatic that the arbitrator being creature of the agreement must operate within the four corners of the agreement and cannot travel beyond it. The arbitrator had to follow the limits set for him and the court can find that he exceeded his jurisdiction on proof of such excess. There are two different and distinct grounds involved in many such cases. One is the error apparent on the face of the record and the other is that the arbitrator exceeded his jurisdiction. In the latter case, the courts can look into the arbitration agreement but in the former, it cannot, unless the agreement was incorporated or recited in the award (See New India Civil Erectors (P) Ltd. Vs. ONGC, (supra) (para 9 and 11 ). The arbitrator being sole judge of the quality and quantity of evidence, it would be unwise for the court to take upon itself the task of being a judge on the evidence before the arbitrator for appraisement of the evidence by the arbitrator is never a matter which the court should question and consider. The court is also not required to consider the reasonableness of reasons (see FCI Vs. Jagan Pal, AIR 1989 SC 1263 ). ( 10 ) IN Goa Daman and Diu Housing Board Vs. Ramakant V. P. Darvotkar, (supra) the objection in conside