High Court Of Delhi
MALTEXMALSTERS PRIVATE LIMITED - Appellant
Versus
ALLIED ENGINEERS - Respondent
C.M. 801 of 1974
Decided On : 03/17/1975
{'KEYWORD': 'ARBITRATION', 'SUBJECT': 'Arbitration Agreement - Filing and Appointment of Arbitrator', 'ACT SECTION LIST': ['Section 20', 'Section 33', 'Section 36', 'Section 39', 'Section 149'], 'SUMMARY': 'The Delhi High Court addressed the issue of whether an arbitration agreement should be filed and an arbitrator appointed in a dispute between parties who had entered into an agreement for the construction of a building. The court considered the jurisdiction of courts in Delhi and Patiala, the effect of a previous application filed under Section 33 of the Arbitration Act, and the validity of the arbitration clause in the agreement.'}
Fact of the Case:
The appellant, Maltex Malsters Private Limited, and the respondent, Allied Engineers, entered into an agreement for the construction of a building in Patiala. Disputes arose between the parties, and the respondent applied under Section 20 of the Arbitration Act for an order to make a reference to arbitration. The appellant contested the application on several grounds, including lack of jurisdiction and the existence of a pending application under Section 33 filed by them at Patiala.
Finding of the Court:
The Delhi High Court held that the courts at Delhi had jurisdiction to try the dispute and that the application was not liable to be stayed in view of the previous application filed by the appellant at Patiala. The court also found that there was a valid arbitration agreement between the parties and that the disputes fell within the scope of the arbitration clause. The court directed the agreement to be filed and appointed a sole arbitrator to decide the disputes.
Issues: 1. Whether the courts at Delhi had jurisdiction to try the application? 2. Whether the application was liable to be stayed under Sections 10 and 151 of the Code of Civil Procedure? 3. Whether there was an arbitration agreement between the parties? If so, whether there were existing disputes which could be referred to arbitration? 4. What was the effect of the suit filed by the petitioner against the respondent at Patiala on the arbitration agreement?
Ratio Decidendi: 1. The court held that as the agreement was executed in Delhi and the building was constructed at Patiala, courts at both places had jurisdiction to try the dispute arising out of the agreement, but as clause (8) of the agreement specifically provided that courts at Delhi alone will have jurisdiction, Delhi courts alone could try the application. 2. The court held that the institution of the suits by the respondent at Patiala made no difference in view of the said clause (8) of the agreement. 3. The court held that there was a dispute between the parties that was covered by the arbitration clause and, therefore, directed the agreement to be filed and appointed a sole arbitrator to decide them.
Final Decision: The Delhi High Court dismissed the appeal and upheld the order of the learned single Judge directing that the arbitration agreement be filed and the dispute between the parties be decided by a sole arbitrator.
( 1 ) THIS appeal under Section 39 of the Arbitration Act, 1940 (hereafter called "the Act") is directed against the order of the learned single Judge of this Court dated March 11, 1974 directing that the arbitration agreement between the parties be filed and the dispute between them be decided by a sole arbitrator.
RESPONDENT, M/s. Allied Engineers, is a firm of Engineers. As per terms of the agreement dated January 20, 1969, they agreed to erect a building at Patiala for the appellant, M/s. Maltex Malsters Private Limited. The appellant is referred to in the. agreement as employer and the respondent as contractors . According to clause 33 of the Articles of Agreement, the respondent-contractor was to be paid by the Employer from time to time by instalments under interim certificates to be issued by the Architect to be appointed in terms of the agreement for the works executed when in the opinion of the Architect work to the approximate value had been done in accordance with the contract. Clause 35 provides that decision, opinion, direction and certificate of the Architect with respect to matters covered by this clause were final and conclusive. Clause 36 then sets out the arbitration clause according to which all differences and disputes between the parties falling within it had to be referred to arbitration in terms of the clause.
( 2 ) DISPUTES arose between the parties and on failure of the appellant to refer the same to arbitration, in October, 1971 the respondents applied under section 20 of the Arbitration Act (hereafter called "the Act") for an order of the court to make a reference to arbitration according to the arbitration clause. The appellant contested the application on several grounds. Amongst others, they maintained that the courts at Delhi had no jurisdiction to try the application and that in any case the application was liable to be stayed in view of a previous application filed by them at Patiala under section 33 of the Arbitration Act. The learned single Judge framed the following issues: (1) Whether this Court has jurisdiction to hear the application? (2) Whether this petition is liable to be stayed under sections 10 and 151 of the Code of Civil Procedure? (3) Whether there is an arbitration agreement between the parties ? If so, whether there are existing disputes which can be referred to arbitration ? (4) What is the effect of the suit filed by the petitioner against the respondent at Patiala on the arbitration agreement? (5) Relief.
( 3 ) ISSUES I and 2 were treated as preliminary issues and were decided by order dated February 13, 1974 and the application was directed to be tried on merits. Evidence of the parties was taken by affidavits and on this evidence the other issues were also decided against the appellant by order dated March II, 1974. It appears that during trial the appellants also applied for permission to lead oral and documentary evidence to substantiate the issues and this application was also dismissed on March II, 1974 but by a separate order.
( 4 ) ON issues 1, 2 and 4 the learned single Judge held that as the agreement was executed in Delhi and the building in pursuance of the agreement was constructed at Patiala, courts at both the places had jurisdiction to try the dispute arising out of the agreement but as clause (8) of the agreement specifically provided that courts at Delhi alone will have jurisdiction, Delhi courts alone could try the application and the question of its stay because of the pending application under section 33 filed by the appellant at Patiala did not arise. The institution of the suits by the respondent at Patiala, it was held, made no difference in view of the said clause (8) of the agreement. On issue No. 3, the learned single Judge held that there was a dispute between the parties that was covered by the arbitration clause and, therefore, directed the agreement to be filed and appointed Professor C. H. S. Jhabavala as sole arbitrator to
REFERRED TO : Monnan Lal v. Mst. Chhotka Bibi
Custodian of Evacuee Property, New Delhi v. Rameshwar Dayal and others
Brij Lal and Co. v. Madhya Pradesh Electricity Board
Indian Express Newspapers (Bombay) v. Basumati Private Ltd.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.