SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2008 Supreme(Del) 851

HIGH COURT OF DELHI
THE HONOURABLE DR. JUSTICE S. MURALIDHAR
Himachal Joint Venture
Versus
Panilpina World Transport
FAO (OS) Appeal No. 123 of 2008
Date of Judgment : 08-08-2008

Advocates appeared:
For the Appearing Parties:Jasmeet Singh, Kiran Suri, Sandeep Sethi, Advocates.

Headnote:Arbitration and Conciliation Act, 1996

       Section 34 - Objection to award--It is not believable that the claimant agreed verbally to terminate the contract particularly when the claimant had made elaborate arrangement for the execution of contract--No credence can be attached to the verbal statement of respondents witness in the absence of any documentary evidence--View taken by the Arbitrator is plausible view and it is not permissible for this Court to interfere with the Arbitrators view merely because another view of the matter is possible--Appeal dismissed.

JUDGMENT :-

(1) AGGRIEVED by the judgment and order dated 11th January, 2008 of the learned single Judge dismissing the appellant's petition under Section 34 of the Arbitration and Conciliation Act, 1996, the appellant has preferred the instant appeal seeking reversal thereof.

(2) THE facts leading to this appeal are that the appellant was desirous of importing Tunnel Boring Machine ("tbm" in short) with backup system and associated equipments from Malm, Norway and Bilbao/spain to Adit-II site of Parbati PB-2 Project site at District Kullu, Himachal Pradesh. The respondent being a leading company in the field of International Freight forwarding with expertise in the movement of such type of heavy machinery submitted its quotations for executing the aforesaid shipment. After discussion and deliberations, revised quotations were submitted. After the preparatory action and submission of offer by the respondent, the appellant issued Letter of Intent on 25th June, 2003. Formal agreement was executed on 15th July, 2003 at Delhi. After signing of the agreement dated 15th July, 2003, certain differences occurred between the parties owing to which the contract was eventually terminated on 2nd August, 2003.

(3) THE disputes between the parties resulting from the termination of the contract were referred to arbitration. This Court vide order dated 15th march, 2004 appointed Justice Usha Mehra (Retd.) as the sole Arbitrator to resolve the disputes between the parties. The respondent filed a statement of claim before the learned Arbitrator in the sum of Rs. 10,00,000/- towards cost incurred and for a sum of Rs. 28,28,024/- (10% of the total contract value)as damages along with interest on the total sum @ 24% per annum. In response, the appellant filed its reply to the statement of claims and filed its statement of counter-claims against the respondent.

(4) THE case of the respondent before the Arbitration was that the appellant had unilaterally terminated the contract dated 15th July, 2003 as a result of which it had to suffer huge costs and losses. It was alleged that the termination of contract by the appellant was not only illegal but also vitiated by mala fide inasmuch as the appellant wanted to award the contract of transportation to some other freight forwarder by the name of m/s Jai Hind Roadways. Per contra, the case of the appellant before the arbitrator was that the respondent had tried to make an unlawful gain at the cost of the

appellant. It was contended that whereas it was always understood between the parties that the loading and stuffing of cargo would entail no extra cost for the appellant, however, the respondent eventually made an unlawful and unreasonable demand for a lump sum amount of NOK 7,40,000. it was submitted that owing to the fundamental breach of the contract dated 15th July, 2003 by the respondent, the said contract was mutually terminated by the parties. An objection to the jurisdiction of the arbitration was also raised on the ground that the claims of the claimant are not within the scope of Arbitration Clause No. 8 of the contract.

(5) THE sole Arbitrator upon hearing the rival contentions of the parties and upon examination of the evidence on record, decided the issue of jurisdiction and maintainability in favour of the respondent vide order dated 1st March, 2006. The other issues qua termination of the contract were decided in favour of the respondent vide award dated 4th January, 2007.

(6) IT is seen from the judgment of the learned single Judge that the award was challenged by the appellant mainly on the following grounds:

(1) Firstly, that the impugned award deals with a dispute not contemplated and not falling within the terms of the submission to arbitration. Thus, inasmuch as the contract was not performed at all, there was no question of execution of the contract at all, and therefore, the disputes were not within the scope of the Arbitration Clause. The arbitral award is accordingly liable to b



















Click Here to Read the rest of this document

1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top