2009 Supreme(Del) 1097
IN THE HIGH COURT OF DELHI AT NEW DELHI
HONBLE MR. JUSTICE MANMOHAN, J.
ANANT RAJ AGENCIES ..... Petitioner
Versus
D.D.A & ANR. ….Respondents
CS(OS) 2204A/1995 & I.A. 7897/1996
Decided on : 15th October, 2009
Subject
Arbitration Law - AWARD
Act Referred
Headnote
Mr. Harish Malhotra, Senior Advocate with Mr. N.K. Kantawala, Mr. Priyank Sharma & Mr. Satyender, Advocates.
Mr. Ajay Verma, Advocate.
MANMOHAN, J: (Oral)
1. Present petition has been filed under Sections 30 and 33 of Indian Arbitration Act, 1940 (hereinafter referred to as “Act, 1940”) raising objections to the Award dated 3rd September, 1995 made and published by Mr. K.D. Bali, Sole Arbitrator. By way of this petition, objector-respondent-DDA has challenged the said Arbitrator’s Award to the extent it awards Claims No. 2 to 6, 8 to 13 and 16.
2. Mr. Ajay Verma, learned counsel for respondent-DDA stated that the Arbitrator had erroneously awarded Rs. 13,41,591.66 under Claim No. 2 on account of infructuous expenditure. He submitted that the said Award was in excess of jurisdiction and contrary to Clause No. 1 of additional specifications read with Clauses 5, 10, 10CC of General Conditions of Contract. The said clauses are reproduced hereinbelow for ready reference :-
“CLAUSE 5. If the contractor shall desire an extension of time for completion of the work on the grounds of his having been unavoidably hindered in its execution or any other ground, he shall apply in writing to the Engineer-in-Charge within 30 days of the date of hindrance on account of which he desires such extension as aforesaid and the Engineer-in-Charge shall, if in his opinion (which shall be final) reasonable grounds be shown thereof, authorise such extension of time if any, as may in his opinion necessary or proper. xxxxx xxxxx xxxxx CLAUSE 10. Stores supplied by Delhi Development Authority:- If the specification of schedule of items provides for the use of any special description of materials to be supplied from Engineer-in-Charge’s stores or if it is required that the contractor shall use certain stores to be provided by the Engineer-in-Charge as shown in the schedule of materials hereto annexed, the contractor shall be bound to procure and shall be supplied, such materials and stores, as are from time to time required to be used by him for the purposes of the contract only, and the value of the full quantity of materials and stores so supplied at the rates specified in the said schedule of materials may be set off deducted from any sums then due, or thereafter to become due to the contractor under the contract, or other-wise or against or from the security deposit, or the proceeds of sale thereof if the same is held in Govt. Securities, the same or a sufficient portion thereof being in this case sold for the purpose…………..
Provided that the contractor shall in no case be entitled to any compensation or damages on account of any delay in supply or non-supply thereof all or any such materials and stores. Provided further that the contractor shall be bound to execute the entire work if the materials are supplied by the DDA within the schedule time for completion of the work plus 50% thereof (Schedule time plus 6 months if the time of completion of the exceed 12 months) but if a part only of the materials has been supplied within the aforesaid period then the contractor shall be bound to do so much of the work as may be possible with the materials and stores supplied in the aforesaid period or the completion of the rest of the work, the contractor shall be entitled to such extension of times as may be determined by the Engineer-in-Charge, whose decision in this regard shall be final. xxxxx xxxxx xxxxx CLAUSE 10CC. If the prices of materials (not being materials supplied of services rendered at fixed prices by the department in accordance with Clauses 10 & 34 hereof) and/or wages of labour required for execution of the work increases, the contractor shall be compensated for such increase as per provisions detailed below and the amount of the contract shall accordingly be varied, subject to the condition that such compensation for escalation in prices shall be available only for the work done during the stipulated period of the contract including such period for which the contract is validity extended under the provisions of clause 5 of the contract without any action un