SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2015 Supreme(Del) 940

DELHI HIGH COURT
RAJIV SAHAI ENDLAW, J.
National Highways Authority of India – Appellant
Vs.
Oriental Structural Engineers Private Limited – Respondent
O.M.P. No. 1640 of 2014
Decided On : 16.1.2015

The main legal point established in the judgment is that the scope of judicial review of an arbitral award is limited and does not extend to re-evaluating the facts and evidence considered by the arbitrators.

Headnote:

Arbitration and Conciliation Act - Setting Aside of Arbitral Award - Section 34

Fact of the Case:

The petitioner sought setting aside of the arbitral award on various grounds including wrongful interpretation of the contract, double payment to the respondent, and excessive interest rates. The respondent had filed claims against the petitioner for various amounts related to construction works under a contract.

Finding of the Court:

The Court dismissed the petition, stating that the grounds for challenging the arbitral award did not fall within the ambit of Section 34(2) of the Arbitration Act. The Court emphasized that the scope of judicial review of an arbitral award is limited and does not extend to re-evaluating the facts and evidence considered by the arbitrators.

Issues: The issues included wrongful interpretation of the contract, double payment, excessive interest rates, and failure to comply with contractual obligations.

Ratio Decidendi: The Court held that the grounds for challenging the arbitral award did not meet the criteria set out in Section 34(2) of the Arbitration Act. The Court emphasized that the scope of judicial review of an arbitral award is limited and does not extend to re-evaluating the facts and evidence considered by the arbitrators.

Final Decision: The petition seeking setting aside of the arbitral award was dismissed by the Court.

ORDER

1. This petition, under Section 34 of the Arbitration and Conciliation Act, 1996, seeks setting aside of the unanimous arbitral Award dated 22.8.2014, of the Arbitral Tribunal comprising of a nominee of the petitioner and the nominee of the respondent and a presiding Arbitrator of the choice of the nominees of the two parties, to the extent the same allows the Claims Nos. 2 to 6 of the respondent against the petitioner (Claim No. 1 of the respondent against the petitioner was disallowed).

2. The petition came up before the Court first on 22.12.2014 when after hearing extensively the senior counsel for the petitioner, orders were reserved.

3. The arbitral award emanates from the claims of the respondent against the petitioner under the contract dated 29.9.2005 for a price of Rs. 115,24,02,683/- between the parties for construction by the respondent of New Four Lane Jhansi Bypass on National Highway 25 in the State of Uttar Pradesh for the petitioner, with the stipulated date of start as 21.11.2005 and the stipulated date of completion as 20.5.2008. The works were however completed only on 31.8.2010.

4. The petitioner seeks setting aside of the arbitral award to the extent:-

(i) It allows the Claim No. 2 of the respondent in the sum of Rs. 89,66,783/- with interest for wrongful certification of Bills of Quantity for construction of reinforced earth, pre-cast concrete facia panel, RCC crash barrier etc. for the period till 31st August, 2010 and holds the respondent entitled to further sums on similar basis for period subsequent to 31st August, 2010 and till final account in respect of wrong quantification.

(ii) It allows Claim No. 3 of the respondent in the sum of Rs. 30,65,779/- towards delay till 31st August, 2010 in payments of the admitted amounts.

(iii) It allows Claim No. 4 of the respondent in the sum of Rs. 3,21,64,657/- for non-payment of price adjustment upto 31st August, 2010 and in a sum of Rs. 60,87,471/- towards interest thereon till 31st August, 2010 and further finds the respondent entitled to payment of correct quantification of price adjustment in subsequent IPCs till final account, together with interest thereon.

(iv) It allows Claim No. 5 of the respondent in the sum of Rs. 16,09,647/- towards additional cost due to increase in royalty on various minerals for the quantities executed till February, 2010 with interest alias 10% compounded monthly from 9th March, 2010 till the completion of the work and simple interest alias 10% per annum including on compound interest aforesaid, from 1st September, 2010 till the date of actual payment.

(v) It allows Claim No. 6 of the respondent in the sum of Rs. 2,68,69,295/- on account of price escalation till 31st August, 2010 and in a sum of Rs. 48,29,367/- towards interest alias 10% per annum thereon compounded monthly and simple interest alias 10% per annum from 1st September, 2010 till the date of actual payment.

5. The petitioner seeks setting aside of the said arbitral award on the grounds of:

(a) The Arbitral Tribunal having wrongly read the Contract between the parties to conclude that certain works required to be carried out were not part of the Contract when in fact as per the Contract they were not to be measured separately and were to be deemed to be incidental to the work under the Contract.

(b) Allowing of certain claims of the respondent by the Arbitral Tribunal amounting to the respondent being paid twice for the same work.

(c) The delays in payment of the admitted amounts by the petitioner to the respondent being on account of the respondent failing to comply with the obligations it was required to comply with before receiving payment and the petitioner being thus not liable to pay interest and the Arbitral Tribunal having wrongly concluded that the petitioner had delayed the payment.

(d) The Arbitral Tribunal having not considered that the respondent had not sought any clarification to the addendum/corrigendum of the pre-bid meeting, thereby impliedly accepting
























































Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top