DELHI HIGH COURT
V. Kameswar Rao, J.
TRG Industries Pvt. Ltd. - Appellant
Versus
N.H.P.C Ltd. - Resopndent
O.M.P. 294/2006
Decided On : 18-02-2015
Award - Construction Contract - Indian Arbitration Act, 1940, Indian Arbitration & Conciliation Act, 1996 - Section 30, Section 33 - Waiver of interest, Idle charges - Clause 13, Clause 14.1, Clause 18, Clause 39.2 - The court discussed the waiver of interest and idle charges under the construction contract, and the applicability of the Indian Arbitration Act, 1940 and the Indian Arbitration & Conciliation Act, 1996. The court highlighted the interpretation of various clauses of the contract and the impact of novation of the agreement on the claims made by the petitioner. The court also considered the conduct of the parties and the doctrine of waiver in reaching its decision.
Fact of the Case:
The petitioner entered into a construction contract with the respondent for a hydroelectric project. The petitioner claimed damages due to delay in providing the site for work, while the respondent argued that a supplemental agreement modified the scope of work, leading to novation of the contract.
Finding of the Court:
The court found that the claims of the petitioner were rightly dismissed by the arbitrator. The court analyzed the conduct of the parties, the impact of the supplemental agreement, and the applicability of the Indian Arbitration Act, 1940 and the Indian Arbitration & Conciliation Act, 1996 in reaching its decision.
Issues: The issues involved waiver of interest, idle charges, novation of contract, and the applicability of the Indian Arbitration Act, 1940 and the Indian Arbitration & Conciliation Act, 1996.
Ratio Decidendi: The court held that the conduct of the parties, the impact of the supplemental agreement, and the interpretation of the contract clauses were crucial in determining the outcome of the case. The court also emphasized the doctrine of waiver and the applicability of the arbitration acts.
Final Decision: The court dismissed the petition, upholding the decision of the arbitrator and finding no grounds for interference with the award.
V. Kameswar Rao, J.:--
1. The challenge in this petition is to the Award dated March 24, 2006, whereby the learned Arbitrator has dismissed the claims made by the petitioner herein.
Facts
2. On January 20, 1985 a notice inviting tender for the work of construction of Garrage Head Regulator and other appurtenant works for Tanakpur Hydroelectric Project situated in the state of Uttar Pradesh (now Uttranchal) was issued by the respondent corporation. The petitioner submitted its tender on April 22, 1985 which was accepted and a letter of intent (LOI) was issued on October 15, 1985 followed by letter of award dated December 26, 1985. A formal agreement was executed between the parties on February 05, 1986. The terms of contract stipulated that the petitioner was to commence the works within 30 days after issuance of letter of award. Any failure on the part of the petitioner would have also led to cancellation of project and forfeiture of money. Clause 13 of the Contract stipulated for grant of mobilization advance upto a maximum limit of 5% of the contract value, which was interest bearing recoverable advance. The Contract also provided for interest bearing recoverable advance upto maximum of 10% for construction plants and equipments.
3. The petitioner in total obtained an amount of Rs. 1,77,61,764/- from the respondent pursuant to this clause in the Contract.
4. It was the case of the petitioner before the learned Arbitrator that immediately after the issuance of letter of award, a site office was set up on November 15, 1985 and with a right earnest to commence the work mobilized its resources, machinery and plant from different work sites within and outside the State, major part of which came from its work of Hydroelectric Project, Salal, J&K.
5. The case of the petitioner was also that despite insisting upon the officer of the respondent of their obligation to make available site so as to enable it to set up crushing plant, offices, stores, mechanical work shop, labour huts, staff quarters etc., the respondent failed to provide the site for the purpose. Only a small fraction was provided. In the absence of the site and the respondent not getting clearance of various authorities, the work was seriously hampered and could be commenced only in late November, 1986 when an area of 96 hectares was handed over to the petitioner by the respondent.
6. It was its case that for the period during which the labour and machinery remained idle due to non-availability of site and also for the damages suffered by it, the petitioner raised disputes as per the terms of the agreement between the parties. A reference was made and the respondent appointed a learned Arbitrator, who was to make an award on the following issues:-
(i) Waiver of interest till November 15, 1986 on mobilization, machinery and equipment advance.
(ii) Idle charges of machinery and manpower from November 15, 1985 to November 15, 1986.
7. The first Arbitrator could not conclude the arbitration proceedings due to his untimely death. The vacancy was filled by a new Arbitrator, who made an award dated January 31, 1995 and the same was filed in this Court for making Rule of the Court.
8. It is noted that both the parties were aggrieved by the Award and filed their respective objections under Sections 30 & 33 of the Indian Arbitration Act, 1940. When the objections came up for hearing before the learned Single Judge on December 20, 2000, the learned Single judge after noting that both the parties are aggrieved by the Award and none of them has prayed for making the award Rule of the Court, was of the view that the best course was to set aside the award and to make appointment of another Arbitrator to resolve the disputes raised by the parties.
9. Mr. Justice, N.C. Kochhar (Retired) was appointed as a Sole Arbitrator, who entered reference.
10. When the proceedings were at the arguments stage, Justice Kochhar unfortunately expired, which resulted filing of an application under Section
Chairman and MD, NTPC Ltd. v. Reshmi Constructions, Builders & Contractors
Continental Construction Ltd. v. State of U.P.
H.P. State Electricity Board v. R.J. Shah
Hind Constructions v. State of Maharashtra
J.G. Engineers Pvt. Ltd. v. Union of India and Another
McDermott International Inc. v. Burn Standard Co. Ltd.
Numaligarh Refinery Limited v. Daelim Industrial Company Limited
P.R. Shah, Shares and Stock Brokers Pvt. Ltd. v. B.H.H. Securities Pvt. Ltd. and others
Pure Helium India (P) Ltd. v. ONGC
Puri Constructions (P) Ltd. v. UOI
SAIL v. Gupta Brothers Steels Ltd.
State of Rajasthan v. Puri Constructions Ltd.
State of U.P. v. Allied Constructions
Steel Authority Ltd. v. Gupta Brothers Steel Tubes Ltd.
Sudarsan Trading Company v. Government of Kerala
Sumitomo Heavy Industries Ltd. v. Oil and Natural Gas Corporation Ltd.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.