2018 Supreme(Del) 396
IN THE HIGH COURT OF DELHI AT NEW DELHI
PRATHIBA M. SINGH, J.
North Delhi Municipal Corporation & Anr. – Appellants
Versus
Raj Rani – Respondent
RFA 558 of 2017& CM APPL. 21042 of 2017 (Stay)
Decided On : 22-03-2018
Important Points
Act Referred
CONSTITUTION OF INDIA : Art.12, Art.14
CONTRACT ACT : S.46, S.19(a), S.16(1), S.23, S.16(2)
COURT FEES ACT : S.16
SPECIFIC RELIEF ACT : S.31(3)
Headnote
The Court held that the clauses in the General Conditions of Contract which stipulated that the payment of bills would depend on the availability of funds in a particular head of account from time to time in MCD and that no interest would be payable to the contractor in case of delay in payment on account of non-availability of funds in the particular head of account of MCD were illegal and contrary to law. The Court further held that the security deposit was refundable upon the fulfilment of the conditions contained in Clauses 17 and 45 of the General Conditions of Contract and that interest would be payable on delayed payments.
Fact of the Case:
The facts of the case are that the Contractors had filed suits against the Corporations for recovery of dues under work orders. The Corporations relied on Clauses 7 and 9 of the General Conditions of Contract, which stipulated that the payment of bills would depend on the availability of funds in a particular head of account from time to time in MCD and that no interest would be payable to the contractor in case of delay in payment on account of non-availability of funds in the particular head of account of MCD. The Contractors argued that these clauses were illegal and contrary to law.
Finding of the Court:
The Court held that the clauses in the General Conditions of Contract which stipulated that the payment of bills would depend on the availability of funds in a particular head of account from time to time in MCD and that no interest would be payable to the contractor in case of delay in payment on account of non-availability of funds in the particular head of account of MCD were illegal and contrary to law. The Court further held that the security deposit was refundable upon the fulfilment of the conditions contained in Clauses 17 and 45 of the General Conditions of Contract and that interest would be payable on delayed payments.
Issues: The issues before the Court were: (i) Whether the clauses in the General Conditions of Contract which stipulated that the payment of bills would depend on the availability of funds in a particular head of account from time to time in MCD and that no interest would be payable to the contractor in case of delay in payment on account of non-availability of funds in the particular head of account of MCD were illegal and contrary to law. (ii) Whether the security deposit was refundable upon the fulfilment of the conditions contained in Clauses 17 and 45 of the General Conditions of Contract. (iii) Whether interest was payable on delayed payments.
Ratio Decidendi: The Court held that the clauses in the General Conditions of Contract which stipulated that the payment of bills would depend on the availability of funds in a particular head of account from time to time in MCD and that no interest would be payable to the contractor in case of delay in payment on account of non-availability of funds in the particular head of account of MCD were illegal and contrary to law. The Court further held that the security deposit was refundable upon the fulfilment of the conditions contained in Clauses 17 and 45 of the General Conditions of Contract and that interest would be payable on delayed payments. The Court reasoned that the clauses were illegal and contrary to law because they were unconscionable and unreasonable. The Court also reasoned that the security deposit was refundable upon the fulfilment of the conditions contained in Clauses 17 and 45 of the General Conditions of Contract because these clauses were clear and unambiguous.
Final Decision: The Court held that the clauses in the General Conditions of Contract which stipulated that the payment of bills would depend on the availability of funds in a particular head of account from time to time in MCD and that no interest would be payable to the contractor in case of delay in payment on account of non-availability of funds in the particular head of account of MCD were illegal and contrary to law. The Court further held that the security deposit was refundable upon the fulfilment of the conditions contained in Clauses 17 and 45 of the General Conditions of Contract and that interest would be payable on delayed payments. The Court decreed the suits filed by the Contractors.
For the Appellant :Ms. Renu Gupta, Advocate
For the Respondent:Mr. Vinay Kumar, Advocate
Prathiba M. Singh, J.
1. These are a batch of appeals which have arisen out of disputes between Contractors/Plaintiffs (hereinafter, ‘Contractors’) on the one hand and the North Delhi Municipal Corporation (hereinafter, ‘NrDMC’) and East Delhi Municipal Corporation (hereinafter, ‘EDMC’), on the other. NrDMC and EDMC are collectively referred to as ‘Corporations'. The facts in each appeal are different and hence separate judgments are being passed in each of the appeals.
2. Briefly, these are cases where various work orders were placed on Contractors by both the Corporations. The works were executed by the Contractors and thereafter, the Engineer-in-Charge has passed the final bills. Payments in respect thereof were not made. Suits for recovery were filed by the Contractors. The Trial Court decreed the suits in favour of the Contractors.
3. In respect of each of the work orders, the Contractors seek either/all of the following payments:
(a). Payment of the principal amount as passed in the final bill;
(b). Refund of security deposit;
(c). Interest on account of late payment of the principal amount, as also due to delay in refund of security deposit.
4. The Corporations rely on Clauses 7 and 9 of the General Conditions of Contract in respect of payment of principal amount and interest, read with the amendment of 19th May, 2006. In respect of the security deposit, the Corporations rely on Clauses 17 and 45 of the General Conditions of Contract for Municipal Corporation of Delhi Works (hereinafter, ‘General Conditions of Contract’). In addition, the Corporations also rely upon Circular dated 10th June 2014 signed by the Chief Engineer, MCD which was issued in the nature of a clarification. The questions that have arisen in all these cases are -
(i) Whether payment of the principal amount can be delayed in view of Clause 7 and Clause 9 of the General Conditions of Contract read with the amendments?
(ii) Whether the refund of earnest money/security deposit can be delayed in view of Clauses 17 and 45 of the General Conditions of Contract?
(iii) Whether interest is payable on delayed payments/refunds and if so, for which period?
5. Arguments have been addressed by Mr. Sunil Goel and Ms. Mini Pushkarna on behalf of the Corporations - NrDMC and EDMC, respectively. On behalf of the Contractors in some matters, Mr. Vinay Kumar has made submissions.
Background of the Case
6. In the present case, two work orders no. 443 and 263 for a sum of Rs.5,65,418/- and Rs. 3,59,160/-, respectively, were placed on the Contractor. The Contractor pleads that it had completed the work before the stipulated time and there was no negative remark. The final bills were passed by the Engineer-in-Charge on 30th March, 2015 and 30th March, 2015, respectively and were recorded in the measurement book as well. The Contractor had also deposited two amounts of Rs.69,883/- and Rs.47,357/- towards the security deposit qua each work order. Though, the bills were passed by the Engineer-in-Charge, the payments were not made. Accordingly notice dated 6th January, 2016 was issued by the Contractor to the Corporation claiming the following amounts:
| Sr. No. | Work Order No. | Amount of passed (first and final) bill in Rs. | Date of passing of bill | Amount of Security deposit/earnest money amount in Rs. |
| 1. | 443 | 454904.00 | 30.03.2015 | 69883.00 |
| 2. | 263 | 289187.00 | 30.03.2015 | 47357.00 |
|
| Total | 744091.00 |
| 117240.00 |
| Grand Total of passed bills and security amounts | 744091 +117240 | 861331.00 | ||
7. Since no payment was made, suit for recovery came to be filed. In the suit, the Contractor prayed for payment of principal amount, refund of security deposit and interest on delayed payments. In the written statement, the Corporation pleaded as under:
“There is a specif