2018 Supreme(Del) 416
IN THE HIGH COURT OF DELHI AT NEW DELHI
NAVIN CHAWLA, J.
UNION OF INDIA & ORS. – Appellant
Versus
GARG ASSOCIATES - Respondent
OMP (COMM) 229 of 2016 & IAs 13462-63 of 2017
Decided on : 23-04-2018
Act Referred
ARBITRATION AND CONCILIATION ACT : S.31, S.34(2), S.31(7), S.34
CONSTITUTION OF INDIA : Art.142
CONTRACT LABOUR REGULATION AND ABOLITION ACT : .
CONTRACT LABOUR REGULATION AND ABOLITION CENTRAL RULES : .
Headnote
Arbitration - Arbitration Award - Arbitration and Conciliation Act, 1996 - Section 31 - Order dated 17th April, 2015 and Arbitral Award dated 19th May, 2015 - [CHALLENGE] - [MODERNIZATION OF SENA BHAWAN, NEW DELHI] - [Section 31 of the Arbitration and Conciliation Act, 1996] - The court set aside the Arbitration Award in favor of the respondent under Claim Nos. 3 and 6, but allowed interest at the rate of 9% per annum for the pre-reference period on the delayed payments under Claim No. 6. The petition was partly allowed and the parties were to bear their respective costs of the proceedings.
Fact of the Case:
The petitioner challenged the order dated 17th April, 2015 and the Arbitral Award dated 19th May, 2015, which awarded certain claims in favor of the respondent. The disputes arose from the modernization of Sena Bhawan, New Delhi, and were referred to arbitration by a Sole Arbitrator. The petitioner argued that the alleged 'joint report' was not a joint report at all and that the Arbitrator had completely misdirected himself in relying upon the document as a settlement. The petitioner also challenged the award of a sum of Rs.54,14,475/- in favor of the respondent under Claim No.5 on account of revision in the minimum wages of labor based on Clause 10(C) of the agreement. The petitioner further challenged the award of interest in favor of the respondent under Claim no. 6 and the award of an amount of Rs.18,48,000/- in favor of the respondent under Claim No. 8 as expenditure incurred on the salaries of the supervisory and supporting staff as well as on idle T & P over a period of 28 months on account of prolongation of contract.
Finding of the Court:
The court set aside the Arbitration Award in favor of the respondent under Claim Nos. 3 and 6, but allowed interest at the rate of 9% per annum for the pre-reference period on the delayed payments under Claim No. 6. The petition was partly allowed and the parties were to bear their respective costs of the proceedings.
Issues: The issues included the challenge to the alleged 'joint report', the award of a sum of Rs.54,14,475/- in favor of the respondent under Claim No.5, the award of interest in favor of the respondent under Claim no. 6, and the award of an amount of Rs.18,48,000/- in favor of the respondent under Claim No. 8.
Ratio Decidendi: The Arbitration Award in favor of the respondent under Claim Nos. 3 and 6 was set aside, but interest at the rate of 9% per annum for the pre-reference period on the delayed payments under Claim No. 6 was allowed. The court partly allowed the petition and the parties were to bear their respective costs of the proceedings.
Final Decision: The Arbitration Award in favor of the respondent under Claim Nos. 3 and 6 was set aside, but interest at the rate of 9% per annum for the pre-reference period on the delayed payments under Claim No. 6 was allowed. The petition was partly allowed and the parties were to bear their respective costs of the proceedings.
Advocate Appeared:
For the Appellant : Mr.Kirtiman Singh, CGSC with Mr.Shailendra Kr. Mishra, Mr.Waize ali Noor, Mr.Prateek Dhanda and Mr.Saeed Qadari, Advs. Along with Mr.Anil Mehta, Ex. Engineer (Retd.)
For the Respondent: Mr.Raman Kapur, Sr. Adv. with Mr.R.P.Singh, Mr. Dhiraj Sachdeva, Advs.
1. The present petition has been filed by the petitioner challenging the order dated 17th April, 2015 and the Arbitral Award dated 19th May, 2015 passed by the Sole Arbitrator awarding certain claims in favour of the respondent.
2. At the outset, it is noted that the order dated 17th April, 2015 was merely an order passed in the course of the arbitration proceedings and is not an Arbitral Award in terms of Section 31 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the ‘Act’). However, the said order, as would be evident from the discussion below, is intrinsically linked with the Impugned Arbitral Award dated 19th May, 2015 as the award, to a large extent is based on this order and so is equally the challenge thereto by the petitioner.
3. The brief factual background leading up to the Impugned Arbitral Award is noted as under:-
4. The petitioner had issued a Letter of Acceptance dated 26th July, 2008 awarding the tender for the work of modernization of Sena Bhawan, New Delhi to the respondent. The stipulated date for completion of the work was 6th February, 2010. The work was actually completed on 15th June, 2012. There were disputes between the parties on the reason for the delay and consequent claims of the respondent. The said disputes were referred to arbitration by a Sole Arbitrator, vide order dated 22nd April, 2014 passed by this Court in Arbitration Petition No.480/2013.
5. Upon completion of the pleadings, the Arbitrator commenced hearing of the oral submissions on 8th January, 2015. The claimant /respondent concluded its arguments on that date. On 5th February, 2015, the petitioner herein commenced its arguments. The order passed on 5th February, 2015 records the objection of the petitioner herein to various claims raised by the respondent. As far as claim no.3, which is with respect to extra items, substituted items and deviated items beyond deviation limit, the order records that the respondent has withdrawn its claim in respect of extra items indicated in Para A of its Claim no.3 at page 7 of its rejoinder to the reply of the petitioner. As far as Claim no.4 is concerned, which was for the amounts withheld by the petitioner, the Arbitrator, after recording the submissions of the parties, further recorded as under:-
“The parties have agreed to undertake a joint inspection of the defects in items of work listed out in the S.E’s letter and reconcile the gaps in their claims and file a joint report before the next date of hearing. In case the Respondent succeeds in convincing the Claimant that certain defects were not rectified, the Respondent would be entitled to deduct proportionate amount from the withheld amount and release the balance sum. However, if it is found during the inspection that the Claimant had attended to all the defects, it may be entitled to receive the balance amount. This exercise should be completed within two weeks and a joint report submitted to the Tribunal.”
6. As far as Claim no.5, which is a Claim under clause 10 (C) of the agreement for payment on account of increase in prices /wages due to statutory order(s), the parties agreed to further deliberate on the issue and work out the labour element required in each sub-component of the project and revise the claim accordingly. Two weeks’ time was given to the parties to report the result of such an exercise. The parties further agreed that as far as Claim nos.7, 8, 9 and 10 are concerned, the same would have to be decided by the Arbitrator.
7. I have given a reference to the above order in detail as there is some dispute between the parties as to whether they had arrived at any settlement with respect to claim nos.3 and 5.
8. By the subsequent order dated 5th March, 2015, the parties reported that they had done the joint inspection and found that except for deduction in respect of water proofing, the other amoun