SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2021 Supreme(Del) 257

IN THE HIGH COURT OF DELHI
VIBHU BAKHRU, J.
Shapoorji Pallonji & Co. Pvt. Ltd. – Petitioner
Versus
The Indure Private Limited & Another – Respondent
O.M.P.(I)(COMM.). No. 430 of 2020 & I.A. No. 1604 of 2021
Decided On : 08-02-2021

Advocate Appeared:
For the Petitioner:Manik Dogra, Animesh Sinha, Omung Gupta, Siddharth Dey, Dhruv Pande, Advocates.
For the Respondents:Prashant Mehta, Varun Gupta, Simran Wason, Divita Vyas, Advocates.

Exceptional cases of egregious fraud, irretrievable injustice, and special equities are required to restrain the encashment of a bank guarantee, which must be performed on its own terms.

Headnote:

Bank Guarantee - Arbitration and Conciliation - Section 9 of the Arbitration and Conciliation Act, 1996 - 9, 17, 37 - The court discussed the provisions of Section 9 of the Arbitration and Conciliation Act, 1996 and the legal principles related to interdicting unconditional bank guarantees. The court highlighted the requirement for exceptional cases of egregious fraud, irretrievable injustice, and special equities to restrain the encashment of a bank guarantee. It referenced key legal provisions from Svenska Handelsbanken v. Indian Charge Chrome, Larson & Toubro Ltd. v. Maharashtra SEB, Hindustan Construction Co. Ltd. v State of Bihar & Ors., and U.P State Sugar Corporation v Sumac International Limited to support its decision.

Fact of the Case:

The petitioner filed a petition under Section 9 of the Arbitration and Conciliation Act, 1996, seeking the return of an original bank guarantee and an order restraining the respondent from invoking and encashing the bank guarantee. The disputes arose from a work order issued by the respondent to complete civil work, with the respondent claiming that the petitioner neglected to perform the contract and incurred extra costs.

Finding of the Court:

The court found that the invocation of the bank guarantee cannot be restrained as none of the grounds for interjecting the bank guarantee, such as fraud or irretrievable injustice, were established. The court also declined the petitioner's request for an order restraining the respondent from transferring or dealing with its assets.

Issues: The issues involved the petitioner's request to restrain the respondent from invoking and encashing the bank guarantee, as well as the petitioner's plea for an order restraining the respondent from transferring or dealing with its assets.

Ratio Decidendi: The court held that exceptional cases of egregious fraud, irretrievable injustice, and special equities are required to restrain the encashment of a bank guarantee. It emphasized that a bank guarantee is a separate contract and must be performed on its own terms.

Final Decision: The petition was disposed of, and the court declined to grant an order restraining the encashment of the bank guarantee or restraining the respondent from transferring or dealing with its assets.

JUDGMENT :

1. The petitioner has filed the present petition under Section 9 of the Arbitration and Conciliation Act, 1996 (hereafter “the A&C Act”), inter alia, praying that direction be issued to respondent no.1 (hereafter “Indure”) to return the original Advance cum Performance Bank Guarantee No. 171020261470-AA, dated 04.02.2010 (hereafter “the PBG”) as extended from time to time. The petitioner also seeks an order restraining Indure from invoking and encashing the said bank guarantee. It is further prayed that respondent no.2 (Standard Chartered Bank – hereafter ‘the Bank’) be restrained from acting on any letter seeking extension or encashing the PBG.

2. The disputes between the parties arose in connection with a Work Order dated 20.11.2009, issued by Indure to complete the civil work at RRVUNL- Chhabra T.P.P - 2 x 250 MW-Unit# 4, CHP & BOP (hereafter “the Contract”) .

3. It is Indure’s case that the petitioner neglected to perform the Contract and failed to complete the work within the stipulated time. Indure further claims that it had from time to time highlighted the slow progress of work performance on part of the petitioner, however, the petitioner had completed only a small fraction of the Contract awarded to it. Indure claims that as a consequence of the petitioner’s deficiency in performing the contract, it had to incur extra cost to complete the work. Indure claims that the petitioner must bear the additional costs in terms of the Contract. Indure further claims that it is also entitled to recover damages on account of breach on the part of the petitioner in performing the Contract.

4. Mr Mehta, the learned counsel appearing for the respondents referred to a letter dated 20.12.2017, whereby Indure had made claims aggregating Rs. 35,63,92,989.44 and called upon the petitioner to pay the same within a period of seven days from the date of receipt of the said notice.

5. Mr. Dogra, learned counsel appearing for the petitioner, submits that the claims made by Indure are unsustainable apart from being barred by limitation. He submits that even without going into the merits of the claims made by Indure, it is apparent that the PBG has been invoked only on the basis that it was not being extended. And, the said premise is wholly erroneous.

6. Mr Dogra referred a letter dated 01.12.2020 addressed by Indure to the Bank stating that the said letter be treated as a notice for invocation of the PBG. However, the said letter also states that in the event, PBG is extended for six months and the Original Bank Guarantee Extension Advice is received by the Bank, the claim may be treated as withdrawn, otherwise its claim stands and the amount equivalent to Rs.4 crores be remitted in favour of Indure. He states that the petitioner complied with the said demand and by a letter dated 19.12.2020 – which was prior to the expiry of the term of the PBG confirmed the extension as demanded by Indure. He submits that since the petitioner had complied with the demand of extension made by the Indure, it is not open for the respondent to insist that PBG be encashed.

7. Mr Mehta countered the aforesaid submissions. He states that the letter dated 01.12.2020 was issued as a matter of usual procedure followed by Indure. He states that as a matter of practice, Indure issues such letters in respect of all bank guarantees, at the beginning of the month in which the bank guarantees are to expire. He states that since PBG was valid till 31.12.2020, Indure sent a letter dated 01.12.2020 seeking extension of the PBG. He submits that the said demand was not complied with and the Bank did not send the Original Bank Guarantee Extension Advice immediately, as requested by Indure. In the circumstances, Indure, after examining the matter, invoked the PBG by a letter dated 16.12.2020. He points out that the extension advice was furnished only after the PBG was invoked.

8. He further submitted that the invocation of the PBG was deferred as the parties were attempting to

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top