IN THE HIGH COURT OF DELHI AT NEW DELHI
MANMOHAN, DINESH KUMAR SHARMA, JJ.
Delhi Development Authority - Appellant
Versus
M/S Eros Resorts And Hotels Ltd - Respondent
FAO (OS) (COMM) 75 of 2022
Decided on : 07-04-2022
Arbitration and Conciliation Act, 1996 – Section 37 (1) (c) - Commercial Courts, Commercial Division and Commercial Appellate Division of the High Courts Act, 2015 - Section 13 - Arbitral Award - Claim - Public notice issued by appellant for auction of plots for construction of hotels in Delhi, respondent submitted its bid and was awarded contract for Hotel Plot nos. 13 A and 13 B located at District Centre, Mayur Vihar, Centre, - Possession of the plots was handed over to respondent with stipulation that work was to be completed - However, work actually completed - Work related to project was pertaining to Commonwealth Games and was considered to be a project of national significance - Parties agreed to general terms and conditions of auction which were part of auction notice - Whether, within this limited jurisdiction, case of appellant is sufficient to exercise that jurisdiction.
Finding of the Court:
Arbitral award would indicate that learned Arbitrator had minutely examined delay in completion of hotel project and reached a finding that delay was attributable to DDA - Findings of Arbitral Tribunal were based on material placed by parties - Finding of Arbitral Tribunal was duly upheld by learned Single Judge - Arbitral Tribunal had also rejected contentions of appellant that clause 3.14 of General Terms and Conditions of auction referred to damages - Arbitral Tribunal held that it referred to impost as a penalty for delay in completion of hotel - Court do not find any patent illegality or violation of fundamental policy of India in conclusion arrived at by Arbitral Tribunal and which has been upheld by learned Single Judge – Court consider that appellant has miserably failed to make out any case to interfere with order of learned Single Judge.
Result: Appeal dismissed
JUDGMENT :
DINESH KUMAR SHARMA, J
C.M.No. 14983/2022
Exemption allowed, subject to all just exceptions. Accordingly, the application stands disposed of.
FAO (OS) (COMM) 75/2022
1. The present appeal under Section 13 of the Commercial Courts, Commercial Division and Commercial Appellate Division of the High Courts Act, 2015 read with Section 37 (1) (c) of the Arbitration and Conciliation Act, 1996 (hereinafter referred as ‘Act’) has arisen out of the impugned order dated 22nd March 2021 in OMP (COMM) No. 455 of 2019 passed by learned Single Bench under Section 34 of the said Act. In the impugned order, the learned Single Judge has upheld the award of the Arbitral Tribunal pertaining to claim no. 1, however, the Tribunal set aside the award pertaining to claim No.2. It is pertinent to mention that the Arbitral Tribunal had rejected claim nos. 3 and 4 made by the respondents and rejected all the counterclaims raised by the appellant.
2. Short of the details, the facts in brief are that pursuant to a public notice issued by the appellant for auction of plots for the construction of hotels in Delhi, respondent submitted its bid and was awarded contract for the Hotel Plot nos. 13 A and 13 B located at District Centre, Mayur Vihar, Centre, New Delhi. The possession of the plots was handed over to the respondent on 5th December 2006 with the stipulation that work was to be completed on 5th June, 2010. However, the work actually completed on 20th December, 2010. The work related to the project was pertaining to Commonwealth Games and was considered to be a project of national significance. The parties agreed to the general terms and conditions of the auction which were part of the auction notice. Clause – 3.14 of the general terms and conditions which is germane to the present controversy reads as under;
| SI. No. | Delay Period beyond 42 months | Penalty Amount |
| 1 | Above 1 day and upto 30 days | 1% of the Bid amount |
| 2 | Above 31 days and upto 90 days | 2% of the Bid amount |
| 3 | Above 91 day s and upto 180 days | 4% of the Bid amount |
| 4 | Above 181 days and upto 365 days | 5% of the Bid amount |
3. In accordance with the terms of the clause – 3.14 of general terms and conditions of the auction, respondent furnished the performance bank guarantee which was duly accepted by the appellant. Subsequent to the issuance of the No Objection Certificate by the DDA (Appellant) on 9th November, 2006, the respondent submitted building plans to DDA for approval on 4th December, 2006. The possession was handed over by the appellant to the respondent on 5th December, 2006 and as per the terms and conditions respondent was required to complete and make the hotel functional by 5th June, 2010 i.e. within 42 months of the delivery of possession of plots. Though, the appellant granted permission for escalation work in respect of plot nos. 13 A and 13 B to the respondent vide communication dated 22nd December, 2006, but imposed a condition
Associate Builders v. Delhi Development Authority: (2015) 3 SCC 49
Dyna Technologies (P) Ltd. v. Crompton Greaves Ltd.
MMTC Limited vs. Vedanta Limited (2019) 4 SCC 163
Arbitration Award - Merely because the arbitrator has taken a view that is plausible and there may be another view also, the award cannot be interfered with.
The main legal point established in the judgment is the interpretation of contract terms, breach of contract, and the limited scope of interference with the arbitrator's award based on the violation ....
Clauses in contracts that prohibit claims for damages are against public policy and void under Section 23 of the Indian Contract Act, 1872, as they undermine the sanctity of contracts.
Arbitration - Arbitral Award - Form and contents of arbitral award - DDA issued a public notice for Auction of prime plots on freehold basis for construction of Hotels in Delhi - The mandate under Se....
The Court's power while exercising jurisdiction under Section 37 of the Act is limited, and it cannot undertake an independent assessment on the merits of the Award.
The appellate jurisdiction under section 37 is limited to the grounds prescribed under section 34. Courts cannot re-appreciate evidence or substitute their views for that of the arbitrator, provided ....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.