IN THE HIGH COURT OF DELHI AT NEW DELHI
Vibhu Bakhru, J.
Union Of India - Appellant
Versus
Om Vajrakaya Construction Company - Respondent
Original Miscellaneous Petition (COMM) No. 299 of 2021, Miscellaneous Application No. 12966 of 2021
Decided On : 20-12-2021
Arbitration and Conciliation Act - Railway - 34 - The impugned award awarded pendente lite and future interest at the rate of 9% per annum. The Arbitral Tribunal found that OVC was not responsible for the delays and awarded costs of the arbitral proceedings. The impugned award to the extent it awards pendente lite interest, is set aside.
Fact of the Case:
The Railway filed a petition under Section 34 of the Arbitration and Conciliation Act, 1996, impugning an arbitral award. The disputes arose between the parties in relation to a contract signed for a project. The Arbitral Tribunal accepted certain claims made by OVC and awarded a sum along with interest and arbitration cost. The Railway challenged the award.
Finding of the Court:
The court set aside the award of pendente lite interest, finding it contrary to the express provisions of the contract. The court upheld the Arbitral Tribunal's finding that OVC was not responsible for the delays and the award of costs, as it was a well-considered view.
Issues: The issues included the award of interest, responsibility for delays, and the award of costs.
Ratio Decidendi: The court found that the award of pendente lite interest was contrary to the contract and set it aside. The court upheld the Arbitral Tribunal's finding that OVC was not responsible for the delays and the award of costs.
Final Decision: The impugned award to the extent it awards pendente lite interest, is set aside. The petition is disposed of in the aforesaid terms.
JUDGMENT
Vibhu Bakhru, J. - The petitioner (hereinafter the Railway) has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter the A&C Act) impugning an arbitral award dated 08.04.2020 (hereinafter the impugned award) passed by the Arbitral Tribunal constituted by Justice (Retd.) Anil Kumar as the Sole Arbitrator (hereinafter the Arbitral Tribunal).
2. The impugned award was rendered in the context of disputes that have arisen between the parties in relation to a contract signed between the parties on 16.12.2011 (hereafter the Contract).
Factual Matrix
3. On 13.01.2011, tenders were invited by the Railway for work described as Earth work in filling for embankment with contractors own earth and cutting to the required profile , Blanketing materials including compaction by vibratory roller, construction/extension of minor bridges less than 6.00 m, retaining wall and other allied works from Ch 0.00 km to Ch 22.71 kms between Ambala Cantt- Dhappar railway Stations in connection with Ambala-Dhappar doubling on UMB-KLK Section, with the overall supervisory control of the Dy. Chief Engineer/C Ambala, Northern Railway. (hereafter the Project).
4. Pursuant to the said tender, the respondent firm (hereafter OVC) submitted its bid. The same was accepted and by a Letter of Acceptance dated 07.04.2011 (hereafter the LoA), the work was awarded to OVC. The period of completion of the works was stipulated to be eighteen months and was required to be completed by 06.10.2012. The Contract with respect to the said work was finally signed on 16.12.2011.
5. OVC claims that after the award of the works, the Railway advised it to deploy its machinery, staff, labour and construct the site office(s) as per the tender stipulations for expeditious execution of the works within the stipulated time. However, the arrangements made by OVC at the site remained unutilized due to non-availability of drawings, site for execution, cutting of trees, non-sanctioning of Engineering Scale Plan (ESP) etc.
6. Despite, OVCs repeated efforts to execute the works, no progress was made as the trees causing hinderances were not removed and full site was not made available to OVC. Thereafter, OVC sent several letters to the Railway requesting it to supply a complete set of drawings, remove the ESP of Dhappar, Lallru and Dhoulkot stations and, to remove the trees at the railway track at Lallru station; however, the said letters did not elicit any satisfactory response.
7. Due to addition in the scope of work and the various hindrances in executing the works, the Railway extended the date of completion of the works to 30.10.2014, without levy of any penalties.
8. Thereafter, on 08.08.2013, one of the constituent partners of OVC expired in a road accident and OVC requested the Railway to treat the work as closed. OVC requested the Railway to prepare the Final Bill along with the extra items executed at the site on the instructions of the supervisory staff. OVC claimed that it was assured that the extra items would be paid along with the Final Bill at an early date along with the earnest money, Performance Guarantee and security deposit.
9. The work was finally treated as satisfactorily completed on 15.10.2014 and thereafter, a Completion Certificate was issued and the Performance Guarantee furnished by OVC was released.
10. OVC states that the Railway had assured it that it would settle all disputes at the time of finalization of the Final Bill. However, the Railway failed to include some of OVCs claims in the Final Bill. OVC claims that it was directed to accept the Final Bill prepared by the Railway without any protest and, to tender its No Claim Certificate failing which the admitted amounts due would not be released.
11. OVC had requested the Railway to prepare the Final Bill on 18.11.2014. However, the Final Bill was prepared after a pe
Union of India v Bright Power Projects India P Ltd: (2015) 9 SCC 695
The court upheld the principle that the award of interest and costs in arbitration proceedings should be in accordance with the contract and the provisions of the Arbitration and Conciliation Act, 19....
The Arbitral Tribunal's awards of costs and findings on execution delays were upheld, but the award of pendente lite interest was set aside for being contrary to the governing contractual provisions.
The court upheld the learned Single Judge's ruling that claims not disclosed under the contract clauses and issues related to 'No Claim' certificates are non-recoverable, emphasizing the importance o....
The court upheld the tribunal's award, concluding that the claims did not fall under 'excepted matters' and corroborated the contractor's entitlement to claims based on inadequate adjudication by the....
The Arbitral Tribunal has considerable discretion in evaluating evidence and interpreting contract clauses, and its decision cannot be interfered with unless found to be patently illegal or in confli....
The Arbitral Tribunal's decision falls within its jurisdiction and does not amount to patent illegality, as it was based on a plausible interpretation of the exclusionary clause in the contracts and ....
In terms of Section 21 of the A&C Act, the arbitral proceedings commence on the date of receipt of notice invoking the arbitration agreement.
Point of law: In terms of Section 21 of the A&C Act, the arbitral proceedings commence on the date of receipt of notice invoking the arbitration agreement.
The court affirmed that an Arbitrator retains authority to grant damages despite contractual clauses seeming to prohibit such claims, provided the termination of the contract is deemed illegal.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.