SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2021 Supreme(Del) 867

IN THE HIGH COURT OF DELHI AT NEW DELHI
Suresh Kumar Kait, J.
Pragati Construction Consultants - Appellant
Versus
Union Of India - Respondent
Arb. P. No. 685/2021
Decided On : 28-09-2021

Advocates appeared:
Mr.Sumit Bansal, Advocate, for the Petitioner; Mr. J.K. Singh, Standing Counsel for Railways with Mr. Amit Kumar, Advocate, for the Respondent

The main legal point established is the necessity of appointing an independent arbitrator to resolve disputes, in accordance with the provisions of the Arbitration and Conciliation Act, 1996 and relevant case law.

Headnote:

Arbitration - Appointment of Sole Arbitrator - Arbitration and Conciliation Act, 1996 - Section 11(6), Clause 63 and 64 of General Conditions of the Contract - Section 12(5) & 31(5) - Perkins Eastman Architects DPC & Anr. Vs. HSCC (India) Ltd. - Indian Railways Standard General Conditions of Contract, 2018 - Vidya Drolia vs. Durga Trading Corpn. (2021) 2 SCC 1

Fact of the Case:

The petitioner sought the appointment of a sole arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996 to adjudicate disputes arising from a construction contract. The respondent delayed appointing an arbitrator and raised objections based on the contract terms and a 'no claim certificate' submitted by the petitioner.

Finding of the Court:

The court found that the appointment of an independent arbitrator was necessary to resolve the disputes between the parties, as per the decisions in similar cases and the provisions of the Arbitration and Conciliation Act, 1996.

Issues: The issues revolved around the appointment of a sole arbitrator, objections raised by the respondent based on contract terms and 'no claim certificate', and the applicability of relevant legal provisions.

Ratio Decidendi: The court held that an independent arbitrator should be appointed to resolve the disputes, considering the provisions of the Arbitration and Conciliation Act, 1996 and relevant case law.

Final Decision: Mr. Justice (Retd.) Satpal Garg was appointed as the sole arbitrator to adjudicate the disputes between the parties, and the arbitration was to be conducted under the Delhi International Arbitration Centre (DIAC). The petition was accordingly disposed of.

JUDGMENT

(Oral)

1. The relief sought in the present petition before this Court is to appoint sole Arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996 to adjudicate the disputes between the parties in accordance with clause 63 and 64 of the General Conditions of the Contract, 2014.

2. It is stated by the petitioner that respondent vide letter dated 03.05.2016 had awarded the work of extensive repairs and complete renovation of old washing line nos.3, 4 & 5 including assembling and linking of track and other allied works at Coach Care Centre, Hazrat Nizammuddin at New Delhi. The total cost of work at the accepted rates was worked out at Rs. 12,07,05,992.60/-. The stipulated date of completion of work was 15 months from the date of issuance of acceptance letter. Thus, in the present case, the stipulated date for completion of work was 02.08.2017.

3. It is contended by the petitioner that immediately upon the award of work, petitioner fully mobilized at the site and constructed the labour hutments which was duly confirmed vide letter dated 07.05.2016 issued to the respondent. During the execution of the work, respondent got various extra items executed at the site but failed to make complete payments towards the work done to the petitioner. Consequently, petitioner could not complete the work within the extended time period due to non-availability of funds by the respondent.

4. Learned counsel for the petitioner submits that on 05.11.2019, petitioner invoked arbitration in terms of clause 64 of the General Conditions of the Contract and requested the Chief Engineer/Construction of the respondent to consider the claim for arbitration and further on 30.07.2020 petitioner issued a letter regarding the losses/claims of the petitioner and requested for appointment of Arbitrator in terms of clause 64 of the General Conditions of Contract.

5. Respondent did not take any steps for a period of more than 4 months and then for the very first time, on 19.01.2021 issued a letter to petitioner wherein it was stated that for the appointment of sole arbitrator/arbitral tribunal, Clause of Section 12(5) & 31(5) of the Arbitration and Conciliation Act, 1996 should be waived off but petitioner refused to waive off the same and again requested for appointment of the Arbitrator by the competent authority.

6. Vide letter dated 09.03.2021, respondent had nominated a panel of four retired railway officers, not below the rank of Senior Administrative Grade Officers to suggest at least two names out of the panel and thereafter, respondent shall appoint one out of them to act as the nominee of the Petitioner. Petitioner vide its letter dated 24.03.2021 had responded to the letter dated 09.03.2021, stating that appointment of the nominee by the respondent as co-arbitrator is bad in the eyes of law as it is contrary to the law laid down by the Hon’ble Supreme Court in the case of Perkins Eastman Architects DPC & Anr. Vs. HSCC (India) Ltd.: (2019) SCC OnLine SC 1517 wherein it has been categorically stated that “person who has interest in the outcome or decision of the dispute must not have the power to appoint a sole arbitrator” and further requested to refer the dispute to The Delhi International Arbitration Centre, New Delhi for the appointment of sole and independent arbitrator.

7. However, respondent had again reiterated its contentions as stated in letter dated 09.03.2021 and sought consent of the petitioner for appointment of the Arbitrator as clause 64 of General Conditions of Contract does not contemplate for the appointment of an outside arbitrator.

8. At the hearing, learned counsel for petitioner submits that petitioner has already invoked arbitration vide notice dated 05.11.2019 and for claim of Rs. 4,64,65,000/- (Rupees Four Crores Sixty Four Lacs Sixty Five Thousand), an Arbitrator is required to be appointed by this Court.

9. Respondent has filed a short counter affidavit to the petition wherein it has been stated that contractor

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top