IN THE HIGH COURT OF DELHI
Suresh Kumar Kait, J.
Pragati Construction Consultants - Appellant
Versus
Union of India - Respondent
Arb.P. 685 of 2021
Decided On : 28-09-2021
| Table of Content |
|---|
| 1. appointment of sole arbitrator requested. (Para 1 , 2 , 3) |
| 2. arbitration process and nominations issues. (Para 4 , 5 , 6) |
| 3. contractor's claims and no claim certificate. (Para 8 , 9) |
| 4. referral to arbitration despite disputes. (Para 10 , 11 , 12) |
| 5. court appoints an independent arbitrator. (Para 13 , 14 , 15 , 16 , 17) |
1. The relief sought in the present petition before this Court is to appoint sole Arbitrator under Section 11(6) of the Arbitration and Conciliation Act, 1996 to adjudicate the disputes between the parties in accordance with clause 63 and 64 of the General Conditions of the Contract, 2014.
2. It is stated by the petitioner that respondent vide letter dated 03.05.2016 had awarded the work of extensive repairs and complete renovation of old washing line nos.3, 4 & 5 including assembling and linking of track and other allied works at Coach Care Centre, Hazrat Nizammuddin at New Delhi. The total cost of work at the accepted rates was worked out at Rs.12,07,05,992.60/-. The stipulated date of completion of work was 15 months from the date of issuance of acceptance letter. Thus, in the present case, the stipulated date for completion of work was 02.08.2017.
3. It is contended by the petitioner that immediately upon the award of work, petitioner fully mobilized at the site and constructed the labour hutments which was duly confirmed vide letter dated 07.05.2016 issued to the respondent. During the execution of the work, respondent got various extra items executed at the site but failed to make complete payments towards the work done to the petitioner. Consequently, petitioner could not complete the work within the extended time period due to non-availability of funds by the respondent.
4. Learned counsel for the petitioner submits that on 05.11.2019, petitioner invoked arbitration in terms of clause 64 of the General Conditions of the Contract and requested the Chief Engineer/Construction of the respondent to consider the claim for arbitration and further on 30.07.2020 petitioner issued a letter regarding the losses/claims of the petitioner and requested for appointment of Arbitrator in terms of clause 64 of the General Conditions of Contract.
5. Respondent did not take any steps for a period of more than 4 months and then for the very first time, on 19.01.2021 issued a letter to petitioner wherein it was stated that for the appointment of sole arbitrator/arbitral tribunal, Clause of Section 12(5) & 31(5) of the Arbitration and Conciliation Act, 1996 should be waived off but petitioner refused to waive off the same and again requested for appointment of the Arbitrator by the competent authority.
6. Vide letter dated 09.03.2021, respondent had nominated a panel of four retired railway officers, not below the rank of Senior Administrative Grade Officers to suggest at least two names out of the panel and thereafter, respondent shall appoint one out of them to act as the nominee of the Petitioner. Petitioner vide its letter dated 24.03.2021 had responded to the letter dated 09.03.2021, stating that appointment of the nominee by the respondent as co-arbitrator is bad in the eyes of law as it is contrary to the law laid down by the Hon'ble Supreme Court in the case of Perkins Eastman Architects DPC & Anr. Vs. HSCC (India) Ltd., (2019) SCC OnLine SC 1517 wherein it has been categorically stated that "person who has interest in the outcome or decision of the dispute must not have the power to appoint a sole arbitrator" and further requested to refer the dispute to The Delhi International Arbitration Centre, New Delhi for the appointment of sole and independent arbitrator.
7. However, respondent had again reiterated its contentions as stated in letter dated 09.03.2021 and sought consent of the petitioner for appointment of the Arbitrator as clause 64 of General Conditions of Contract does not contemplate for the appointment of an outside arbitrator.
8. At the hearing, learned c
The court affirmed that arbitration proceedings should be initiated to resolve disputes, even if a no-claim certificate is invoked, unless the claims are manifestly devoid of merit.
The main legal point established is the necessity of appointing an independent arbitrator to resolve disputes, in accordance with the provisions of the Arbitration and Conciliation Act, 1996 and rele....
The court confirmed the validity of invoking arbitration under the Arbitration and Conciliation Act when disputes arise over contract performance and payment.
Appointment of a sole arbitrator must comply with the provisions of the Arbitration and Conciliation Act, 1996 and should not be in violation of relevant legal precedents.
Arbitration Agreement - Appointment of - The learned Arbitrator shall ensure compliance of Section 12 of Arbitration and Conciliation Act, 1996 before commencing the arbitration.
No single party can be permitted to unilaterally appoint the Arbitrator, as it would defeat the purpose of unbiased adjudication of dispute between parties.
The main legal point established in the judgment is the court's authority to appoint an arbitrator as per the contract clause and the provisions of the Arbitration and Conciliation Act, 1996.
The main legal point established is that the appointment of an arbitrator must be in accordance with the law and the parties' written consent, and the court has the authority to appoint an arbitrator....
The court confirmed the existence of an arbitration agreement and mandated the appointment of a sole arbitrator to adjudicate contract disputes, highlighting the necessity of complying with contractu....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.