SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Article Pause Article
judgment-img

2021 Supreme(Del) 1084

IN THE HIGH COURT OF DELHI AT NEW DELHI
C. Hari Shankar, J.
M/s Dinesh Kumar Yadav (huf) - Appellant
Versus
M/s Aims Sanya Developers (p) Ltd - Respondent
Arbitration Petition No. 27 of 2021
Decided On : 14-07-2021

Advocates appeared:
Shantanu Aggarwal, Advocate

The court emphasized the importance of referring disputes to arbitration as per the arbitration clause in the agreement and held that issues such as limitation should be decided by the Arbitral Tribunal.

Headnote:

Arbitration - Dispute Reference - Arbitration & Conciliation Act, 1996, Section 11(6)

Fact of the Case:

The petitioner sought reference of disputes to arbitration under Section 11(6) of the Arbitration & Conciliation Act, 1996, due to non-response from the respondent after issuing a notice of demand.

Finding of the Court:

The court found the respondent's single ground of limitation as an issue to be decided by the Arbitral Tribunal and not a basis to reject the petitioner's request for arbitration reference.

Issues: The main issue was the reference of disputes to arbitration under Section 11(6) of the Arbitration & Conciliation Act, 1996, and the respondent's contention of limitation.

Ratio Decidendi: The court held that the issue of limitation should be decided by the Arbitral Tribunal and referred the disputes to arbitration as per the arbitration clause in the agreement.

Final Decision: The court referred the disputes between the parties to arbitration to be held under the aegis of the Delhi International Arbitration Centre (DIAC) and in accordance with its rules and regulations.

JUDGMENT

C Hari Shankar, J. - This is a petition under Section 11(6) of the Arbitration & Conciliation Act, 1996 ('the 1996 Act') seeking reference of the disputes between the parties to arbitration.

2. The substratum of the disputes, as captured in paras 10 to 12 and 14 to 17 of the petition may be reproduced, verbatim, thus:

"10. That the Respondent has also entered into a Space Buyer Agreement dated 07.09.2010, which also includes annexure including the terms and conditions of payment of monthly assured returns payable by the Respondent to the Petitioner.

11. That the cost of the said office space was agreed to be at Rs. 4,439.61 per sq. ft. (basic sale price) i.e. total cost of Rs. 44,28,111/- (Rupees Forty Four Lacs Twenty Eight Thousand One Hundred and Eleven Only).

12. That the Respondent had represented to the Petitioner that it shall pay monthly assured returns @Rs.85.01 per sq. ft. per month till the time the possession is not handed over by the Respondent to the Petitioner. Accordingly, a total sum of Rs.84,790/- (Rupees Eighty Four Thousand Seven Hundred and Ninety Only) per month is payable by the Respondent to the Petitioner till the time the possession of the proposed office complex is not handed over by the Respondent to the Petitioner.

***

14. That under Clause 18 of the said agreement, the Respondent was to complete the construction and handover the possession of the allotted unit to the Petitioner within 36 months from the date of booking i.e. 26.07.2010. A period of 6 months was also reserved as grace period. As such, the Respondent was liable to handover the possession latest by 25.01.2014.

15. That the abovesaid period of 42 months from the date of booking including the grace period had already expired. In fact, a period of 84 months had also expired after that. What to say to the completion of project and handing over of the possession, no construction, whatsoever has been started by the Respondent till date. In fact, the Respondent had abandoned the project. The Respondent has further committed various fraudulent acts. However, the Petitioner is not mentioning those acts in the present proceedings as they are not relevant here.

16. That the Respondent has also failed and neglected to make the monthly payment of assured returns calculated @ Rs.85.01 per sq. ft. per month in terms of the Space Buyer Agreement dated 07.09.2010 under the assured returns plan. The Respondent has defaulted in making the payment of assured returns since 01.05.2016. The cheques issued towards the assured returns have also got dishonored. As such, assured returns calculated @ Rs.85.01 per sq. ft. per month w.e.f. 01.05.2016 till 30.11.2020 is due and payable by the Respondent to the Petitioner.

17. That in these circumstances, the Petitioner got issued and served upon the Respondent a notice of demand dated 05.08.2020 thereby invoking the arbitration clause. The following claims were made in the said notice of demand:-

a) Refund of an amount of Rs.40,06,708/- (Rupees Forty Lacs Six Thousand Seven Hundred and Eight Only)

b) Payment towards the assured returns calculated @ Rs.85.01 per sq. ft. per month w.e.f. 01.05.2016 till 31.07.2020 and further a payment of Rs.84,790/- per month toward the assured returns till the time the entire payment is made.

c) Payment of interest @ 18% p,a. on the arrears of amount of monthly-assured returns from the date of the amounts becomes due till its realization."

3. The notice, dated 5th August, 2020, addressed by the petitioner to the respondent did not meet with any response from the respondent. 30 days having elapsed since the date of the notice, the petitioner has approached this Court under Article 11(6) of the 1996 Act, for appointment of an arbitrator.

4. The demand is between Rs. 40 and 45 lakhs.

5. The respondent has filed a reply to the petition, in which the only ground taken in a single sentence is that the claims of the petitioner are barred by limitation.

6. This, in my view, is an issue which woul

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
whatsapp-icon Back to top