2021 Supreme(Del) 2302

IN THE HIGH COURT OF DELHI AT NEW DELHI
Navin Chawla, J.
Srinagar Banihal Expressway Ltd - Appellant
Versus
National Highways Authority Of India & Anr. - Respondents
W.P. (C) No. 4034 of 2021
Decided On : 26-03-2021

Advocates appeared:
Sandeep Sethi, Advocate, Rajeev Mehra, Advocate, Amar Gupta, Advocate, Divyam Agarwal, Advocate, Pallavi Kumar, Advocate, Anuj Aggarwal, Advocate, Gunjan Sinha, Advocate, Kapil Arora, Advocate

The court emphasized the importance of the Concession Agreement clauses, particularly Article 37.1.3, 17.10, 36.1, and 36.2, in determining the rights and obligations of the parties and the validity of the executed agreement.

Headnote:

Tender - Concession Agreement - Article 37.1.3, 17.10, 36.1, 36.2 - The court discussed the Concession Agreement and its clauses, particularly focusing on Article 37.1.3, 17.10, 36.1, and 36.2. The court highlighted the rights and obligations of the parties, the authority's entitlement to complete the balance work through a third party, and the lender's role in the execution of the agreement. The court found that the agreement between the respondent no.1 and respondent no.2 was valid based on the provisions of the Concession Agreement.

Fact of the Case:

The petitioner sought an ad interim injunction to complete the balance work at the rates offered by the respondent no.2, citing disputes with lenders. The respondent no.1 executed an agreement with respondent no.2 for the balance work, leading to the petitioner's plea for an injunction.

Finding of the Court:

The court found that no case for an ad interim injunction was made out by the petitioner at this stage due to the already executed agreement between the respondent no.1 and respondent no.2.

Issues: The issues revolved around the completion of balance work, the authority's entitlement to execute an agreement with a third party, and the petitioner's plea for an ad interim injunction.

Ratio Decidendi: Based on the facts and the executed agreement, the court concluded that the petitioner's plea for an ad interim injunction was not justified at this stage.

Final Decision: The case was listed for further hearing on 20th May, 2021 before the Roster Bench.

JUDGMENT

Navin Chawla, J. -

Cm No.12197/2021 (Exemption)

Allowed, subject to all just exceptions.

WP(C) 4034/2021 & CM 12196/2021

1. Issue notice.

2. Notice is accepted by Ms.Gunjan Singh, Advocate on behalf of the respondent no. 1 and Mr.Kapil Arora, Advocate on behalf of the respondent no. 2.

3. Let counter affidavit be filed within a period of four weeks. Rejoinder, if any, be filed within a period of three weeks thereafter.

4. It is an admitted case of the petitioner that the Notice Inviting Tender for the balance work of petitioner's contract was issued by the respondent no.1 on 14.07.2020. Prior thereto, the respondent no.1 had issued a notice dated 22.05.2020 to the petitioner informing it as under:

"Accordingly, Concessionaire is hereby called upon for remedying the aforesaid defaults no later than the period as specified in the Concession Agreement, from the date of receipt of this notice, failing which the Authority shall be constrained to exercise its rights under the relevant clauses of the Concession Agreement and including issuing the separate tender on standalone basis for completing the balance work of Rs 142 Cr. Overriding powers of the Authority under Clause 17.10.1 states that if in the reasonable opinion of the Authority, the Concessionaire is in material breach of its obligations under this Agreement and in particular, the Maintenance Requirements, and such breach is causing or likely to cause material hardship or danger to the Users, the Authority may without prejudice to any of its rights under this Agreement including Termination thereof, by notice require the Concessionaire to take reasonable measures immediately for rectify."

5. The petitioner and the respondent have been corresponding thereafter on the plea of the petitioner that the petitioner be allowed to complete the balance work at the rates offered by the respondent no.2. Initially, the respondent no.1 was agreeable to the said offer and called upon the petitioner to sign the necessary MoU/Tripartite Agreement with including its lenders. It is not denied by the petitioner that such MoU/Tripartite Agreement could not be executed by it due to disputes between the petitioner and the lenders. It has also come on record that the lenders have moved the learned Debts Recovery Tribunal and the learned National Company Law Tribunal for recovering the amounts due to them from the petitioner.

6. By the letter dated 04.02.2021, the respondent no.1 called upon the petitioner to inter alia show credible evidence of availability of required funds for completion of the balance work. It is the say of the respondent no.1 that in spite of the opportunity granted, the petitioner was unable to do the same. In this regard, the respondent no.1 is also relying upon the letter dated 01.03.2021 of the Independent Engineer.

7. The learned counsel for the respondent no.1 submits that the project was in fact to be completed within 90 days of 02.04.2018, and has already been considerably delayed, leaving respondent no.1 with no option but to execute the agreement with the respondent no.2 for completion of the balance work. In fact, the agreement with the respondent no.2 has already been executed on 23.03.2021.

8. The learned senior counsel for the petitioner has placed reliance on Article 37.1.3 of the Concession Agreement to submit that for awarding the balance work to a third party, the respondent no.1 was to first issue a notice intending to terminate the Concession Agreement and seek the view of the lenders for entering into such contract with the third party. He submits that in the present case, there is no notice issued by the respondent no.1 of its intent to terminate the Concession Agreement and therefore, the respondent no.1 cannot execute such Agreement with the respondent no.2.

9. Article 37.1.3 of the Concession Agreement reads as under:

"37.1.3 The Authority shall, if there be Senior Lenders, send a copy of its notice of intention to issue a Termination Notice referred to