SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
V. Kameswar Rao, J.
Pink City Expressway Private Limited - Appellant
Versus
National Highway Authority of India - Respondent
O.M.P.(I) (COMM.) 166 of 2022
Decided On : 03-06-2022




A concession period extension under a contract requires compliance with specific procedural conditions, and is not automatic despite recommendations from an independent engineer.

Headnote:(A) Contract Law - Concession Agreement - Article 29 - Extension of concession period - Issues regarding entitlement to automatic extension under Concession Agreement and default conditions set by NHAI - NHAI's position communicated that concession shall not extend beyond June 02, 2022, due to non-compliance by petitioner - The court held that the NHAI's refusal to further extend the concession period is valid, as the petitioner failed to challenge earlier communications or adhere to necessary conditions. (Paras 36 to 54)

(B) Specific Relief Act, 1963 - No automatic extension - Requirement of compliance with procedures outlined under the Concession and Tri-partite Agreements - The NHAI retains rights under Article 37 for termination of agreement in case of defaults. (Para 40)

Facts of the case:
The petitioner sought an extension to operate toll plazas based on prior traffic surveys indicating a shortfall. A review committee indicated extension up to August 2023 was warranted. However, NHAI denied this due to unpaid dues and project maintenance failures.

Findings of Court:
The NHAI had the right to deny further extension based on the absence of compliance by the petitioner. The court directed that proper contractual processes and earlier communications should have been legally contested by the petitioner.

Issues: Whether the petitioner is entitled to an automatic extension under Article 29; legality of NHAI's enforcement of default conditions.

Ratio Decidendi: The court expressed that the extension under Article 29 is not automatic and requires competent authority's approval, contrary to the petitioner's claims. The necessity of adhering to dispute resolution mechanisms in the Concession Agreement was emphasized.

Result: Petition dismissed.

Table of Content
1. petitioner filed for operational rights based on the concession agreement. (Para 1 , 2)
2. details on project completion and nhai's commitments. (Para 3 , 4)
3. the concession extension is automatic upon traffic shortfall. (Para 5 , 6)
4. nhai must follow specific procedures outlined for termination. (Para 7 , 8 , 9)
5. dispute resolution mechanism should address the arguments. (Para 10 , 11 , 12)
6. court observations on good faith and obligations of nhai. (Para 13 , 14)
7. urging the protection of lenders' interests in disputes. (Para 15 , 16 , 17)
8. arguments on financial agreements and obligations. (Para 18 , 19 , 20)
9. petitioner seeks relief against nhai's refusal to extend concession. (Para 21 , 22)
10. assessing eligibility for relief based on submissions made. (Para 23 , 24 , 25)
11. outcome must consider broader implications for public interest. (Para 26 , 27 , 28)
12. final remarks on the necessity of maintaining contract sustainability. (Para 29 , 30)
13. court dismisses the petition based on factual findings. (Para 31 , 32 , 33)
14. liberal approach suggested for rights of all parties. (Para 34 , 35 , 36)

JUDGMENT

V. Kameswar Rao, J. (Oral)--The present petition has been filed by the petitioner with the following prayers:

    "a) To hold that as an interim measure; the Petitioner shall be entitled to operate the Toll plazas as per the recommendation of Independent Engineer upto 26.08.2023 as per Article-29 of the Concession Agreement determination done by the Independent Engineer vide letter dated 01.08.2018.

    b) Allow the Petitioner to operate the toll plazas as per the Concession Agreement dated 06.06.2008 and Tri-partite Agreement dated 16.03.2017.

    c) Pass such further order/orders as this Hon'ble Court may deem fit and proper under the facts and circumstances of the case."

2. It is the case of the petitioner and so contended by Mr. Amit Sibal, learned Senior Counsel appearing for Pink City Expressway Private Limited (hereinafter referred to as `petitioner' and `concessionaire' interchangeably) that the petitioner and the respondent NHAI entered into a Concession Agreement dated June 6, 2008 with regard to widening (six laning) of Gurgaon-Kotputli-Jaipur section of National Highway No.8 from KM 42.70 to KM 273.00 (length of 225.60 km) in the State of Haryana and Rajasthan (`Project Highway', hereinafter) on Build Operate and Transfer (`BOT', for short) basis.

3. The petitioner has completed approximately 96% of the widening of the Project Highway. He states that this aspect has been accepted by the respondent/NHAI. It was also agreed that the concession period shall be extended till August 2023 for recovering the deferred premium. In the month of September 2017, owing to shortage of funds and non completion of the project, a One Time Fund Infusion Scheme (`OTFIS', for short) of Rs.354 Crore was allowed for the completion of the pending works. He stated, it was also agreed by the NHAI that the petitioner has in no way defaulted in executing the above work. A Review Committee of the lenders was constituted and the respondent NHAI with the power to impose and approve sanctions in case of default by the concessionaire/petitioner in getting the above amounts released. According to him, as per Article 29 of the Concession Agreement, the concession is deemed to have been extended, if the actual traffic at the Project Highway has fallen short of the specific target traffic (79,835 PCUs per day) on the target date. The petitioner as well as the respondent NHAI have conducted their respective traffic surveys and have reached the conclusion that the actual traffic has fallen short of the target by more than 2.5% on the target date thereby leading to deemed extension as per Article 29.1.2 of the Concession Agreement. In fact, he stated that actual traffic has fallen short by 14.87% as per the survey conducted by the petitioner. Even as per the survey conducted by the respondent NHAI, the actual traffic has fallen sho

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top