IN THE HIGH COURT OF DELHI
V. Kameswar Rao, J.
Pink City Expressway Private Limited - Appellant
Versus
National Highway Authority of India - Respondent
O.M.P.(I) (COMM.) 166 of 2022
Decided On : 03-06-2022
| Table of Content |
|---|
| 1. petitioner filed for operational rights based on the concession agreement. (Para 1 , 2) |
| 2. details on project completion and nhai's commitments. (Para 3 , 4) |
| 3. the concession extension is automatic upon traffic shortfall. (Para 5 , 6) |
| 4. nhai must follow specific procedures outlined for termination. (Para 7 , 8 , 9) |
| 5. dispute resolution mechanism should address the arguments. (Para 10 , 11 , 12) |
| 6. court observations on good faith and obligations of nhai. (Para 13 , 14) |
| 7. urging the protection of lenders' interests in disputes. (Para 15 , 16 , 17) |
| 8. arguments on financial agreements and obligations. (Para 18 , 19 , 20) |
| 9. petitioner seeks relief against nhai's refusal to extend concession. (Para 21 , 22) |
| 10. assessing eligibility for relief based on submissions made. (Para 23 , 24 , 25) |
| 11. outcome must consider broader implications for public interest. (Para 26 , 27 , 28) |
| 12. final remarks on the necessity of maintaining contract sustainability. (Para 29 , 30) |
| 13. court dismisses the petition based on factual findings. (Para 31 , 32 , 33) |
| 14. liberal approach suggested for rights of all parties. (Para 34 , 35 , 36) |
JUDGMENT
V. Kameswar Rao, J. (Oral)--The present petition has been filed by the petitioner with the following prayers:
"a) To hold that as an interim measure; the Petitioner shall be entitled to operate the Toll plazas as per the recommendation of Independent Engineer upto 26.08.2023 as per Article-29 of the Concession Agreement determination done by the Independent Engineer vide letter dated 01.08.2018.
b) Allow the Petitioner to operate the toll plazas as per the Concession Agreement dated 06.06.2008 and Tri-partite Agreement dated 16.03.2017.
c) Pass such further order/orders as this Hon'ble Court may deem fit and proper under the facts and circumstances of the case."
2. It is the case of the petitioner and so contended by Mr. Amit Sibal, learned Senior Counsel appearing for Pink City Expressway Private Limited (hereinafter referred to as `petitioner' and `concessionaire' interchangeably) that the petitioner and the respondent NHAI entered into a Concession Agreement dated June 6, 2008 with regard to widening (six laning) of Gurgaon-Kotputli-Jaipur section of National Highway No.8 from KM 42.70 to KM 273.00 (length of 225.60 km) in the State of Haryana and Rajasthan (`Project Highway', hereinafter) on Build Operate and Transfer (`BOT', for short) basis.
3. The petitioner has completed approximately 96% of the widening of the Project Highway. He states that this aspect has been accepted by the respondent/NHAI. It was also agreed that the concession period shall be extended till August 2023 for recovering the deferred premium. In the month of September 2017, owing to shortage of funds and non completion of the project, a One Time Fund Infusion Scheme (`OTFIS', for short) of Rs.354 Crore was allowed for the completion of the pending works. He stated, it was also agreed by the NHAI that the petitioner has in no way defaulted in executing the above work. A Review Committee of the lenders was constituted and the respondent NHAI with the power to impose and approve sanctions in case of default by the concessionaire/petitioner in getting the above amounts released. According to him, as per Article 29 of the Concession Agreement, the concession is deemed to have been extended, if the actual traffic at the Project Highway has fallen short of the specific target traffic (79,835 PCUs per day) on the target date. The petitioner as well as the respondent NHAI have conducted their respective traffic surveys and have reached the conclusion that the actual traffic has fallen short of the target by more than 2.5% on the target date thereby leading to deemed extension as per Article 29.1.2 of the Concession Agreement. In fact, he stated that actual traffic has fallen short by 14.87% as per the survey conducted by the petitioner. Even as per the survey conducted by the respondent NHAI, the actual traffic has fallen sho
A concession period extension under a contract requires compliance with specific procedural conditions, and is not automatic despite recommendations from an independent engineer.
Lenders cannot independently seek extension of concession period under Concession Agreement, their rights do not confer standing in this matter according to the agreements in place.
The main legal point established in the judgment is that the right to seek extension of the concession period was vested in the concessionaire alone, and the senior lenders did not have the independe....
The court clarified that the powers under Section 9 of the Arbitration and Conciliation Act cannot extend to granting specific performance of a contract or automatic extensions beyond terms explicitl....
The interpretation of contractual obligations under the Concession Agreement indicates that the construction of additional toll lanes was excluded from maintenance obligations, contrary to the tribun....
it appropriate to exercise writ jurisdiction under Article 226 in the aforesaid peculiar circumstances for the limited purpose of interim protection while relegating the parties to arbitration.
The appellant cannot seek a writ for extension of the concession period as it is not a party to the concession agreement, and suggested to seek remedy under the agreements with all defences available....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.