PRATHIBA M. SINGH
Jagdish Chand Gupta – Appellant
Versus
NHPC Ltd – Respondent
JUDGMENT
Prathiba M. Singh, J. - The present petition has been filed by the Petitioner challenging the impugned letter dated 24th June 2019, issued by Respondent No. 1- NHPC Ltd. (hereinafter NHPC ), directing the appointment of Shri. H.L. Bajaj as the Adjudicator in respect of claims raised by NHPC for a sum of Rs.4.55 crores qua the Reconstruction of the permanent bridge over the River Jhelum at Bandi, Jammu and Kashmir.
2. The case of the Petitioner is that the appointed Adjudicator had earlier rejected the claim for compensation of the NHPC, and a second round of adjudication by the same Adjudicator is not permissible, under the terms of the contract entered into on 6 th February 2006.
3. Mr. Anish Chawla, ld. counsel for the Petitioner submits that the Adjudicator is charging a huge fee and the Petitioner is being saddled with the expenses of the same. In terms of the contract, he submits that the Adjudicator ought to have decided the issue within 28 days, as provided in Clause 56.1.2 of the General Conditions of Contract, which he has failed to do and hence he became functus officio.
4. On the other hand, Mr. Sharma, ld. counsel for Respondent No.1, has challenged the territorial
The main legal point established in the judgment is that the detailed and exhaustive dispute resolution mechanism specified in the contract provides various options for the petitioner to exercise if ....
The court reaffirmed that contractual dispute resolution mechanisms should be utilized, disallowing jurisdiction under Article 227 unless there is a demonstrated case of perversity.
The court established that the jurisdiction for appointing an arbitrator is governed by the terms of the contract between the parties, and any deviation from those terms, including the applicable law....
The appointment of an Arbitrator comes after the decision of the Adjudicator, and the Adjudicator and the Arbitrator are two distinct forums for dispute resolution under the contract.
The Adjudicator's decision is binding if not challenged within 28 days, emphasizing the enforceability of dispute resolution clauses in contracts.
The court established that disputes between government entities must be resolved under the statutory framework of the Arbitration and Conciliation Act, 1996, ensuring enforceability and legal clarity....
The decision of an Adjudicator is binding if not challenged within the stipulated time, emphasizing the importance of contractual dispute resolution mechanisms.
The main legal point established is the applicability of the Act as amended with effect from 23rd October 2015 and the disqualification of the appointed Arbitrator under Section 12(5) of the Act.
A court can appoint an arbitrator when a party fails to do so despite repeated requests and after exhausting all pre-arbitration mechanisms.
The specified venue in an arbitration clause denotes the seat of arbitration, thus limiting jurisdiction to designated courts and excluding others.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.