2024 Supreme(Ker) 1054

IN THE HIGH COURT OF KERALA AT ERNAKULAM
A. MUHAMED MUSTAQUE, A.C.J., S. MANU, J.
KERALA STATE ELECTRICITY BOARD – Appellant
Versus
ALANKAR CONSTRUCTION COMPANY – Respondent
W.A. No. 7 of 2023
Decided On : 06-09-2024

Advocates:
Advocate Appeared:
For the Appellant : B. PREMOD.
For the Respondent: C.S. AJITH PRAKASH.

IMPORTANT POINT
The decision of an Adjudicator is binding if not challenged within the stipulated time, emphasizing the importance of contractual dispute resolution mechanisms.

Headnote:

Adjudication - Dispute Resolution - Clause 25 - The court emphasized the binding nature of the Adjudicator's decision when not challenged within the stipulated time frame, reinforcing the importance of adhering to contractual dispute resolution mechanisms.

Fact of the Case:

The respondent, a partnership firm, sought enforcement of an Adjudicator's decision regarding claims from a construction contract with the Kerala State Electricity Board, which the appellants contested on procedural grounds.

Finding of the Court:

The court found that the appellants failed to challenge the Adjudicator's decision within the required 28 days, rendering it final and binding, and rejected the appellants' claims of the decision being void.

Issues: Whether the Adjudicator's decision was binding despite the appellants' claims of procedural invalidity and whether the appellants could refuse to honor the decision.

Ratio Decidendi: The court held that the Adjudicator's decision is binding if not contested within the contractual timeframe, and the parties must adhere to the agreed dispute resolution process.

Result: The writ appeal was dismissed, upholding the Adjudicator's decision.

JUDGMENT :

S. MANU, J.

1. Appellants are the respondents in W.P. (C) No. 19299 of 2021. The respondent herein approached this Court by filing the writ petition praying mainly for a direction to the 2nd appellant to calculate, sanction and disburse the amount as per the Adjudicator's decision with respect to the disputes notified as per claim (m) and (n) in Ext.P7 and decided by the Adjudicator by Ext.P12 within a time frame and for interest on the said amount.

2. The petitioner, a partnership firm engaged in civil construction works was awarded with a work by the Kerala State Electricity Board Limited (KSEBL). Name of the work is “DRIP-Idukki Hydro Electric Project-Rehabilitation including remedial measures and basic facilities- improvement of approach roads to Idukki and Cheruthoni Dam - (Part-II works)”. Agreement was executed on 16.6.2016. The agreement contains an adjudication clause. As per the said clause if the parties to the contract notified a dispute, same shall be referred to an Adjudicator at the first instance. Whenever the Adjudicator takes decisions, either party may refer the decision of the Adjudicator for arbitration within 28 days of the Adjudicator's decision. If no reference is made for arbitration within 28 days, the decision of the Adjudicator will be final and binding.

3. After completing the works on 14.2.2018 the respondent notified a dispute on 08.01.2019 before the Adjudicator. The dispute included 25 claims under separate and distinct heads. The Adjudicator, by Ext.P7, decided claims under (m) and (n) in favour of the respondent. The respondent referred the remaining matters for arbitration by the Arbitral Tribunal. KSEBL did not choose to approach the Arbitral Tribunal against the claims decided in favour of the respondent. Before the Arbitral Tribunal, the 2nd appellant filed a defence statement. However, no counter claim against granting of claims under (m) and (n) in favour of the respondent was raised. On 06.02.2021, the Arbitral Tribunal passed an award. The respondent preferred the writ petition aggrieved by non-quantification and disbursal of the claims allowed in its favour by the Adjudicator. The appellants resisted the writ petition. According to the appellants, the Adjudicator's proceedings were null and void since the contractors' complaints were submitted much beyond 14 days’ time limit under Clause 24 of the agreement. It was also contended that the Adjudicator failed to consider claims (m) and (n) in a proper manner and the decision of the Adjudicator cannot be implemented as there is no quantification of the amount to be paid. Further contention of the appellants is that the Adjudicator's decision is no more relevant as the Arbitral Tribunal has passed an award subsequently. According to the appellants, if the decision rendered by the Adjudicator in favour of a party is not accepted by other party, the dispute would not get crystallized and the parties will have to go by the arbitration clause. Decision rendered by the Adjudicator is only a procedural order preceding the arbitration proceedings. The appellants never accepted the authority of the Adjudicator as well as his decision. The defence statement preferred before the Arbitral Tribunal clearly shows that the appellants never accepted the decision of the Adjudicator. The appellants therefore contended that the prayer in the writ petition cannot be allowed and the writ petition is liable to be dismissed.

4. The learned Single Judge after hearing both sides held that if any of the parties had any grievance against the decision of the Adjudicator, the remedy was to refer the matter for arbitration within a period of 28 days. The learned Single Judge found that the KSEBL did not challenge the decision of the Adjudicator with respect to claims (m) and (n) by referring the same for arbitration. Plea of the appellants that the respondent ought to have sought the approval of the Arbitrator regarding the claims decided by the Adjudicator in

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
Judicial Analysis

AI

SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top