SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2021 Supreme(Del) 1698

IN THE HIGH COURT OF DELHI AT NEW DELHI
C. Hari Shankar, J.
Reliance Communications Infrastructure Limited - Appellant
Versus
Bharat Sanchar Nigam Limited - Respondent
O.M.P. (Misc) (Comm)(Original Miscellaneous Petition (Misc) (Comm)) No. 277 of 2020
Decided On : 09-02-2021

Advocates appeared:
Gauhar Mirza, Advocate, Prakhar Deep, Advocate, Nishant Doshi, Advocate, Nalin Tripathi, Advocate

The court's decision emphasized the authority of the Resolution Professional to seek extension of the Arbitral Tribunal's mandate and the impact of the continuing lockdown in Maharashtra on the ongoing arbitral proceedings.

Headnote:

Arbitration and Conciliation Act - Extension of Arbitral Tribunal's Mandate - Section 29A(5) - 1996 Act

Fact of the Case:

The petitioner, an Interim Resolution Professional (IRP) appointed by the NCLT, filed a petition seeking extension of the mandate of the Arbitral Tribunal to conclude ongoing arbitral proceedings and render an award. The respondent questioned the competence of the petitioner to file the petition, citing Section 12 of the IBC, which stipulates a time limit for completion of the insolvency resolution process.

Finding of the Court:

The court found that a lockdown was prima facie continuing in Maharashtra, as indicated by orders of the NCLAT and the Government of Maharashtra. The court held that the petition was maintainable and extended the mandate of the Arbitral Tribunal by 12 months, leaving other issues open for the Arbitral Tribunal to decide.

Issues: Competence of the petitioner to file the petition, continuation of the lockdown in Maharashtra, and the authority of the Resolution Professional to seek extension of the Arbitral Tribunal's mandate.

Ratio Decidendi: The court's decision was based on the prima facie continuation of the lockdown in Maharashtra and the authority of the Resolution Professional to seek extension of the Arbitral Tribunal's mandate.

Final Decision: The court allowed the petition and extended the mandate of the Arbitral Tribunal by 12 months, leaving other issues open for the Arbitral Tribunal to decide.

JUDGMENT

C. Hari Shankar, J. - This petition is in the nature of an application under Section 29A (5) of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as "the 1996 Act"), and has been filed by Mr. Anish Niranjan Nanavaty, who claims to be an Interim Resolution Professional (IRP), appointed by the National Company Law Tribunal (hereinafter referred to as "NCLT"), vide order dated 25 th September, 2019, to oversee the affairs of M/s. Reliance Communications Infrastructure Limited (hereinafter referred to as "the Company"), in terms of the Insolvency and Bankruptcy Code, 2016 (IBC). Mr. Mirza, learned counsel for the petitioner, submits that subsequently, vide a resolution of the Committee of Creditors (CoC) of the Company, passed on 22nd October, 2019, the petitioner was appointed as Resolution Professional (RP) in respect of the Company.

2. Xxx xxx xxx

3. Admittedly, arbitral proceedings, between the petitioner and the respondent, were continuing before a three-member Arbitral Tribunal, and have yet to conclude. The mandate of the learned Arbitral Tribunal has, in the interregnum, expired. The petitioner has, in these circumstances, invoked Section 29A(5) of the 1996 Act, by means of the present petition, seeking extension of the mandate of the learned Arbitral Tribunal to conclude the arbitral proceedings and render award.

4. A reply to the present petition has been filed by the respondent, which is represented by Mr. Nalin Tripathi, learned counsel. Mr. Tripathi, essentially, questions the competence of the petitioner, as RP, to file the present petition on behalf of the company. Reliance has been placed, for this submission, on Section 12 of the IBC, which reads thus:

    "12. Time-limit for completion of insolvency resolution process

      (1) Subject to sub-section (2), the corporate insolvency resolution process shall be completed within a period of one hundred and eighty days from the date of admission of the application to initiate such process.

        (2) The resolution professional shall file an application to the Adjudicating Authority to extend the period of the corporate insolvency resolution process beyond one hundred and eighty days, if instructed to do so by a resolution passed at a meeting of the committee of creditors by a vote of sixty-six per cent of the voting shares.

          (3) On receipt of an application under sub-section (2), if the Adjudicating Authority is satisfied that the subject matter of the case is such that corporate insolvency resolution process cannot be completed within one hundred and eighty days, it may by order extend the duration of such process beyond one hundred and eighty days by such further period as it thinks fit, but not exceeding ninety days:

            Provided that any extension of the period of corporate insolvency resolution process under this section shall not be granted more than once."

            5. Mr. Tripathi submits that a strict regimen is stipulated in Section 12 of the IBC, with the resolution process requiring to be completed within 180 days under sub-section (1) thereof and in default, an application to be filed by the RP, under subsection (2), seeking extension of time. In the present case, he submits, such an application was filed by the RP, being IA 941/2020, whereon the learned NCLT, vide order dated 19th March, 2020, extended the Corporate Insolvency Resolution Period (CIRP) by 90 days, commencing 24th March, 2020. Even so reckoned, submits Mr. Tripathi, the authority of Mr. Anish Niranjan Nanavaty to continue as RP expired on 22nd June, 2020. He submits that no second extension could be granted to the RP, in view of the first proviso to Section 12(3) of the IBC.

            6. In response, Mr. Mirza, learned Counsel for the petitioner, has placed on record an order dated 30th March, 2020, passed by the learned National Company Law Appellate Tribunal (hereinafter referred to as "the learned NCLAT") in Suo Motu Company Appeal (AT) (Insolvency) No. 1 of 2020, which reads thus:

              "Upon requests for urgent li

                              Click Here to Read the rest of this document
                              1
                              2
                              3
                              4
                              5
                              6
                              7
                              8
                              9
                              10
                              11
                              SupremeToday Portrait Ad
                              supreme today icon
                              logo-black

                              An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

                              Please visit our Training & Support
                              Center or Contact Us for assistance

                              qr

                              Scan Me!

                              India’s Legal research and Law Firm App, Download now!

                              For Daily Legal Updates, Join us on :

                              whatsapp-icon Back to top