SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 Supreme(Del) 979

IN THE HIGH COURT OF DELHI AT NEW DELHI
Vibhu Bakhru, J.
Director General Central Reserve Police Force - Appellant
Versus
Fibroplast Marine Pvt. Ltd. - Respondent
Original Miscellaneous Petition (COMM) No. 511 of 2019, I. A. Nos. 17282, 17283 of 2019
Decided On : 04-05-2022

Advocates appeared:
Praveen Kumar Jain, Advocate, Bhavna Ruia, Advocate, Sudhanshu Batra, Advocate, Gurinderpal Singh, Advocate, Jaya Bajpai, Advocate

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Challenge to arbitral award - The court found that the arbitral tribunal had committed an error in accepting excessive claims for damages and awarding substantial interest. Key terms of the agreement were breached when delivery quantities were reduced without amendment. The tribunal's findings were set aside due to inordinate delay and lack of evidence. (Paras 35-78)

(B) Enforcement of contract - When a party modifies contract terms significantly, such modifications must be formalized; failure of the petitioner to adhere to delivery obligations resulted in breach and damages awarded. (Paras 19-49)

Facts of the case:
The dispute arose between two parties regarding the supply of boats and motors under a tender, with claims for large sums due to contract breaches, which were later escalated in arbitration.

Findings of Court:
The arbitral tribunal awarded damages amounting to Rs. 18,32,22,680/- due to the petitioner's breach but failed to stipulate the delivery of inventory awarded.

Issues: The primary issues included the validity of claims regarding loss of profits and the reasonableness of awarded sums as they exceeded the original contract amount and the integrity of the arbitrator’s process.

Ratio Decidendi: The court concluded that the tribunal's delayed award lacked adequate evidence for substantial claims and breached the contractual terms justifying rejection of claims.

Result: The arbitral award was set aside, allowing the parties to re-agitate the disputes.

Table of Content
1. factual background of the arbitration agreement and disputes. (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18)
2. arguments against the arbitral award and its quantifications. (Para 26 , 27 , 28 , 29 , 30 , 31 , 32 , 33)
3. court observations regarding delay, merits, and errors in the arbitral award. (Para 35 , 36 , 37 , 38 , 39 , 40 , 41 , 46 , 48 , 52 , 59 , 63 , 67)
4. legal standards for reviewing arbitral awards and its implications. (Para 45 , 72 , 74 , 76)
5. conclusion on setting aside the arbitral award and further proceedings. (Para 78 , 79)

JUDGMENT

Vibhu Bakhru, J. - The petitioner has filed the present petition under Section 34 of the arbitration and Conciliation act, 1996 (hereafter the 'a&C act') impugning an arbitral award dated 31.05.2019 (hereafter the 'impugned award') rendered by an arbitral Tribunal comprising of a Sole arbitrator (hereafter the 'arbitral Tribunal').

2. On 17.07.2008, the petitioner floated a tender bearing no. U.II.708(a)/2008-09-PROC-(NDRF) inviting bids for supply of 288 numbers of Boat assault Universal Type (hereafter 'BaUT') and 288 numbers of 50 HP Out Board Motor (hereafter 'OBM'). In response to the same, the respondent submitted its bid and was declared as the lowest bidder.

3. Subsequently, on 17.07.2009, the parties entered into an agreement bearing number U.II.708(a)/2008-09-PROC-(NDRF)-II for supply of 288 numbers of BaUTs and 288 numbers of OBMs (hereafter the 'agreement') at a consideration of Rs. 16,87,79,520/-. The respondent was liable to pay inspection charges quantified at 2% of the said contract value along with applicable service tax as levied by the Inspecting agency under the Directorate General Quality assurance, Ministry of Defence (hereafter 'CQaE').

4. In terms of the agreement, the respondent was required to submit two pilot samples of the BaUTs and OBMs within a period of two months from the date of the supply order, that is, by 15.09.2009. However, the respondent was unable to comply with the deadline due to various reasons, which it stated were beyond its control. By its letter dated 03.09.2009, it sought extension of one month to submit the two pilot samples. The petitioner accepted the same and by its letter dated 15.09.2009, extended the time till 15.10.2009. On 08.10.2009, the pilot samples were delivered and was received by the CQaE on 12.10.2009.

5. Thereafter, by its letter dated 21.10.2009, the CQaE raised concerns in respect of the pilot samples delivered by the respondent on the ground that the same was submitted after the expiry of the stipulated delivery period. However, in response to the said letter, the respondent informed the CQaE that the petitioner had already extended the time period for delivery of the pilot samples and further, requested the petitioner to issue a formal delivery period extension to the CQaE. The respondent informed the CQaE that it had provided the raw material test specimen and further assured it, that a delivery inspection would be submitted within a period of ten days.

6. The CQaE rejected the pilot samples submitted by the respondent due to certain discrepancies in some materials and informed the same to the respondent by its letter dated 15.03.2010. The respondent requested the CQaE to re-test the pilot samples and the said request was accepted by the CQaE on 15.04.2010. On 28.04.2010, the respondent also provided fresh samples, however, it was found that the same did not conform to the specifications.

7. On 21.12.2010, the respondent submitted fresh samples for evaluation by the CQaE and the pilot samples were finally approved by the CQaE on 24.03.2011. accordingly, the respondent received clearance for bulk production. The CQaE, by its letter dated 24.03.2011, informed the petitioner to issue re-fixation of the bulk delivery period till 24.09.2011 in terms o



Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top