IN THE HIGH COURT OF DELHI AT NEW DELHI
Vibhu Bakhru, J.
Union Of India - Appellant
Versus
M/s Aadhar Stumbh Township Pvt Ltd - Respondent
Original Miscellaneous Petition (COMM) No. 348 of 2021, Miscellaneous Application No. 15537, 15538, 15539 of 2021
Decided On : 29-11-2021
Arbitration and Conciliation Act - Challenge to Arbitral Award - Section 34 - The petitioner challenged an arbitral award passed by the Arbitral Tribunal. The petitioner contended that the Contract in question was discharged by accord and satisfaction, and the impugned award was vitiated on the ground of patent illegality. The Arbitral Tribunal partly allowed the claims and awarded a sum of Rs. 92,69,297/- along with interest. The petitioner assailed the impugned award on limited grounds.
Fact of the Case:
The petitioner issued a Notice Inviting Tenders for construction work. The works were completed, and the final bill was submitted. The respondent claimed balance payment, which was not accepted. The respondent invoked the arbitration agreement and sought reference of its claims to arbitration. The Arbitral Tribunal partly allowed the claims and awarded a sum of Rs. 92,69,297/- along with interest.
Finding of the Court:
The Court found that the impugned award was not vitiated on the ground of patent illegality. The Court held that the decision of the Arbitral Tribunal was based on evidence and material on record. The Court dismissed the petition and all pending applications.
Issues: The issues included the discharge of the Contract by accord and satisfaction, award of interest on Performance Guarantee, and the validity of the claims made by the respondent.
Ratio Decidendi: The Court held that the decision of the Arbitral Tribunal was based on evidence and material on record. The Court also found no ground to interfere with the award of interest and bank guarantee charges. The Court dismissed the petition and all pending applications.
Final Decision: The petition was dismissed, and all pending applications were also disposed of.
JUDGMENT
Vibhu Bakhru, J. - The petitioner has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereafter the A&C Act) challenging an arbitral award dated 14.07.2020 (hereafter the impugned award) passed by the Arbitral Tribunal comprising of a Sole Arbitrator (hereafter the Arbitral Tribunal).
2. The petitioner states that after the impugned award was delivered, the parties filed an application under Section 33 of the A&C Act seeking certain corrections. The said application was disposed of by the Arbitral Tribunal on 27.08.2020 and therefore, the period of limitation under Section 34(3) of the A&C Act is required to be reckoned from that date.
3. The petitioner states that on 10.12.2020, the petitioner filed its petition under Section 34 before the District Court, which was OMP (COMM) 103/2020 captioned Union of India v. M/s Aadhar Stumbh Township Pvt. Ltd.. However, the said petition was disposed of as withdrawn as the learned District Judge found that the court did not have pecuniary jurisdiction to entertain the said petition.
Factual Background
4. The petitioner [CPWD, Ministry of Urban Development, Government of India] had issued a Notice Inviting Tenders (NIT) for the construction of office building and staff quarters at Mandawali, Fazalpur, Delhi [SH. C/o T-III-16 Nos. and T-II-32 Nos. (8 Story)] and basement including an internal electrical installation. The respondent submitted its bid, which was opened on 09.10.2012. The respondent was declared successful and the petitioner issued a Letter of Intent (hereinafter LoI) dated 30.01.2013 for awarding the Contract in favour of the respondent. The aforesaid Contract awarded to the respondent had a negotiated value of Rs. 10,70,67,114/-, which was about 10.35% below the estimated cost of Rs. 11,94,26,929/-.
5. The date of commencement of the work was stipulated as fifteen days after issuance of the LoI. Thus, the works were to commence on 14.02.2013. The Contract was to be completed within a period of 450 days and the expected date of completion was agreed as 09.05.2014.
6. The works were completed on 19.06.2015. There is some controversy regarding the date of completion of the works. The petitioner claims that the parties had agreed that the works were completed on 19.06.2015, however, the physical works were completed on 21.06.2021. However, this controversy is not material.
7. The final bill was submitted on 17.09.2015 and the respondent claimed that the balance amount of Rs. 4,14,19,475/- was due. Thereafter, on 15.10.2015, the respondent applied for extension of time, which was granted without levy of any compensation.
8. The final bill was paid on 29.08.2016. The respondent had made an endorsement, which reads as 15th bill accepted with measurement on account of full and final. Thereafter, on 28.09.2016, the respondent sent a letter demanding the balance payment payable under the final bill. It claimed that it had only received part payment of the amounts due to it.
9. The demand raised by the respondent was not accepted. Consequently, on 15.10.2016, the respondent sent a letter to the Superintendent Engineer raising certain claims and further, stating that the endorsement made by it for receiving part payment of the final bill was under coercion and economic duress. The said Superintendent Engineer did not accept the claims as raised.
10. Thereafter, the respondent sent a letter dated 23.01.2017 referring its claims to the concerned Chief Engineer with a request that a Dispute Resolution Committee (DRC) be constituted in terms of Clause 25(1) of the General Conditions of Contract (GCC).
11. Pursuant to the request made by the respondent, a DRC was constituted. It considered the claims made by the respondent and rendered its decision on 19.04.2018 directing the petitioner to make a payment of Rs. 92,69,297/- to the respondent. The respondent accepted the said amount while reserving its right to pursue the remaining claims in arbitratio
Union of India & Ors. vs. M/s Master Construction Co.: (2011) 12 SCC 349
The main legal point established in the judgment is that the decision of the Arbitral Tribunal must be based on evidence and material on record, and the Court will not interfere with the award unless....
Claims can still be made post-final bill if made under coercion; the final arbiter's decisions should not contravene public policy.
The arbitral tribunal's decision to deny claims for damages due to lack of supporting evidence is valid under Section 34 of the Arbitration and Conciliation Act, emphasizing minimal judicial interfer....
The main legal point established in the judgment is the limited grounds for challenging arbitral awards under Section 34 of the A&C Act, emphasizing the principles of public policy and fundamental In....
Failure to raise claims for escalation in a timely manner and acceptance of payments in full and final settlement preclude further claims.
The Arbitral Tribunal has considerable discretion in evaluating evidence and interpreting contract clauses, and its decision cannot be interfered with unless found to be patently illegal or in confli....
The Arbitral Tribunal's decision falls within its jurisdiction and does not amount to patent illegality, as it was based on a plausible interpretation of the exclusionary clause in the contracts and ....
Statutory limitation under Section 34 of the Arbitration Act is strict and cannot be relaxed without sufficient justification; defective petitions lead to being treated as non-est.
The Arbitral Tribunal's jurisdiction to consider claim amounts and reject specific claims under the Arbitration and Conciliation Act, 1996.
The court affirmed the limited scope of review under Section 34 of the Arbitration and Conciliation Act, emphasizing respect for arbitral awards unless stark violations of public policy or procedural....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.