IN THE HIGH COURT OF DELHI AT NEW DELHI
Vibhu Bakhru, J.
Director General Central - Appellant
Versus
Fibroplast Marine Private Limited - Respondent
O.M.P. (Comm) 511 of 2019 & Ia Nos. 17282 of 2019 and 17283 of 2019
Decided On : 04-05-2022
| Table of Content |
|---|
| 1. introduction of factual background and contractual obligations (Para 1 , 2 , 3 , 4 , 5 , 6 , 7 , 8 , 9 , 10 , 11 , 12 , 13 , 14 , 15 , 16) |
| 2. tribunal's analysis of claims for losses (Para 19 , 20 , 21 , 22 , 23 , 24) |
| 3. petitioner's arguments against the arbitral award (Para 26 , 27 , 28 , 29 , 30 , 31 , 32) |
| 4. legal principles on delay and public policy (Para 38 , 44) |
| 5. court's view on the arbitral tribunal's delay (Para 39 , 45) |
| 6. conclusion: impugned award set aside (Para 77 , 78 , 79) |
JUDGMENT
Vibhu Bakhru, J. - The petitioner has filed the present petition under Section 34 of the Arbitration and Conciliation Act, 1996 (hereafter the 'A&C Act') impugning an arbitral award dated 31.05.2019 (hereafter the 'impugned award') rendered by an Arbitral Tribunal comprising of a Sole Arbitrator (hereafter the 'Arbitral Tribunal').
2. On 17.07.2008, the petitioner floated a tender bearing no. U.II.708(A)/2008-09-PROC-(NDRF) inviting bids for supply of 288 numbers of Boat Assault Universal Type (hereafter 'BAUT') and 288 numbers of 50 HP Out Board Motor (hereafter 'OBM'). In response to the same, the respondent submitted its bid and was declared as the lowest bidder.
3. Subsequently, on 17.07.2009, the parties entered into an agreement bearing number U.II.708(A)/2008-09-PROC-(NDRF)-II for supply of 288 numbers of BAUTs and 288 numbers of OBMs (hereafter the 'Agreement') at a consideration of ?16,87,79,520/-. The respondent was liable to pay inspection charges quantified at 2% of the said contract value along with applicable service tax as levied by the Inspecting Agency under the Directorate General Quality Assurance, Ministry of Defence (hereafter 'CQAE').
4. In terms of the Agreement, the respondent was required to submit two pilot samples of the BAUTs and OBMs within a period of two months from the date of the supply order, that is, by 15.09.2009. However, the respondent was unable to comply with the deadline due to various reasons, which it stated were beyond its control. By its letter dated 03.09.2009, it sought extension of one month to submit the two pilot samples. The petitioner accepted the same and by its letter dated 15.09.2009, extended the time till 15.10.2009. On 08.10.2009, the pilot samples were delivered and was received by the CQAE on 12.10.2009.
5. Thereafter, by its letter dated 21.10.2009, the CQAE raised concerns in respect of the pilot samples delivered by the respondent on the ground that the same was submitted after the expiry of the stipulated delivery period. However, in response to the said letter, the respondent informed the CQAE that the petitioner had already extended the time period for delivery of the pilot samples and further, requested the petitioner to issue a formal delivery period extension to the CQAE. The respondent informed the CQAE that it had provided the raw material test specimen and further assured it, that a delivery inspection would be submitted within a period of ten days.
6. The CQAE rejected the pilot samples submitted by the respondent due to certain discrepancies in some materials and informed the same to the respondent by its letter dated 15.03.2010. The respondent requested the CQAE to re-test the pilot samples and the said request was accepted by the CQAE on 15.04.2010. On 28.04.2010, the respondent also provided fresh samples, however, it was found that the same did not conform to the specifications.
7. On 21.12.2010, the respondent submitted fresh samples for evaluation by the CQAE and the pilot samples were finally approved by the CQAE on 24.03.2011. Accordingly, the respondent received clearance for bulk production. The CQAE, by its letter dated 24.03.2011, informed the petitioner to issue re-fixation of the bulk delivery period till 24.09.2011 in terms of Clause 9(ii) of the Agreement. On 04.04.2011, the respondent, once again, requested the petitioner to
Oil India Ltd. v. Essar Oil: 192 (2012) DLT 417
The arbitral tribunal's decision to deny claims for damages due to lack of supporting evidence is valid under Section 34 of the Arbitration and Conciliation Act, emphasizing minimal judicial interfer....
The main legal point established in the judgment is the limited grounds for challenging arbitral awards under Section 34 of the A&C Act, emphasizing the principles of public policy and fundamental In....
Excessive and unexplained delay in arbitral proceedings vitiates the award, impacting fairness and leading to its annulment under public policy and patent illegality.
The main legal point established in the judgment is that the decision of the Arbitral Tribunal must be based on evidence and material on record, and the Court will not interfere with the award unless....
An arbitrator's decision can only be challenged under limited grounds; violations must be significant to justify setting aside the award.
Statutory limitation under Section 34 of the Arbitration Act is strict and cannot be relaxed without sufficient justification; defective petitions lead to being treated as non-est.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.