SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 Supreme(Del) 1617

IN THE HIGH COURT OF DELHI AT NEW DELHI
C. Hari Shankar, J.
National Highways Authority Of India - Appellant
Versus
M/s Abhijeet Angul Sambalpur Toll Road Limited - Respondent
Original Miscellaneous Petition (COMM) No. 224 of 2021, I.A. No. 9860 of 2021
Decided On : 28-02-2022

Advocates appeared:
Aishwarya Bhati, Advocate, Neetica Sharma, Advocate, Nitin Chowdhary, Advocate, Sandeep Bajaj, Advocate, Devansh Jain, Advocate, Vipul Jai, Advocate

The right to file counter-claims exists independent of any liberty granted by the arbitral tribunal, and the tribunal can reject counter-claims on various grounds. The definition of 'interim award' and its amenability to challenge under Section 34 were clarified.

Headnote:

Section 34 - Arbitration and Conciliation Act, 1996 - 17

Fact of the Case:

The petition under Section 34 of the Arbitration and Conciliation Act, 1996 ('the 1996 act') challenges the arbitral tribunal's decision to not entertain or adjudicate any counter-claims raised by the petitioner-NHaI, except the counter-claim for ?12.2 crores.

Finding of the Court:

The court found that the arbitral tribunal's decision was based on a misreading of the earlier order and that the right of the petitioner to file counter-claims exists independent of any liberty granted by the tribunal. The tribunal's decision was quashed and set aside.

Issues: The issues revolved around the interpretation of the arbitral tribunal's earlier order, the authority of the tribunal to reject counter-claims, and the maintainability of the petition under Section 34.

Ratio Decidendi: The court held that the right of the petitioner to file counter-claims exists independent of any liberty granted by the tribunal and that the tribunal could reject counter-claims on grounds such as merits, limitation, or arbitrability. The court also clarified the definition of 'interim award' and its amenability to challenge under Section 34.

Final Decision: The petition was allowed, and the arbitral tribunal's decision was quashed and set aside with no order as to costs.

JUDGMENT

C. Hari Shankar, J. - This petition under Section 34 of the arbitration and Conciliation act, 1996 ('the 1996 act'), assails para 6.1.7 of order dated 26th august, 2020 passed by the majority of the learned arbitral Tribunal, which consisted of three members, whereby the learned arbitral Tribunal has held that it would not entertain or adjudicate any of the counter-claims raised by the petitioner-NHaI vide its application dated 4th February, 2020 except the counter-claim for ?12.2 crores. The impugned para 6.1.7 reads thus:

    '6. 1.7 It is seen that the aT had allowed the Respondent to file a CounterClaimfor the amount of Rs.12.2 Crores only, as claimed through theirapplication dated 04.02.2020.

    However, the Respondent nave filedthree Counter-Claims.

    The two Counter-Claims besides the Counter-Claim for Rs. 12.2 Crores have been filed without any authority.

    The aT reiterates that it wilt adjudicate only one Counter-Claim forRs.12.2 Crores as per liberty allowed to the Responding for filing theparticular Counter-C1aim.

    The-aT shall not entertain and adjudicate-other Counter-Claims.'

    2. The impugned majority decision proceeds on the premise that the learned arbitral Tribunal had, vide its earlier order (dated 24th September, 2019) allowed NHaI to file a counter-claim 'for the amount of ? 12.2 crores only'.

    3. From a reading of the order dated 24thSeptember, 2019 passed by the learned arbitral Tribunal, it is clear that this assumption of the learned arbitral Tribunal is actually predicated on a misreading of the order dated 24th September, 2019. The order dated 24th September, 2019, which was passed by the learned arbitral Tribunal on an application by the NHaI under Section 17 of the 1996 act, does not state that the petitioner would file a counterclaim only for an amount of ?12.2 crores. For ready reference, the entire order dated 24th September, 2019 is reproduced thus:

      'BEFORE THE aRBITRaL TRIBUNaL COMPRISING OF

      Shri O.P. Goel PRESIDING aRBITRaTOR

      Shri Sudesh Dhiman aRBITRaTOR

      Shri K.K. Singal aRBITRaTOR

      IN THE MaTTER OF aRBITRaTION BETWEEN

      M/s abhijeet angul Sambalpur Toll

      Road Limited. ..... Claimant/Concessionaire

      and

      National Highways

      authority of India ..... Respondent/Employer

      24.09.2019

      Sub: Four Laning of angul-Sambalpur Section of NH-42 from Km 112.00 toKm 265.00 in the State of Orissa under NHDP-IV to be executed asBOT (Toll) on DBFOT Pattern. Concession agreement dated13.03.2012

      Re: application under Section 17 of the arbitration & Conciliation act, 1996on behalf of National Highways authority of India (Respondent)seeking withdrawal of money towards bank guarantee deposited withState Bank of India Nagpur in the High Court of Delhi along withinterest accrued thereon w.e.f. 20.09.2013.

      The Respondent has filed an application under Section 17 of the arbitration& Conciliation act, 1996 on 04.02.2019. The Claimant filed their reply to theapplication vide letter dated 02.03.2019. The Respondent did not want tofile their rejoinder. arguments were presented by the parties during hearing.Both parties filed their Brief Notes.

      Respondent's case:

      1. as per Concession agreement, the Claimant was required to submit aperformance guarantee of Rs.61 crores. This has not been done. Thereasons advanced by the Claimant for not furnishing performanceguarantee are not relevant. against the request of extension of timefor 120 days for submission of the performance guarantee, period of7 days was allowed by the Respondent. Despite thatthe performanceguarantee was not furnished.

      2. The Claimant filed an application before Hon'ble High Court of Delhiseeking stay on encashment of the bank guarantee (bid security) ofRs. 12.2 crores available with the Respondent. The Hon'ble High Courtstayed the invocation of bank guarantee till final orders. The HighCourt decided on 22.8.2013 to get the money deposited in the court.On the money being deposited with the Registry of the Court, theRegistry will invest the same in an interest bearing fixed deposit.Thefinal orders

          Click Here to Read the rest of this document
          1
          2
          3
          4
          5
          6
          7
          8
          9
          10
          11
          SupremeToday Portrait Ad
          supreme today icon
          logo-black

          An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

          Please visit our Training & Support
          Center or Contact Us for assistance

          qr

          Scan Me!

          India’s Legal research and Law Firm App, Download now!

          For Daily Legal Updates, Join us on :

          whatsapp-icon Back to top