IN THE HIGH COURT OF DELHI AT NEW DELHI
Vibhu Bakhru, J.
Tata Motors Ltd - Appellant
Versus
Delhi Transport Corporation - Respondent
Original Miscellaneous Petition (I) (COMM.) No. 62 of 2021, Miscellaneous Application No. 9829, 12274, 14103 of 2021, 656 of 2022
Decided On : 27-01-2022
arbitration - Stay of impugned communication - Section 9 of the Arbitration & Conciliation Act, 1996 - [Section 9] - The court discussed the provisions of Section 9 of the Arbitration & Conciliation Act, 1996 and the implications of the arbitral award dated 16.08.2017 on the dispute regarding excess consumption of CNG. The court restrained the respondent from withholding any amount against the alleged excess consumption of CNG, subject to the petitioner furnishing an unconditional Bank Guarantee for said amount in favor of the respondent.
Fact of the Case:
The petitioner, TML, filed a petition under Section 9 of the Arbitration & Conciliation Act, 1996, seeking stay of an impugned communication from the respondent, DTC, regarding the alleged excess consumption of CNG and deductions from payments due to TML.
Finding of the Court:
The court found that the dispute regarding excess consumption of CNG was covered in favor of TML by the arbitral award dated 16.08.2017. The court restrained the respondent from withholding any amount against the alleged excess consumption of CNG, subject to the petitioner furnishing an unconditional Bank Guarantee for said amount in favor of the respondent.
Issues: Dispute over excess consumption of CNG, Stay of impugned communication, Effect of arbitral award on the dispute, Fresh arbitration invoked by TML
Ratio Decidendi: The court held that the respondent cannot withhold amounts from the invoices raised by TML, as the dispute regarding excess consumption of CNG was covered in favor of TML by the arbitral award dated 16.08.2017. The court also found that TML's invocation of a fresh arbitration under Section 21 of the Arbitration & Conciliation Act, 1996, was justified due to the respondent's inconsistent stand.
Final Decision: The court restrained the respondent from withholding any amount against the alleged excess consumption of CNG, subject to the petitioner furnishing an unconditional Bank Guarantee for said amount in favor of the respondent. The petition was disposed of in the aforesaid terms.
JUDGMENT
Vibhu Bakhru, J. - The petitioner (hereafter 'TML') has filed the present petition under Section 9 of the arbitration & Conciliation act, 1996 (hereinafter 'the a&C act'), inter alia, praying as under:
'(a) Stay of the impugned communication dated 05.02.2021 bearing no. CWS-I/DY.CGM(M)/Plng./ 2021/08 addressed by the Respondent to Petitioner;
(b) Pass an order from restraining the Respondent acting upon and giving effect including adjusting/recovering of the alleged cost of excess CNG (Rs.127.86 crores approx.) consumed as per Fuel Efficiency Norms in terms of the impugned communication dated 05.02.2021 bearing no. CWS-I/DY.CGM(M)/Plng./ 2021/08 addressed by the Respondent to Petitioner, from the contractual quarterly payments towards aMC or from any other payment due; or
(c) Pass ex-parte ad-interim orders in terms of aforementioned prayer (a) & (b) above and confirm the same upon notice pending final adjudication of the present petition;
2. TML is a company engaged in the business of manufacturing and selling wide range of buses as well as light, medium and heavy commercial vehicles. The respondent (hereafter 'DTC') is a statutory body and is the principal public transport operator in Delhi.
3. On 31.01.2008, DTC issued a Request for Proposal (RFP) inviting offers for supply of 'CNG propelled bus chassis and fully built up CNG buses for supply of Low Floor CNG propelled City type non aC and aC buses'. The bidders were also responsible for maintaining the said buses for a length of 7,50,000 kms. TML participated in the said tender and was declared successful. Subsequently, the parties entered into an agreement dated 18.10.2008, whereby TML agreed to provide buses and maintain the same for 7,50,000 kms.
4. Certain disputes arose between the parties in connection with the contract in question. The said disputes were referred to arbitration. One of the disputes raised in the arbitration related to the consumption norms of CNG. TML contended that the consumption norms are covered under Clause 24.4.1 of the General Conditions of Contract (GCC) issued along with the Request for Proposal. However, DTC contended that excess consumption of CNG was required to be calculated and recovered in terms of Clause 46.16 of the annual Maintenance Contract (aMC).
5. The said dispute was adjudicated in favour of TML in terms of the arbitral award dated 16.08.2017. DTC has not accepted the said award and has impugned the same under Section 34 of the a&C act [OMP(COMM) No.425/2017]. However, the said award has not been stayed.
6. Notwithstanding that TML has prevailed in the arbitration, DTC is insisting in making deductions on account of fuel efficiency norms from the amounts payable to TML, as according to it, excess consumption is required to be computed and recovered under Clause 46.16 of the aMC. aggrieved by the said deductions, TML has filed the present petition.
7. This Court has pointedly asked Mr. Vashisht, learned senior counsel appearing for DTC, whether the controversy is covered in favour of TML in terms of the arbitral award dated 16.08.2017. He fairly conceded in the affirmative. He also stated that there was no dispute that if the said arbitral award is sustained, the deductions sought to be made pursuant to the letter dated 05.02.2021, would be impermissible. He, however, stated that since the period covered under the arbitration (which culminated in the arbitral award dated 16.08.2017) was different, DTC was not precluded to deduct the amount against excess consumption, according to its stand, till the matter is finally decided.
8. Mr. Vashisht further states that TML has invoked a fresh arbitration by issuing two notices under Section 21 of the a&C act being notices dated 13.08.2020 and 09.10.2020. These notices are premised on the basis that a fresh dispute has arisen. He states that TML cannot be permitted to contend that the issues are covered under the earlier arbitral award dated 16.08.2017 because it has sought a fre
The court emphasized the importance of upholding the arbitral award and restrained the respondent from making deductions based on a dispute that was already covered in favor of the petitioner by the ....
Deductions contrary to an arbitral award are impermissible. Fresh arbitration notices can be issued if new disputes arise, despite prior awards.
The main legal point established in the judgment is the power of the Arbitral Tribunal to grant interim mandatory injunction orders under Section 17 and the limitations of constructive res judicata.
A rise in commodity prices does not frustrate a contract; parties must fulfill contractual obligations despite financial challenges.
The court confirmed that under Section 34 of the Arbitration Act, an arbitral award can only be set aside on narrow grounds, emphasizing the interpretation of contract terms is primarily for the arbi....
The court emphasized that arbitrators must operate within the contractual provisions; awards can be overturned if arbitrators act beyond their jurisdiction, particularly regarding deductions not expl....
The main legal principle established in the judgment is that the arbitrator's role is to arbitrate within the terms of the contract and not to interpret or rewrite the contract. The arbitrator cannot....
An arbitral award cannot be set aside for lacking elaborate reasoning but must provide intelligible bases; deductions for shortfall in MGCC are impermissible without clear contract provisions.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.