SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Del) 36

IN THE HIGH COURT OF DELHI AT NEW DELHI
AVNEESH JHINGAN, J.
Steel Authority of India Limited – Appellant
Versus
M/s Primetals Technologies India Pvt. Ltd. – Respondent
O.M.P. (COMM) No. 451 of 2023, I.A. No. 21931 of 2023
Decided On : 23-02-2026

Advocates Appeared:
For the Appellants : Siddharth Yadav, Ashish Tiwari, Anurag Tiwari, Sahib Patel
For the Respondents: Rajesh Markanda, Keshri Kumar, Saurav Markanda

An arbitral award cannot be set aside for lacking elaborate reasoning but must provide intelligible bases; deductions for shortfall in MGCC are impermissible without clear contract provisions.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Challenge to arbitral award - Claim for reimbursement for shortfall in Minimum Guaranteed CENVAT Credit (MGCC) - Deduction of MGCC not permitted in absence of pertinent clause in contract - Claims filed within limitation period due to pandemic extension - Award reasonable and adequately reasoned. (Paras 20, 26)

Facts of the case:
The appellant challenged the arbitral award regarding deductions made from contract price due to shortfall in MGCC against a backdrop of a contractual dispute over CENVAT credits for work completed on 01.06.2007, with ongoing proceedings leading to arbitration initiated in 2021 after failed conciliation attempts.

Findings of Court:
The court found that the arbitrator had correctly held that the deduction for shortfall in MGCC could not apply due to the lack of a specific contractual clause permitting such a deduction. The claim was deemed timely filed, and the costs awarded were appropriate.

Issues: The main issues involved the applicability of limitation laws, waiver of claims due to previous communications, and whether the arbitrator's decision on MGCC was valid based on the contract's terms.

Ratio Decidendi: The court concluded that the interpretation of the contractual clauses by the arbitrator was correct, with no clause warranting MGCC deductions. The award was not substantially flawed or unreasonable in its conclusions.

Result: Petition dismissed.

Table of Content
1. contract execution and certificate issuance timeline. (Para 2 , 3)
2. arguments regarding limitation and deductions. (Para 4 , 5)
3. court's analysis of limitation claims and waiver. (Para 6 , 7 , 8 , 9 , 10)
4. interpretation of contract clauses relating to mgcc. (Para 11 , 12 , 13 , 14 , 15 , 16 , 17 , 18 , 19)
5. judicial perspective on arbitral awards and interpretations. (Para 20 , 21)
6. court upholds arbitral interpretation on deductions. (Para 22 , 23 , 24 , 25)
7. final conclusion and dismissal of the petition. (Para 26 , 27)

JUDGMENT :

AVNEESH JHINGAN, J.

1. This petition is filed under Section 34 of the Arbitration and Conciliation Act, 1996 (for short "the Act") challenging the arbitral award dated 02.05.2023, modified vide order dated 07.07.2023.

FACTS

2. The facts in brief emerging from the record are that the parties to the lis executed a contract on 01.06.2007 whereby the respondent was to replace "Existing MG Sets for Roughing and Finishing Stand Drives Motors of Plate Mill by Digital Thyristor Converters" at Bhilai Steel Plant (hereinafter "BSP"). The work was to be completed by the respondent within twenty-one months and was for a price of Rs.44,93,20,127/-. The contract was executed, the commissioning certificate and the final acceptance certificate were issued on 03.08.2010 and 24.05.2013 respectively. The final invoices dated 28.05.2018 were submitted by the respondent and the payment was released on 10.07.2018 after deducting liquidated damages (in short "LD") and Rs.1,40,38,523/- for shortfall in minimum guaranteed CENVAT credit (in short "MGCC"). On failure of conciliation attempts, the arbitration proceedings as per clause 6 of the General Contract Conditions (in short "GCC") were invoked on 28.12.2021.

3. The arbitrator framed seven issues:

“1. Whether the claims of the Claimant are barred by Limitation?

2. Whether the claims are barred by principles of estoppel, waiver and acquiescence?

3. Whether the Claimant is entitled to the declaration from this Tribunal that the amount Rs.1,40,38,523/- deducted by the Respondent on account of shortfall of guaranteed CENVAT is bad in law?

4. Whether the Claimant is entitled to reimbursement of Rs.1,40,38,523/- deducted by the Respondent on account of shortfall of guaranteed CENVAT.

5. Whether the Respondent has withheld any amount on account of Entry Tax over and above the withheld amounts towards shortfall in CENVAT Credit and levy of Liquidated damages?

If yes, what amount?

6. Whether the Claimant is entitled to reimbursement of Rs.31,02,155/- on account deduction made against Entry Tax?

7. Whether the Claimant is entitled to interest and if so and, if so, at what rate?

8. Relief and costs;”

3.1 Issues 1, 2, 4 and 7 were decided in favour of the respondent/claimant. The claim was held to be within limitation and there was no estoppel, waiver or acquiescence by the respondent. The deduction of Rs.1,40,38,523/- on account of shortfall in MGCC was faulted. Interest pendente lite @12% and post-award interest @9% were awarded. The respondent was held entitled to costs of Rs.18,20,644/-. Hence, the present petition.

SUBMISSION OF THE PETITIONER

4. Learned senior counsel for the petitioner contends that a notice dated 17.05.2014 was issued for imposing LD and deducting the shortfall in MGCC and therefore, the initiation of arbitration on 28.12.2021 is time-barred.

4.1 It is contended that in response to the notice dated 17.05.2014 no objection was raised against the deduction on account of shortfall in MGCC, the right to contest the deduction was waived and the respondent was estopped from invoking arbitration. Further that at the time of final discharge the respondent undertook not to raise any claim and an affidavit dated 09.05.2015 to a similar effect was executed.

4.2 It is canvassed that the arbitrator wrongly held that vide letter dated 21.05.2018 directions were issued by the petitioner for submission of the final invoices.

4.3 The argument is that the arbitrator h

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top