SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2026 Supreme(Del) 69

IN THE HIGH COURT OF DELHI AT NEW DELHI
AVNEESH JHINGAN, J.
Steel Authority Of India Limited -Petitioner
Versus
Primetals Technologies India Pvt. Ltd. - Respondent
O.M.P. (COMM) 233 of 2025 & I.A. 15455 of 2025
Decided On : 18-02-2026

Advocates:
Advocate Appeared:
For the Petitioner: Mr. Rajshekhar Rao, Sr. Adv.with Mr. Samaksh Goyal, Adv.
For the Respondent: Mr. Rajesh Markanda, Mr. Keshri Kumar & Mr. Saurav Markanda, Advs.

The court confirmed that under Section 34 of the Arbitration Act, an arbitral award can only be set aside on narrow grounds, emphasizing the interpretation of contract terms is primarily for the arbitral tribunal.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Challenges to Arbitration Award - Petition against arbitral award regarding deduction from contract value due to shortfall in Minimum Guaranteed CENVAT Credit. Court found the claim not barred by limitation, as the cause of action accrued upon deduction, and upheld the tribunal’s interpretation that deductions are to be made from the gross contract price and not the net contract price. (Paras 10, 11, 12)

(B) Limitation - The court emphasized that claims are not deemed time-barred as long as arbitration proceedings were invoked within the permissible time frame post cause of action. No merit in the petitioner's limitation argument regarding reimbursement of excise duty. (Paras 3.1, 8)

Facts of the case:
The parties entered a contract for a galvanizing line project, where post-completion deductions were disputed over Minimum Guaranteed CENVAT Credit. The tribunal ruled against the petitioner on limitations and deductions based on previous court rulings. (Paras 2, 2.2)

Findings of Court:
The tribunal's interpretation of contract clauses was affirmed, emphasizing deductions from gross contract price due to clear contractual terms. The findings were supported by precedent. (Paras 9, 12)

Issues: The court addressed questions of whether claims were barred by limitation and the proper application of contract terms regarding CENVAT deductions. (Paras 4, 11)

Ratio Decidendi: The tribunal's interpretation of the contract concerning deductions was upheld as reasonable and within legal standards, reiterating that courts do not substitute their interpretations unless clearly unreasonable. (Paras 11.1, 12)

Result: Petition dismissed.

Table of Content
1. challenge to an arbitral award under section 34 (Para 1 , 2)
2. petitioner's argument on limitation and contract interpretation (Para 3)
3. respondent's defense against petitioner's claims (Para 4)
4. tribunal's reasoning on deductions and contract terms (Para 7 , 8 , 9 , 10)
5. scope of interference under section 34 (Para 11)
6. conclusion on tribunal's decision and lack of grounds for interference (Para 12 , 13)
7. final dismissal of the petition (Para 14)

JUDGMENT :

AVNEESH JHINGAN, J.

1. This petition is filed under Section 34 of the Arbitration and Conciliation Act, 1996 (for short 'the Act') challenging the arbitral award dated 28.08.2024 read with the addendum dated 22.11.2024.

FACTS

2. The brief facts are that the parties to the lis entered into a contract on 03.03.2008 for setting up a Hot Dip Galvanising Line (HDGL) and Electrolytic Cleaning Line (ECL). The contract amount was Rs.223,78,09,443/- for HDGL and Rs.67,77,77,720/- for ECL and was to be executed within twenty-eight months. The projects were successfully commissioned by the respondent on 26.06.2018 and 20.02.2017 respectively. The final acceptance certificates were issued on 05.05.2023 and 15.02.2019 respectively.

2.1 The contract provided for a minimum guaranteed CENVAT credit (for short 'MGCC') to be passed on to the petitioner. Deduction for shortfall in MGCC from the net contract value led to the invocation of arbitration proceedings.

2.2 The Arbitral Tribunal (for short 'tribunal') decided the issue against the petitioner relying upon the decision of this court in Steel Authority of India Limited v. M/s Primetals Technologies India Pvt. Limited (formerly known as Siemens VAI Metals Technologies Pvt. Ltd.) 2020 SCC OnLine Del 2496. It was considered that the issue has been finally decided inter se the parties by learned single judge of this court and the decision was upheld by the Division Bench and the SLP was dismissed.

CONTENTIONS OF PETITIONER

3. Learned senior counsel for the petitioner contends that claim no.1 relating to the deduction made on account of shortfall in MGCC is barred by limitation. It is submitted that the cause of action arose on expiry of forty-five days after submission of the invoices dated 03.04.2017, 10.09.2018 and 30.10.2018 but the arbitration proceedings were invoked on 02.03.2022 i.e. beyond three years. The argument is that clause 12.1.6 of the General Conditions of Contract (for short 'GCC') provides that payment was to be made within forty- five days of submission of the invoices and thereafter the respondent had cause of action.

3.1 Claim no. 2 pertaining to reimbursement of excise duty is contested to be barred by limitation in view of clause 12.1.6 of the GCC. It is submitted that payment of the invoices issued between 28.11.2009 and 07.12.2016 was to be made within forty-five days and thereafter grievance if any arose however, the arbitration proceedings were invoked after expiry of three years on 02.03.2022.

3.2 The contention is that in terms of clause 14.5.6 of the GCC in the eventuality of a shortfall in MGCC the petitioner was entitled to deduct the corresponding amount from the net contract value to compensate for the shortfall. Lastly, it is submitted that the tribunal ignored the terms of the contract in holding that the deduction could have been made either from the gross or the net contract value.

ARGUMENTS OF RESPONDENT

4. Learned counsel for the respondent defends the impugned award and submits that neither claim no. 1 nor claim no. 2 is barred by limitation. Vis-a-vis claim no.1 it is argued that the cause of action arose upon deduction of the amount on 09.03.2019 and not upon submission of the invoices. Qua claim no.2 it is emphasized that till 14.02.2022 the reimbursement of excise duty was under active consideration by the petitioner.

4.1 The submission is that the tribunal while interpreting clause 14.5.6 of the contract relied upon the judgment of this Court in Steel Authority of India v. Primetal

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon telegram-icon
whatsapp-icon Back to top