SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2022 Supreme(Del) 1494

IN THE HIGH COURT OF DELHI AT NEW DELHI
C. Hari Shankar, J.
Hindustan Cleanenergy Limited - Appellant
Versus
Maif Investments India 2 Pte Limited & Ors. - Respondents
O.M.P.(I) (Comm.) 308 of 2020 and I.As. 8634 of 2020, 8635 of 2020
Decided On : 20-01-2022

Advocates appeared:
Dr. Abhishek Manu Singhvi, Sr. Advocate with Mr. Vijay Aggarwal, Ms. Barkha Rastogi, Mr. Shailesh Pandey and Mr. Deepanshu Choithani, Advocate, for the Appellant; Mr. Rajiv Nayar, Sr. Advocate, with Mr. Jafar Alam, Ms. Shivani Khandekar, Mr. Pranav Jain, Mr. Sidhanth; Kumar and Mr. Samykya Mukku, Advocate, for the Respondent.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 9 - Interim measures in arbitration - Petitions arose from multiple agreements concerning solar power projects - Court restricted actions against the petitioner pending arbitration, given it had secured marketable title for 88% of the disputed land - COVID-19 pandemic cited for delays in obtaining titles for remaining land - Findings emphasized limited jurisdiction under Section 9 to prevent infringing on arbitral authority. (Paras 5-6, 62-67, 83)

(B) Legal Obligations - The court clarified that the petitioner had made substantial efforts to comply with contractual obligations under the Framework Agreement despite the pandemic - Issues regarding whether time was of the essence and whether clause 3.9 was penal in nature to be adjudicated by arbitral tribunal, not the court. (Paras 48-56)

Facts of the case:
The petitioner sought to prevent enforcement of pledged securities after default notices citing failure to secure land titles, arguing all efforts were made to comply with contract obligations, with 88% compliant and delays due to COVID-19. (Paras 7-21)

Findings of Court:
The court determined the invocation of the pledge could be restrained pending arbitration and that a prima facie case existed to warrant protection against coercive actions by the respondents. (Paras 62-68)

Issues: Issues included the nature of clause 3.9, whether petitioner had defaulted, and implications of the pandemic on contractual obligations. (Paras 49-56)

Ratio Decidendi: The court ruled it could not delve into the merits of the case without influencing the arbitral tribunal, emphasizing the necessity of interim protection to ensure arbitration was not frustrated. (Paras 36-39, 70-82)

Result: Interim protection granted, restraining respondents from invoking the pledge until further orders from the arbitration tribunal.

Table of Content
1. overview of parties and agreements in dispute (Para 1 , 2 , 3 , 4 , 19)
2. jurisdiction and limitations of section 9 (Para 5 , 7 , 28)
3. arguments regarding compliance and contractual obligations (Para 6 , 25 , 26)
4. court observations on the status of compliance (Para 8 , 9 , 10 , 11 , 12)
5. final orders and conclusions (Para 68 , 83 , 84)

JUDGMENT

1. These petitions, preferred under Section 9 of the Arbitration and Conciliation Act, 1996 (the 1996 Act) arise out of the same set of agreements. They are, therefore, being disposed of by a common judgement though, as the disputes in the petitions are distinct, they would be dealt with separately.

OMP (I) (COMM) 308/2020

2. Given the nature of the dispute in this petition, it would be appropriate, at the outset, to introduce the dramatis personae.

3. The petitioner provides clean energy solutions and, inter alia, sets up and implements Solar Power Projects. Kindle Engineering and Construction Pvt Ltd, Responsive SUTIP Ltd and Ujjawala Power Pvt Ltd, Respondents 3, 4 and 5, are three of 18 Special Purpose Vehicles (SPVs), set up by the petitioner for executing 18 Solar Power Projects. Respondents 1 and 2, by agreement with the petitioner, purchased the Solar Power Projects. Respondent 6 is a Debenture Trustee, which holds in trust the Kindle Pledge constituting the Kindle restricted shares of Respondent 3, for the benefit of Respondent 1.

4. Respondents 1 and 2 are Investment Management Firms incorporated in Singapore. They have no official presence in India, though they are registered as a Foreign Portfolio Investor and a Foreign Venture Capital Investor, with the Securities and Exchange Board of India (SEBI) under the SEBI (Foreign Portfolio Investor) Regulations, 2014 and the SEBI (Foreign Venture Capital Investors) Regulations, 2000 respectively.

A prefatory note

5. This Court is seized with a petition under Section 9 of the Arbitration and Conciliation Act, 1996 (the 1996 Act). The peripheries of jurisdiction of Section 9 Court are logistically circumscribed, the parameters of such circumscription being authoritatively delineated by the recent decision of a Division Bench of this Court in DLF Ltd. v. Leighton India Contractors Pvt. Ltd., 2021 SCC OnLine Del 3772 The Court is completely proscribed, while exercising Section 9 jurisdiction, in entering into detailed analysis of contractual clauses, which is a territory exclusively reserved for the Arbitral Tribunal. The limited extent to which the clauses of the agreements between the parties are of relevance to a Section 9 Court is for the Court to ascertain whether a case for granting interim protection, so as to prevent frustration of the arbitral proceedings or the rendition of an award, if it comes to be rendered in favour of the applicant.

6. The manner, detail and extent to which arguments were addressed in the present case and the exhaustive submissions advanced with respect to the intricacies of the contractual covenants, in my view, far exceeded the legitimate limits of discussion in a Section 9 proceeding.

The issue in précis

7. The controversy, in substance, is simple. The Framework Agreement dated 26th January, 2017, forming, as it were, the parent contract in the present case, required the petitioner to obtain marketable title in respect of certain lands of Respondents 4 and 5, from the Government of Gujarat. Failure, on the part of the petitioner, to obtain such marketable title within the stipulated period entitled Respondents 1 and 2, under the Framework Agreement, to redemption of the Optionally Cumulative Convertible Debentures (OCCDs) of Respondent 5 and transfer of the shares of Respondent 3, of a total value of ? 95 crores, for ? 1. The petitioner contends that marketable title has been obtained in respect of 88% of the disputed lands and that the application in respect of remaining 12% is presently pending with the Government of Gujarat. The time for obtaining marketable title, as originally f

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top