SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2023 Supreme(Del) 689

IN THE HIGH COURT OF DELHI AT NEW DELHI
SATISH CHANDRA SHARMA, SACHIN DATTA, JJ.
Rajo - Appellant
Versus
Delhi Building and Other Construction Workers Welfare Board and Another - Respondents
LPA No.209 Of 2023 & CM APPLs. No.14917 Of 2023, 14919 Of 2023
Decided On : 17-04-2023

Advocates Appeared:
For the Appellant : Mr. Chirayu Jain and Ms. Sakshi Dewangan, Advs.
For the Respondents: Mr. Abhay Dixit with Mr. Ankit Kumar, Ms. Avni Singh.

The main legal point established in the judgment is that the BOCW Act and Rules do not specify a timeline for processing pension applications, and the court emphasized the need for early submission of applications to expedite the pension process.

Headnote:

PENSION - Building and Other Construction Workers Act, 1996 - Rule 272 of the Delhi Building and Other Construction Workers Rules, 2002 - The court discussed the provisions of the BOCW Act and Rules, particularly Rule 272, and highlighted the absence of a specific timeline for processing pension applications. The court also emphasized the need for construction workers to be allowed to submit pension applications six months before becoming eligible, and directed the respondent Board to consider accepting early applications to expedite the pension process.

Fact of the Case:

The appellant sought release of pension under the Building and Other Construction Workers Act, 1996. The Single Judge held that the delay in sanctioning the pension was not inordinate and directed payment of interest at 6% per annum. The appellant appealed, seeking enhancement of interest from 6% to 18% on delayed payment of pension.

Finding of the Court:

The court found that the BOCW Act and Rules do not specify a timeline for processing pension applications and emphasized the need for early submission of applications. It upheld the Single Judge's decision on interest at 6% per annum and dismissed the appeal.

Issues: The issues involved the interpretation of Rule 272 of the BOCW Rules, the absence of a specific timeline for processing pension applications, and the appropriate interest rate for delayed pension payment.

Ratio Decidendi: The court held that the BOCW Act and Rules do not provide a specific timeline for processing pension applications and emphasized the need for early submission of applications. It upheld the Single Judge's decision on interest at 6% per annum.

Final Decision: The appeal was dismissed, and the court upheld the Single Judge's decision on interest at 6% per annum for delayed pension payment.

JUDGMENT :

CM APPL.14919/2023 (delay)

1. In view of the averments made in the application, the same is allowed and the delay stands condoned.

CM APPL.14917/2023 (for filing of additional documents)

2. This is an application seeking filing of certain additional documents.

3. Having considered the averments made in the application, the same is allowed and the additional documents, as referred to in the application are taken on record.

4. The application stands disposed of.

LPA 209/2023

5. The present appeal has been preferred against the judgment dated 10.01.2023 passed by the learned Single Judge of this Court in W.P.(C) 15941/2022. The said writ petition was filed by the appellant seeking that the respondent no. 1 be directed to release the pension payable to her under the Building and Other Construction Workers (Regulation of Employment and Conditions of Service) Act, 1996, [“the BOCW Act”] with interest @18% per annum.

6. Vide the impugned judgment, the learned Single Judge has, inter alia, held as under:—

    “6. Having considered the submissions of the learned counsel for the parties and perused the record, I find that while there is no dispute that the petitioner was entitled to receive pension w.e.f. 01.02.2021, it is also an admitted position that the requisite documents for sanction of pension were submitted by her only on 05.08.2022. In these circumstances, the respondent is justified in urging that pension could not be sanctioned in the petitioner's favour without her submitting the requisite documents and, therefore, it cannot be said that there was any inordinate delay on it's part in sanctioning the pension payable to the petitioner. Even though, both, the Act and the Rules are silent regarding the time period within which the pension must be sanctioned, in my view, the respondent, which is enjoined with a statutory duty to disburse pension in favour of these construction workers, who play a crucial role in the building of the society, ought to take expeditious steps to ensure that pension is released to them at the earliest.

7. In the present case, the petitioner submitted all the requisite documents on 05.08.2022 and therefore, even if a period of 45 days is taken as a reasonable period for the respondent to have processed the petitioner's application for grant of pension, there is still a delay of more than three months in sanctioning the pension in her favour. Learned counsel for the respondent, except for stating that the respondent is dealing with 16 lakhs registered building and construction workers, is unable to provide any justification for this delay. The pension in favour of the petitioner has been sanctioned only on 06.01.2023 and that too after she was compelled to approach this Court.

8. I have also considered the decisions of the Apex Court relied upon by the petitioner, I find that the same unlike the present case, pertain to cases where the Court was dealing with grant of pension to government employees where the dates of their superannuation are known to the employers well in advance. In the present case, the Board, which is dealing with over 16 lakhs registered building and construction workers, is discharging altogether a different responsibility and, therefore, the parameters applicable in the cases of government employees cannot be made per se applicable to the Board. However, this does not imply that the petitioner should not be paid any interest at all. In my view, it would be in the interest of justice that the petitioner should be paid interest on the delayed amount of pension after discounting 45 days from the date she submitted her documents on 05.08.2022. The writ petition is, accordingly, disposed of by directing the respondent to pay interest @ 6% per annum on the delayed amount of pension with effect from 21.09.2022 (after excluding 45 days w.e.f. 05.08.2022).

9. Before I conclude, I may observe that since the Act and Rules are silent regarding the time period during which the pension must be sanct

    Click Here to Read the rest of this document
    1
    2
    3
    4
    5
    6
    7
    8
    9
    10
    11
    SupremeToday Portrait Ad
    supreme today icon
    logo-black

    An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

    Please visit our Training & Support
    Center or Contact Us for assistance

    qr

    Scan Me!

    India’s Legal research and Law Firm App, Download now!

    For Daily Legal Updates, Join us on :

    whatsapp-icon Back to top