2022 Supreme(Del) 2200

IN THE HIGH COURT OF DELHI AT NEW DELHI
SATISH CHANDRA SHARMA, SUBRAMONIUM PRASAD, JJ.
M/s. Green Gene Enviro Protection And Infrastructure Pvt. Ltd. - Petitioner
Versus
Municipal Corporation Of Delhi & Anr. - Respondents
W.P.(C) No.11491 Of 2022 and C.M. Nos.33956-33957 Of 2022, W.P.(C) No.11550 Of 2022 and C.M. Nos.34185-34186 Of 2022
Decided On : 12-10-2022

Advocates Appeared:
For the Petitioner: Mr. Yogesh Chhabra.
For the Respondents: Ms. Beenashaw N. Soni with Mr. Bhupesh Pandotra.

The court emphasized the need for deference to the recommendations of experts in matters involving policy considerations and held that the Petitioners' conditional acceptance did not result in a concluded contract.

Headnote:

Tender Jurisdiction - Municipal Waste Management - N/A - The court discussed the principles of tender jurisdiction and the importance of accountability and transparency in contractual obligations. The court emphasized the need for deference to the recommendations of experts in matters involving policy considerations. The court held that the Petitioners' conditional acceptance did not result in a concluded contract, and they were unable to fulfill an essential requirement of the tender. Consequently, the court dismissed the petitions.

Fact of the Case:

The Petitioners sought a writ of mandamus to execute an agreement for waste management facilities. The Respondents added a condition for GPS tracking in the vehicles, to which the Petitioners expressed inability to comply. The Respondents then issued a fresh tender, leading to the filing of the petitions.

Finding of the Court:

The court found that the Petitioners' conditional acceptance did not result in a concluded contract, and they were unable to fulfill an essential requirement of the tender. The court emphasized the need for deference to the recommendations of experts in matters involving policy considerations.

Issues: Premature foreclosure of bid, validity of additional criteria, enforceability of agreement, and cancellation of fresh tender.

Ratio Decidendi: The court held that the Petitioners' conditional acceptance did not result in a concluded contract, and they were unable to fulfill an essential requirement of the tender. The court emphasized the need for deference to the recommendations of experts in matters involving policy considerations.

Final Decision: The court dismissed the petitions, stating that no valid contract was entered into by the Respondents with the Petitioners, and there was no merit in issuing a writ of mandamus or canceling the fresh NIT.

JUDGMENT :

1. The present Judgment will dispose of two Writ Petitions being W.P.(C) 11491 OF 2022 filed by one M/S Green Gene Enviro Protection & Infra and W.P.(C) 11550 OF 2022 filed by one M/s Recycling Solutions Pvt. Ltd. (“Petitioner/Petitioner Companies”) seeking inter alia the issuance of the writ of mandamus directing the Municipal Corporation of Delhi (“Respondent No. 1”) to execute the agreement dated 10.06.2022 to operate and maintain facilities to process minimum 1000 tonnes per day (hereinafter referred to as ‘TPD’) of incinerable waste, fraction recovered from processing of 80,00,000 MT legacy waste to produce RDF and its subsequent transportation and disposal on daily basis.

2. The facts leading up to the filing of the present petitions are as follows:-

a. On 08.03.2022, the Executive Engineer, Special Project Rohini Zone, on behalf of Respondent No. 1 issued a Notice Inviting Tender dated 08.03.2022 (“NIT”) for “Design, finance, build, own, operate & maintain processing facility to process minimum 1000 TPD of incinerable waste fraction recovered from processing of legacy waste to produce RDF and its subsequent transportation and disposal on daily basis.” (“Impugned Tender Process”)

b. Thereafter, two addendums were circulated on 29.03.2022 and 08.04.2022.

c. On 2nd May 2022, as per a condition in Addendum-2, Respondent No. 2 asked the Petitioners to match the lowest bid of L-1. The director of the Petitioner companies vide emails dated 03.05.2022 communicated the acceptance of the lowest bid offer to Respondent Nos. 1 and 2 (“Respondents”)

d. Pursuant thereto, on 10.06.2022, Respondent No. 1 issued a letter of acceptance (“LOA”) in favour of the Petitioners. As per the said LOA, the agreement was to be executed within 15 days. Pertinently, the Respondents added additional criteria in the LOA i.e the vehicle transporting the wase should have a GPS tracking system. For ease of reference the condition is reproduced below:-

“In order to ensure accounting of the waste transported, the vehicles to be used for transportation from the dump site to the place where it is consumed should have GPS Tracking System and the GPS data should be logged into MCD system electronically in real time basis. Further certificate from the agency consuming the incinerable waste shall be sought with respect to quantity received by it.”

e. As a response to the LOA, the Petitioners gave their acceptance vide letter dated 20.06.2020. However, the Petitioners specifically mentioned that they would be unable to fulfil the above mentioned criteria i.e. they would not be able to install a GPS tracking system in the vehicle.

f. Thereafter, the Respondents floated a fresh NIT to undertake the integrated work of Bio-mining of legacy waste including disposal of all the fractions recovered through bio-mining process viz., inert, RDF and C&D waste.

g. Vide letter dated 28.07.2022, the bids of the Petitioners were foreclosed. Aggrieved by the issuance of the fresh tender, and foreclosure of their bids, the Petitioners have filed the instant Writ Petitions.

3. In a nutshell, it has been argued on behalf of the Petitioners that the premature foreclosure of their bid is unjust, unfair, illegal, and arbitrary. Consequently, that this would cause undue delay in achieving the target for clearance of the MSW legacy dump.

4. Per contra, the Respondents have placed before this Court certain additional facts. It was brought to this Court’s attention that the tender was placed before the competent authority for administrative approval, on 31.05.2022, after the bids were received. During this meeting, the Special Officer, MCD incorporated the need for GPS Tracking system in the vehicle to be used for transportation of waste. Thereafter, the Respondents added this condition in the LOA issued to inter alia, the Petitioners. It was also pointed out that the LOA did not by itself create any rights or contractual relationship between the Petitioners and Respondents.

5. The Petition

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
whatsapp-icon Back to top