IN THE HIGH COURT OF DELHI AT NEW DELHI
Navin Chawla, J.
Ambey Mining Pvt. Ltd. – Appellant
Versus
Ntpc Ltd. – Respondent
Arb.P. 878 of 2022
Decided On : 11-01-2023
Arbitration - Appointment of Arbitrator - Arbitration and Conciliation Act, 1996 - Clause 7.3 of the General Conditions of the Contract - Section 11(6) of the Act
Fact of the Case:
The petitioner filed a petition seeking appointment of an Arbitrator for adjudicating disputes arising from a Contract Agreement. The respondent contended that the petition was premature as the petitioner failed to comply with the mandatory conciliation procedure prescribed in the Arbitration Agreement.
Finding of the Court:
The court found that the petitioner had attempted mutual consultation as required by Clause 7.1 of the General Conditions of the Contract. The court also interpreted the Arbitration Agreement and held that the conciliation process was not a mandatory pre-condition for invoking arbitration.
Issues: The issues involved the maintainability of the petition under Section 11(6) of the Act and the compliance with the conciliation procedure prescribed in the Arbitration Agreement.
Ratio Decidendi: The court held that the conciliation process was not mandatory and that the petitioner had made attempts at mutual consultation as required by the contract. The court also emphasized that the failure to mention the details of claims in the invocation notice did not deny the relief of arbitration to the petitioner.
Final Decision: The court allowed the petition and appointed an Arbitrator to adjudicate the disputes between the parties.
JUDGMENT
Navin Chawla, J. (Oral)
1. This petition has been filed under Section 11 of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as the 'Act') seeking appointment of an Arbitrator for adjudicating the disputes that have arisen between the parties in relation to the Contract Agreement dated 17.12.2019 executed between the parties regarding the "Engagement Of An Agency For Tipper Loading, Wagon Loading & Transportation Of Coal From Any Designated Mines To Any Designated Railway Siding For NTPC BARH-II (2X660 MW) Through RCR Mode".
2. The Arbitration Agreement between the parties is contained in Clause 7.3 of the General Conditions of the Contract (in short, the 'GCC').
3. The petitioner, before invoking the Arbitration Agreement, vide letter dated 05.09.2020, called upon the respondent to hold a joint discussion so that suitable course of action with regard to recommencement/reinstatement of work may be worked out mutually between the parties. In response, the respondent vide letter dated 04.12.2020, however, stated that the claim of the petitioner is not tenable. The petitioner, thereafter, by its letter dated 07.01.2021, while reiterating its claims, again called upon the respondent to hold a joint meeting to amicably resolve the existing issues. As no response to this notice was received, the petitioner invoked the Arbitration Agreement vide notice dated 19.02.2021.
4. The learned counsel for respondent submits that the present petition is not maintainable inasmuch as the petitioner has failed to comply with the mandatory procedure prescribed to be followed prior to seeking appointment of an Arbitrator. Referring to Clause 7.2 of the GCC, he submits that prior to invoking arbitration, the petitioner was to seek conciliation through an Expert Settlement Council (in short, 'ESC'). He submits that the petitioner failed to do so and, therefore, the present petition is premature. Referring the judgment of this Court in Sushil Kumar Bhardwaj v. Union of India, 2009 SCC OnLine Del 4355, he submits that for maintainability of the petition under Section 11(6) of the Act, the petitioner has to necessarily show that the procedure prescribed in the Arbitration Agreement has been duly followed. In the present case, as the petitioner has admittedly not invoked the conciliation process, the present petition is not maintainable. He submits that, in fact, Conciliation, as a process of dispute resolution, is to be encouraged and is even statutorily mandated in terms of Section 62 of the Act.
5. The learned counsel for the respondent further submits that the notice dated 19.02.2021 is also not in terms of Clause 7.3.1 of the GCC inasmuch as it does not give the details of the claims, including the heads/sub-heads of the claims. He submits that the Arbitration Agreement is restricted in nature inasmuch as arbitration can be invoked only where the total amount of claim, excluding claim of interest, does not exceed Rs.25 Crore.
6. I have considered the submissions made by the learned counsels for the parties.
7. Clause 7.1 of the GCC provides for the parties to attempt resolution of their disputes through mutual consultation. Admittedly, the petitioner made attempts of such settlement and invoked the said process by its notices dated 05.09.2020 and 07.01.2021.
8. Clause 7.2 of the GCC reads as under:
"7.2 Resolution of Dispute through Expert Settlement Council
If the parties fail to resolve such a dispute or difference by mutual consultation, the dispute if the parties agree, may be referred to Conciliation in cases involving disputed amount up to Rs 250 crores, which is to be arrived at considering the claim and counter claim of the parties to the dispute."
(Emphasis supplied)
9. A reading of the above Clause of the GCC would show that upon failure of the parties to arrive at an amicable settlement through mutual consultation, a further forum has been created for exploring the possibility of an amicable settlement t
The Conciliation process mentioned in the Contract was not mandatory and could not affect the petitioner's right to invoke the Arbitration Agreement, especially when there was justified urgency to pr....
The main legal point established in the judgment is that the appointment of an independent sole arbitrator is necessary, and the refusal of the petitioner to participate in conciliation proceedings d....
The main legal point established is that invoking the conciliation clause as per the contract and the respondent's failure to respond allows the petitioner to seek the appointment of an Arbitrator un....
The main legal point established in the judgment is that the petitioner's failure to exhaust the mandatory dispute resolution procedure as per the contract rendered the petition premature and non-mai....
The main legal point established in the judgment is the strict construction of arbitration clauses and the adherence to the terms of the arbitration agreement by the parties.
Failure to appoint an arbitrator within the agreed timeframe under Arbitration Agreement allows the court to intervene and appoint an arbitrator under Section 11(6) of the Arbitration and Conciliatio....
The main legal point established is the applicability of Section 11(6) of the Arbitration and Conciliation Act, 1996, in cases where a party fails to appoint an arbitrator within the stipulated time ....
The main legal point established in the judgment is the interpretation of arbitration clauses in favor of early resolution of disputes through arbitration, emphasizing the purpose of arbitration for ....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.