IN THE HIGH COURT OF DELHI AT NEW DELHI
Manoj Jain, J.
Ghh Bumi Mining Services Pvt. Ltd. – Appellant
Versus
Hindustan Zinc Ltd. – Respondent
O.M.P.(I) (COMM.) 204 of 2023
Decided On : 30-06-2023
Arbitration & Conciliation Act - Urgent directions sought for staying operation of termination of a project - Determinable nature of contract - Specific Relief Act provisions - Breach notices - Termination based on contractual terms - Injunction not permissible for determinable contract
Fact of the Case:
The petitioner sought urgent directions to stay the termination of a project awarded to it. The respondent terminated the project, claiming poor performance and breach of contract terms. The petitioner argued that the termination was arbitrary and illegal, and sought an injunction to stay the termination.
Finding of the Court:
The court found that the contract was determinable in nature and the termination was based on contractual terms and breach notices. The court held that the petitioner's remedy, if the termination was wrongful, would be to seek compensation for wrongful termination, not specific performance of the agreement. Therefore, the court dismissed the petition as the petitioner failed to make out a case for grant of interim injunction or protection.
Issues: The core issue was whether the contract in question was determinable by nature or not.
Ratio Decidendi: The court held that a contract which is determinable in nature cannot be specifically enforced, and no injunction against termination and enforcement of the contract can be issued. The court also emphasized that the observations made were prima facie in nature and would not prejudice any proceeding before the Arbitral Tribunal.
Final Decision: The petition was dismissed as the petitioner failed to make out a case for grant of any interim injunction or protection.
JUDGMENT
Manoj Jain, J. (Oral)
1. Present petition has been filed under Section 9 of the Arbitration & Conciliation Act, 1996 (in short `said Act') seeking urgent directions from this Court for staying operation of the termination by the respondent of a project awarded to it.
2. Since pressing urgency in the matter has been expressed by Sh. Sandeep Sethi, Ld. Senior Advocate, with the consent of both the sides, the arguments have been heard for the purposes of final disposal.
3. According to the petitioner, the project in question was for providing services including development of an underground approach to ore body to produce mines at Zwarmala Mine in Udaipur District, Rajasthan. This project was awarded on 30.12.2020 for 48 months i.e. till 31.12.2024. This was an extremely capital-intensive project which required huge investment of resources and creating of necessary infrastructure by the petitioner. The job was being done, all along, by the petitioner in the most earnest manner. However, by virtue of letter dated 31.05.2023, the respondent has, arbitrarily and in complete violation of the specific terms of the agreement between the parties, has chosen to terminate the services of the petitioner with effect from 30.06.2023. According to the petitioner, it had invested huge money, resources and manpower in the aforesaid project and the contract could not have been terminated in unilateral manner, particularly when it was not guilty of any breach, much less a material one.
4. The attention of the Court has also been drawn towards various clauses of the contract as well as to the several communications exchanged between the parties. It is claimed that it was obligatory for the respondent to have adhered to the terms mentioned in the contract and if at all the respondent was of the view that there were material breaches, it should have given three breach notices, as contemplated under the contract and only if the petitioner had not carried out the requisite remedy, the contract could have been terminated. According to the petitioner, there is nothing which may indicate that there was any breach on the part of the petitioner. According to the petitioner, if one goes through the alleged breach notices, it would become clear that these were, in fact, never the notices which could be termed as `breach notices' and thus there is arbitrary and illegal termination of the contract, without any cause and without any kind of lapse on the part of the petitioner. It is prayed that if the interest of the petitioner is not protected, it will be in complete defiance of the provisions of the contract and would also cause irreversible and irreparable loss to the petitioner, who has already made extensive investment of resources and manpower and has employed as many as 430 personnel on the aforesaid project. It is thus prayed that the termination letter dated 31.05.2023 be directed to be stayed and the respondent be restrained from taking any coercive steps in furtherance thereto.
5. The application has been vehemently opposed. According to Sh. Krishnan Venugopal, learned Senior Counsel for the respondent, this Court cannot entertain the above request and stay the termination. It is claimed that the contract in question was `determinable in nature' and when any such contract is determinable in nature and thus cannot be specifically enforced, no injunction against termination and thereby enforcement of contract can be issued.
6. The core issue is obviously plain and simple.
7. Whether the contract in question is determinable by nature or not?
8. Sh. Sandeep Sethi, learned Senior Counsel for the petitioner has relied upon the judgments of Coordinate Bench of this Court given in Ascot Hotels and Resorts Pvt. Ltd. & Anr. vs. Connaught Plaza Restaurants Pvt. Ltd., 2018 SCC Online Del 7940 and Golden Tobacco Limited vs. Golden Toble Private Limited, 2021 SCC Online Del 4506. He has also drawn the attention of this Court to the various cla
A contract that is determinable in nature cannot be specifically enforced, and no injunction against termination and enforcement of the contract can be issued.
The main legal point established in the judgment is that in the case of a determinable contract, no injunction against termination and enforcement of the contract can be issued.
A contract with specific termination conditions is not inherently determinable under Section 14 of the Specific Relief Act, allowing for interim relief to maintain status quo pending arbitration.
A determinable contract, such as an insurance contract subject to renewal, cannot be specifically enforced under Section 14 of the Specific Relief Act, and no injunction can be granted to prevent its....
Injunctions cannot be granted in cases involving infrastructure project contracts under Section 20A of the Specific Relief Act; damages are the appropriate remedy for wrongful termination in terminab....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.