SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2023 Supreme(Del) 3345

IN THE HIGH COURT OF DELHI AT NEW DELHI
Najmi Waziri, Vikas Mahajan, JJ.
Haryana State Industrial And Infrastructure Development Corporation – Appellant
Versus
IDBI Bank Limited & Anr. – Respondents
FAO(OS) (COMM) 90 of 2022, CM APPL. 19636 of 2022 & CM APPL. 24671 of 2023
Decided On : 11-07-2023

Advocates appeared:
Mr. Sudhir Nandrajog, Sr. Advocate with Mr. Lokesh Sinhal, Addl. AG for HSIIDC with Mr. Parvinder Chauhan, and Mr. Nikunj Gupta, Advocates for HSIIDC.
Mr. P. Chidambaram, Mr. Salman Khurshid, Sr. Advocates with Mr. Deepak Khurana and Ms. Nishtha Wadhwa, Advocates for KMP Expressway.
Dr. Abhishek Manu Singhvi and Mr. Gopal Jain, Sr. Advocates with Mr. Raunak Dhillon, Ms. Madhavi Khanna, Ms. Ananya Dhar Chaudhary, Ms. Isha Malik and Ms. Niharika Shukla, Advocates for IDBI Bank Ltd.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 37 - Appeal against arbitral award - HSIIDC challenged the award given by a three-member tribunal in favor of IDBI, awarding damages of Rs.1,737.11 crores for breach of the Substitution Agreement - Arbitral Tribunal found HSIIDC failed to ensure Senior Lenders were adequately considered in the appointment of new concessionaires. (Paras 3, 4, 12, 14, 17)

(B) Standards of Review - The scope of judicial review in arbitration matters is limited; courts do not re-evaluate the merits, focusing instead on public policy and patent illegality. (Paras 13.8, 30)

(C) Doctrine of Election - IDBI had impliedly consented to the new contractor as it did not oppose the Tender Notice released by HSIIDC, potentially compromising its claims against HSIIDC under the Doctrine of Election. (Paras 8, 9)

(D) Public Policy - The tribunal's findings were deemed plausible; mere errors of law do not constitute grounds for setting aside an award. (Paras 30, 31)

Facts of the case:
HSIIDC terminated its contract with KMPEL to appoint new concessionaires, leading IDBI to claim damages, asserting its interests were prejudiced. The tribunal awarded damages, finding that HSIIDC changed the project scope and failed to adhere to the substitution rights of lenders.

Findings of Court:
The court upheld the arbitral award, emphasizing that HSIIDC breached its obligations under the Substitution Agreement and recognizing the tribunal's compensatory measures as reasonable and justified.

Issues: The main issues concerned the validity of IDBI's claims given its lack of action, HSIIDC's obligations under the Substitution Agreement, and the nature of the award.

Ratio Decidendi: The court reasoned that the tribunal acted within its jurisdiction and that contractual obligations must be respected, noting that the decisions arrived at by the tribunal do not shock judicial conscience hence affirming the award's validity.

Result: Appeal dismissed.

Table of Content
1. appeal under arbitration act. (Para 1 , 2 , 3)
2. claims of misunderstandings in the contract and failure to comply with timelines. (Para 4 , 5)
3. argument on compensating for actual losses. (Para 6 , 7 , 8)
4. contention on interpretation of substitution agreement clauses. (Para 9 , 10)
5. scope of judicial review under sections 34 and 37. (Para 11 , 13 , 14)
6. conclusions drawn by the arbitral tribunal upheld. (Para 16)
7. hsiidc's responsibilities towards senior lenders. (Para 18 , 19 , 20 , 21)
8. recourse of senior lenders under the terms of the agreement. (Para 22 , 23 , 24 , 25 , 26)
9. preservation of rights and liability in dispute. (Para 27 , 28 , 29 , 30)

JUDGMENT

Najmi Waziri, J.

1. This appeal under section 37 of the Arbitration and Conciliation Act, 1996 (`the Act') impugns the order dated 29.03.2022 of the learned Single Judge dismissing the appellant/HSIIDC appeal in FAO(OS) (COMM) 90/2022 under section 34 of the Act against the Arbitral Award dated 24.03.2020. The Arbitral Award was delivered by a three-member Arbitral Tribunal comprising a former Chief Justice of India and two former judges of the Supreme Court.

2. For developing the Kundli-Manesar-Palwal (`KMP') Expressway, HSIIDC/appellant had appointed M/s. KMP Expressway Limited (KMPEL)/R-2 as the concessionaire. Monies were borrowed from the banks/Senior Lenders, which were represented by IDBI/R-1 as a lenders. agent. HSIIDC terminated the contract and appointed two concessionaires on terms that were different from KMPEL.s. Referring to the Substitution Agreement dated 08.01.2007, IDBI claimed that the appointment of the concessionaires by the appellant had prejudiced the interest of the Senior Lenders, therefore, it be awarded damages.

3. Finding the issues in favor of the IDBI, the Arbitral Tribunal awarded damages of a sum of Rs.1,737.11 crores along with future interest at the rate of 9% per annum from the date of the impugned award in favour of the IDBI and against the HSIIDC. Interestingly, it also noted that pursuant to proceedings initiated by the IDBI, before the DRT against KMPEL, HSIIDC would be entitled to re- imbursement of such amounts as may be recorded through DRT.

4. Mr. Sudhir Nandrajog, the learned Senior Advocate for HSIIDC submits that the impugned judgment is vitiated primarily because: (i) the Arbitral Tribunal.s findings suffer from perversity, ii) for the Award to hold that the appellant was in breach of the Substitution Agreement is erroneous and contrary to the records; iii) it disregards the fact that on 13.08.2013, a notice of default followed by a substitution notice dated 13.01.2014, was issued by IDBI itself and the latter being aware of the 120 days time window, ought to have nominated another entity in lieu of KMPEL. It did not do so, therefore, the appellant issued a cure notice dated 28.01.2015, especially when IDBI had already issued the afore-noted two notices; (iv) it was always open to IDBI to nominate another concessionaire but it failed to do so, therefore, in the larger public interest, the appellant was compelled to issue a cure notice dated 28.01.2015.

5. He further submits that since because of a delay in completion of the project, on 30.01.2015 the Supreme Court directed the appointment of a new concessionaire within a period of two months; therefore the Concession Agreement was terminated on 19.03.2015. It was in view of the Supreme Court.s strict timeline that the existing Concession Agreement became unworkable and impossible to follow the timeline prescribed in clause 3.1(iii) of the Substitution Agreement of at least 120 days for IDBI to nominate its Selectee. Therefore, in view of the imperative directions of the Supreme Court, Tender Notice was issued on 20.02.2015. Fresh bids were accepted for two separate sections of the KMP Highway on 28.03.2015 for Manesar-Palwal section and on 31.07.2015 for Kundli-Manesar section. The appellant argues that with the termination of the Concession

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top