IN THE HIGH COURT OF DELHI AT NEW DELHI
Sachin Datta, J.
Satluj Jal Vidyut Nigam Ltd. – Appellant
Versus
M/s Jaiprakash Hyundai Consortium & Ors. – Respondents
O.M.P. (COMM) 170 of 2017 and IA No.11895 of 2020 (Stay)
Decided On : 12-07-2023
ARBITRATION - Setting aside of award - Subsequent legislation - Price adjustment formula - Minimum wages - Interpretation of contract - Perversity - Public policy - Scope of judicial review.
Fact of the Case:
The dispute between the parties pertains to a contract for construction of civil works of pressure shafts and power house complex of the `Nathpa Jhakri Hydro-Electric project'. The subject matter of the dispute is the alleged quantum increase in the minimum wages payable to labour during the course of execution of the contract. The respondent/claimant is stated to have raised its claims before the concerned Engineer-in-Charge of the petitioner; the respondent/claimant is also stated to have taken recourse to filing an appeal before the CMD of the petitioner. The dispute/s having remained unresolved, the respondent (claimant) thereafter sought reference of the same to the Dispute Review Board ("DRB") prior to initiation of arbitration.
Finding of the Court:
The impugned arbitral award is set aside.
Issues: Whether, under the facts and circumstances of the matter, the claim is barred by limitation as contended by the Respondents. Whether, the notifications issued by the Govt. of Himachal Pradesh fixing/revising the minimum wages under the Minimum Wages Act, 1948 amount to subsequent legislation attracting the provisions of Clause 70(v) of the General Conditions of contract. Whether, under the facts and circumstances of the matter, the claim of the Claimants for expenses that the Claimants had to incur on account of revision of Minimum wages is tenable as per the Contract. If the answer to the issue no.iii supra is in the affirmative, as to what extent the claim is tenable.
Ratio Decidendi: The interpretation accorded by the arbitral tribunal to the relevant provisions of the contract is beyond the pale of interference in exercise of jurisdiction under Section 34 of the Arbitration and Conciliation Act, 1996. The conclusion of the arbitral tribunal to the effect that notification/s issued under the Minimum Wages Act attract the provisions of Clause 70 (v) of the GCC, brook no interference in exercise of jurisdiction under Section 34 of the A&C Act, 1996. The arbitral tribunal acted without evidence in concluding that the respondent/claimant had "incurred an expenditure of Rs.77.26 crores" towards labour wages in the relevant claim period. The notional scaling down of the labour escalation amount (from Rs.43.18 crores to Rs.14.39 crores) results in re-writing Annexure-XI of the contract. It is completely perverse to proceed (as the impugned award does) on the basis that respondent/claimant realised only an amount of Rs.14.21 crores (and not 43.18 crores) through escalation payable under Clause 70 (iii) of the GCC.
Final Decision: The impugned arbitral award is set aside.
JUDGMENT
O.M.P. (COMM) 170/2017
1. The present petition under Section 34 of the Arbitration and Conciliation Act, 1996 assails the Arbitral Award dated 11.01.2009, read with the order dated 26.02.2009 passed by the Arbitral Tribunal on an application filed by the petitioner under Section 33(1) of the Arbitration and Conciliation Act, 1996.
2. The disputes between the parties pertain to a contract for construction of civil works of pressure shafts and power house complex of the `Nathpa Jhakri Hydro-Electric project'. The subject matter of the dispute is the alleged quantum increase in the minimum wages payable to labour during the course of execution of the contract. It is the case of the respondent (claimant before the Arbitral Tribunal) that, as of 30 days prior to submission of the bid, the minimum wage of unskilled labour, as notified by the State Government of Himachal Pradesh was Rs.22/- per day. It is submitted that after submission of the bid, the minimum wage was increased to Rs.24/- per day w.e.f. 14.11.1993 and thereafter to Rs.26/- per day w.e.f. 01.10.1994. It is stated that thereafter, there was a quantum increase in minimum wage to Rs.45.75/- per day w.e.f. 01.03.1996. The claims raised before the Arbitral Tribunal were founded on the assertion that such increase in the minimum wage could not have been foreseen by the respondent/claimant and that the additional cost occasioned thereupon was also not taken into account by the claimant while tendering; the same was also not contemplated in the indexing of any inputs to the Price Adjustment Formula as contained under Clause 70 of the General Conditions to the Contract ("GCC"). It was contended that the financial impact of increase in minimum wages, being occasioned owing to "subsequent legislation", is payable to the respondent (claimant) in terms of Clause 70 (v) of the GCC.
3. Prior to reference of the aforesaid dispute to arbitration, the respondent/claimant is stated to have raised its claims before the concerned Engineer-in-Charge of the petitioner; the respondent/claimant is also stated to have taken recourse to filing an appeal before the CMD of the petitioner. The dispute/s having remained unresolved, the respondent (claimant) thereafter sought reference of the same to the Dispute Review Board ("DRB") prior to initiation of arbitration. The relevant contractual clause on the basis of which the claim was raised by the respondent/claimant on account of increase in minimum wages, is reproduced hereinbelow:
".........
Changes in Costs and Legislation
Clause-70 Increase or Decrease of Costs.
(i) Price Adjustment Factor
The amount payable to the Contractor and valued at base rates and prices in the Interim payment certificates issued by the Engineer-in-charge pursuant to sub-clause-60 (i) hereof shall be adjusted in respect of the increase or decrease in the indexed costs of labour, materials and fuel and lubricants in accordance with the following principles and procedures:
a) The cost of electrical energy supplied by the NJPC at fixed prices shall be excluded from the scope of price adjustment;
b) Price adjustment shall apply only for work carried out within the stipulated time or extensions granted by the NJPC and shall not apply to work carried out beyond the stipulated time for reasons attributable to the Contractor;
c) Price adjustment shall be calculated for the local and foreign components of the payment for work done in the manner explained in the sub-clause (iii) hereof.
d) The price adjustment shall be determined during each quarter from the formulae as detailed hereinafter under sub-clause (iii) of this Clause.
The following expressions and meanings are assigned to the value of the work done during each quarter:
R=Total value of work done during the quarter excluding cost of electrical energy supplied by the NJPC at fixed prices and any adjustment in payments resulting from legislative or statutory action as per sub clause (v) of this clause.
RI=Portion of `R. a
State of Madhya Pradesh versus Ramcharan
Associate Builders. Vs. Delhi Development Authority
Centrotrade Minerals & Metals Inc. versus Hindustan copper Ltd.
Edward Mills Co. Ltd. Vs. State of Ajmer
Hindustan Zinc Limited versus Friends Coal Carbonisation
JG Engineers (P) Ltd. versus Union of India & Anr.
Kailash Nath and Another versus State of U.P. and Others
McDermott International Inc. v. Burn Standard Co. Ltd.
Narinder Chand Hem Raj versus Lt. Governor & Administrator, UT H.P. & Ors.
NHAI vs. ITD Cementation India Ltd.
ONGC Ltd. versus Saw Pipes Ltd.
ONGC Ltd. versus Western Geco International Ltd.
State of Bombay and another versus F.N. Balsara
Subhash Ramkumar Bind alias Vakil and Another versus State of Maharashtra
U. Unichoyi & Ors. v. State of Kerala
Union of India versus Col. L.S.N. Murthy & Anr.
Video Electronics (P) Ltd. & Anr. versus State of Punjab & Anr.
Every error of law committed by an arbitral tribunal does not fall within the scope of the patent illegality. However, the Court had also clarified that illegality, which goes to the root of the matt....
Point of law: Scope of examination under Section 34 is limited. The decision of the Arbitral Tribunal regarding consideration and interpretation of the Contract is final and this Court cannot supplan....
The Arbitral Tribunal's interpretation of reimbursement based on actual costs incurred due to statutory changes is valid, despite disputes over contract terms, reinforcing the principle of contractua....
The court affirmed that an arbitral award can be set aside if it contravenes the terms of the contract or exceeds the jurisdiction of the arbitrator, emphasizing the importance of notified claims.
Point of law: In terms of Section 21 of the A&C Act, the arbitral proceedings commence on the date of receipt of notice invoking the arbitration agreement.
In terms of Section 21 of the A&C Act, the arbitral proceedings commence on the date of receipt of notice invoking the arbitration agreement.
An arbitrator cannot exceed contractual terms; applying external recommendation outside the agreed terms constitutes a jurisdictional error and is subject to judicial review under Sections 34 and 37 ....
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.