SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img



IN THE HIGH COURT OF DELHI
Vibhu Bakhru, J.
NTPC Ltd. - Appellant
Versus
Larsen and Toubro Limited - Respondent
O.M.P. (COMM) 560 of 2020 and O.M.P. (COMM) 524 of 2020
Decided On : 26-11-2021




The Arbitral Tribunal's interpretation of reimbursement based on actual costs incurred due to statutory changes is valid, despite disputes over contract terms, reinforcing the principle of contractual obligations under the arbitration framework.

Headnote:(A) Arbitration and Conciliation Act, 1996 - Section 34 - Minimum Wages Act, 1948 - Dispute regarding reimbursement of additional costs due to increase in basic minimum wages - Tribunal ruled L&T entitled to Rs.18.24 crores + 10% interest, subject to proof of additional costs incurred - Court upheld tribunal's interpretation that Clause 31.4.3 allows reimbursement for actual expenditure incurred, despite NTPC's challenges regarding contract terms - Award partially set aside regarding future payments tied to certification by a Chartered Accountant. (Paras 20, 24, 39)

Facts of the case:
Dispute arose over L&T's claim for additional payment due to increased minimum wages as per a government notification, leading to arbitration initiated by NTPC after disagreements over contract terms and entitlements. (Paras 2.5, 3, 9)

Findings of Court:
The Arbitral Tribunal found L&T entitled for reimbursement of additional costs under the contract, based on the increase in basic minimum wages, supported by evidence presented, despite NTPC's contention otherwise. (Paras 12, 19, 39)

Issues: The court addressed whether L&T was entitled to the claimed reimbursement considering the contractual provisions and whether the tribunal's award was patently illegal. (Paras 19, 31)

Ratio Decidendi: The court upheld that reimbursement for actual costs must be proven, affirming the Arbitral Tribunal's discretion on contractual interpretation and awarding a factual basis for reimbursement claims, dismissing NTPC’s objections. (Paras 21, 38)

Result: NTPC’s petition partly allowed; L&T's petition dismissed.

JUDGMENT

Vibhu Bakhru, J. The parties have filed these petitions under Section 34 of the Arbitration and Conciliation Act, 1996 (hereinafter the `A&C Act') impugning an arbitral award dated 12.06.2020 (hereinafter `the impugned award') delivered by the Arbitral Tribunal constituted of three members, Mr Arun Kumar, I.A.S (Retd.), Justice M.Y. Eqbal (Retd.) and Justice Dr Mukundakam Sharma (Retd.) as the Presiding Arbitrator (hereafter `the Arbitral Tribunal').

2. The controversy in the present case arises in the following context:

2.1. Tenders were invited by NTPC Limited (hereafter `NTPC') for implementation of contracts relating to setting up of the Khargone Super Thermal Power Project (hereinafter `the Project'). The work was divided into three packages as under:

    Contract Package 1 : CIF Supply (Indian Port of Entry)

    Contract Package 2 : Ex-works (India) Supply

    Contract Package 3 : Inland Transportation, Inland Insurance, Civil Works, Structural Works, Installation, Testing & Commissioning of EPC

2.2. Larsen and Toubro Limited (hereafter `L&T') had participated in the bidding process pursuant to the aforesaid notice inviting tenders. L&T's bid for the contracts was accepted and on 31.03.2015, NTPC issued three Notifications of Awards in favor of L&T.

2.3. Thereafter, contracts for all the aforesaid packages were signed by the parties on 03.04.2015.

2.4. The impugned award was rendered in the context of the disputes that have arisen between the parties in connection with the third contract package (hereafter `the Contract Agreement') for the `supply and erection including civil works of EPC Package Khargone Super Thermal Power Project' awarded to L&T by NTPC by the Notification of Award on 31.03.2015.

2.5. The dispute between the parties relates to the L&T's claim for payment of additional amounts as compensation for the increase in costs on account of increase in the basic minimum wage rates notified in terms of notification no. S.O.188 (E) dated 19.01.2017 (hereafter `the Notification') issued under the Minimum Wages Act, 1948.

2.6. By its various communications, L&T stated that the increase in minimum wages of construction workers had severely affected the labour cost portion in executing the contracts and requested NTPC to consider reimbursement of additional costs in terms of Clause 31.4.3 of the Special Conditions of Contract (hereafter `SCC'), which provided for reimbursement of increased expenses, inter alia, resulting from any change in law.

2.7. NTPC rejected L&T's claim stating that price adjustment for compensation for any increase in the minimum wages was covered in Appendix-2 of the Contract Agreement.

2.8. L&T did not accept NTPC's stand and requested NTPC to appoint an adjudicator for settlement of the disputes. By the award passed by the adjudicator on 07.10.2018, NTPC was directed to reimburse L&T in terms of Clause 31.4.3 of the SCC.

2.9. Aggrieved by the award passed by the adjudicator, NTPC invoked Clause 6.2 of the General Conditions of Contract (hereafter `GCC') read with Clauses 4 and 42 of the SCC and referred the matter to arbitration for adjudication of the disputes.

3. The claims made by L&T before the Arbitral Tribunal are set out below:

CLAIMPARTICULARSAMOUNT
Claim no.1Impact due to revision in minimum wagesRs.99 crores (revised to Rs.103.2 crores/-)
Claim no.2(a)Interest @14% per annum on monthly payments due from March 2017 till 31st December 2018Rs.13.03 crores/-
Claim no.2(b)Interest @14% per annum on monthly payments due from 1st January, 2019 till date of payment
Claim no.3To pay increased costs on account of the notification dated 19.01.2017 from 1st January 2019 till completion of the contract within a time period and in default, interest.
Claim no.4Costs of arbitrationRs.1,53,81,629/-

4. The impugned award was delivered by majority, with Justice (Retired) M.Y. Eqbal entering a partially dissenting opinion. The Arbitral Tribunal partially allowed the claims of L&T and held that

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top