SupremeToday Landscape Ad
Back
Next
Judicial Analysis Court Copy Headnote Facts Arguments Court observation
Listen Audio Icon Pause Audio Icon
judgment-img

2023 Supreme(Del) 3844

IN THE HIGH COURT OF DELHI AT NEW DELHI
Manoj Kumar Ohri, J.
Government of NCT of Delhi – Appellant
Versus
R. S. Sharma Contractors Pvt. Ltd. – Respondent
O.M.P. (COMM) 130 of 2023 and I.A. 6584 of 2023
Decided On : 16-08-2023

Advocates appeared:
Mr. Anupam Srivastava, ASC, GNCTD with Mr. Dhairya Gupta and Mr. Vasuh Misra, Advocates, for the Petitioner.
Mr. M.K. Ghosh, Advocate with Mr. H.S. Sharma, AR, for the Respondent.

The Court upheld the AT's findings regarding the attribution of delay, enforcement of NOC, and the allowance of the claim for escalation cost without a specific clause in the Contract, based on the narrow scope of Section 34 of the A&C Act.

Headnote:

A&C Act - Dispute arising from widening of bridge project - Arbitral Award challenged - Claims for escalation cost and prolongation of Contract allowed - Scope of Section 34 of A&C Act defined - Patent illegality principle explained - NOC issuance and enforcement - Claim for escalation cost without specific clause in Contract - AT's findings upheld

Fact of the Case:

The petitioner, Govt. of NCT of Delhi, challenged an Arbitral Award regarding a widening of bridge project. The Contractor raised claims for escalation cost and prolongation of Contract, which were allowed by the Arbitral Tribunal. The petitioner restricted the challenge to the impugned Award to the extent that claims for escalation cost and prolongation of Contract were allowed, and contended that the ground of challenge is restricted to patent illegality.

Finding of the Court:

The Arbitral Tribunal found that the delay in completion of the Project was attributable to the petitioner. The AT observed that the petitioner admitted delay of 1047 days as justified delay, whereas the Contractor's request for extension of time was only for 1041 days. The AT also opined that the NOC issued by the Contractor was involuntary and hence, cannot be enforced against the Contractor to deny a claim, to which it was otherwise entitled. The AT upheld the claim for escalation cost, even without a specific clause in the Contract, as the delay was attributable to the petitioner.

Issues: The issues revolved around the attribution of delay in the project, enforcement of NOC, and the allowance of the claim for escalation cost without a specific clause in the Contract.

Ratio Decidendi: The Court upheld the AT's findings that the delay was attributable to the petitioner, the NOC issued by the Contractor was involuntary, and the claim for escalation cost was justified even without a specific clause in the Contract, as the delay was attributable to the petitioner.

Final Decision: The objections failed and the petition, along with pending application, was dismissed with no order to costs.

JUDGMENT

Manoj Kumar Ohri, J. The present petition under section 34 of the A&C Act [Arbitration and Conciliation Act, 1996] has been preferred by the petitioner, Govt. of NCT of Delhi, assailing the Arbitral Award dated 16.11.2022 rendered by the AT [Arbitral Tribunal] comprising of a Sole Arbitrator.

2. The impugned Award was rendered in the context of disputes arising w.r.t. Agreement No. EE/CD-III/ACS/Agmnt/10/14-15 ("the Contract") dated 13.09.2014, executed in favour of the Respondent/Contractor [R.S. Sharma Contractors Pvt. Ltd.] for widening of bridge at RD-900m of Shahdara out fall drain near Kalindi Kunj, Noida ("the Project").

3. The stipulated dates for commencement and completion of the Project were 13.09.2014 and 12.03.2016 respectively. Indisputably, the Project could not be completed within the stipulated period, resulting in a request for extension of time by the Contractor. The extension was granted, and the Project was finally completed on 17.01.2019. Disputes having arisen w.r.t. payment of final bills and attributability of delays, arbitration was invoked. In its statement of claim, the Contractor raised claims for a total of Rs.5,44,24,036/-, inter alia, alleging that the delay in execution of work was attributable to the petitioner. A total of 8 claims were filed, pursuant to which the petitioner filed its statement of defence, but no counter claim.

4. The details of the claims raised are as follows:

i) Claim 1: Claim on account of work done not paid. Petitioner denied the claim on the ground that the cost of the initial test pile was not payable as per MORTH specification and that the pile was rejected as per the terms and conditions of the agreement, as the quantity of RMC poured in pile was less than the required quantity. Thus, nothing extra is payable

ii) Claim 2: Claim on account of less payment of substituted item. Petitioner denied the claim on the ground that the rate was derived on the basis of CPWD/DAR components and the same was approved on 15.10.2015, and not after completion of the work. Thus, nothing extra is payable

iii) Claim 3: Claim on account of less rate paid for extra item 4. Petitioner denied the claim on the ground that the rate paid by the department was accepted by the Contractor. Thus, nothing extra is payable

iv) Claim 4: Claim on account of increase in wages as per clause 10C. Petitioner denied the claim on the ground that the Contractor had already given an undertaking to not claim anything extra due to delay on the EOT proforma part 1. Thus, nothing extra is payable

v) Claim 5: Claim on account of prolongation of contract

Claim 5(a): Claim on account of increase in wages for labour on prevailing rates as per clause 10C as a compensation

Claim 5(b): Claim on account of increase in prices of material as damages in prolongation of contract

Claim 5(c): Compensation for losses on account of overstay at site in extended period for site establishment

Claim 5(d): Compensation for losses on account of overstay of machinery, tools and plant in extended period

Claim 5(e): Claim on account of head office expenses

Petitioner denied the claims on the ground that the Contractor had already given an undertaking to not claim anything extra due to delay on the EOT proforma part 1. Thus, nothing extra is payable

vi) Claim 6: Claim on account of interest @12%. Petitioner denied the claim on the ground of whatever was stated in the above-mentioned claims

vii) Claim 7: Due on account of GST on claim amount @ 12%. Petitioner denied the claim on the ground of whatever was stated in the above-mentioned claims

viii) Claim 8: Cost of arbitration. Petitioner denied the claim on the ground of the general submissions made

5. The summary of claim amounts, as claimed and as awarded by the AT, is set out below:

Claim No.Claimed Amount (in Rs.)Awarded Amount (in Rs.)Interest awarded @ 10% p.a. from date
1.10,31,144/-10,00,000/-17.03.2021
2.38,67,054/-32,93,054/-17.03.2021
3.30,10,524/-2,25,000/-17.03.2021
4.17,58,801/-17,58

Click Here to Read the rest of this document
1
2
3
4
5
6
7
8
9
10
11
SupremeToday Portrait Ad
supreme today icon
logo-black

An indispensable Tool for Legal Professionals, Endorsed by Various High Court and Judicial Officers

Please visit our Training & Support
Center or Contact Us for assistance

qr

Scan Me!

India’s Legal research and Law Firm App, Download now!

For Daily Legal Updates, Join us on :

whatsapp-icon Back to top