IN THE HIGH COURT OF DELHI AT NEW DELHI
MANMOHAN, C.J., TUSHAR RAO GEDELA, J.
Jamia Arabia Nizamia Welfare Education Society – Appellant
Versus
Delhi Development Authority Through Its Vice Chairman & Ors. - Respondents
W.P.(C) 638 of 2024, CM APPL. 2793 of 2024, CM APPL. 6077 of 2024, CM APPL. 10222 of 2024, CM APPL. 10223 of 2024, CM APPL. 27052 of 2024, CM APPL. 27387 of 2024 & CM APPL. 27388 of 2024
Decided on : 13-11-2024
(A) Public Interest Litigation - Illegal construction - Unauthorized construction at Ziyrat Guest House - Petitioner sought demolition of illegal structures - Court directed investigation by CBI due to inaction by statutory authorities - MCD and DDA admitted lapses in enforcement - Structural reforms mandated to prevent future encroachments. (Paras 1-24)
(B) Jurisdiction - Overlapping jurisdiction of MCD and DDA - Need for clear demarcation of responsibilities highlighted - Court emphasized the importance of effective enforcement against unauthorized constructions. (Paras 22-23)
Facts of the case:
The petitioner filed a PIL against unauthorized construction at Ziyrat Guest House, leading to a CBI investigation due to inaction by MCD and DDA despite multiple complaints.
Findings of Court:
The court found significant administrative lapses by MCD and DDA, leading to unauthorized constructions in public land.
Issues: The main issues included the responsibility of statutory authorities in preventing illegal constructions and the need for structural reforms.
Ratio Decidendi: The court ruled that the CBI should investigate the matter thoroughly, emphasizing the need for accountability among officials and effective measures against unauthorized constructions.
Result: PIL closed as the unauthorized construction was demolished.
JUDGMENT :
MANMOHAN, C.J.
1. Present Public Interest Litigation had been filed seeking action against officials of the respondents who had allowed the encroachers to carry out unauthorized/illegal construction at Khasra no. 556, Ziyrat Guest House, near Baoli Gate, Hazrat Nizamuddin Dargah, near Police Booth. The petitioner had also sought a direction to demolish the said illegal and unauthorized construction.
2. When the matter was listed for the first time on 16th January, 2024, this Court was informed that despite the petitioner’s representation dated 3rd November, 2023 to the respondents highlighting the illegal construction being carried out at Ziyrat Guest House and the Archaeological Survey of India (ASI) issuing a Work Stop Notice dated 11th December, 2023, the statutory authorities had failed to take any action. Since learned counsel for ASI had stated that it had written a letter dated 2nd January, 2024 to the SHO, Nizamuddin (West) to register an FIR, this Court had observed that, prima facie, illegal and unauthorized construction was taking place with the tacit support, if not active connivance of statutory authorities and hence directed the respondents to ensure that no further construction was carried out at Ziyrat Guest House arrayed as respondent no.5.
3. Thereafter, on 1st February, 2024, an impleadment application was filed by Mr. Babu Ali, who claimed himself to be the new owner of Ziyrat Guest House. At that time, learned counsel for MCD had stated that despite sealing the first and second floor of the said property, the erstwhile owner namely, Mr. Raisuddin sold the property to Mr. Babu Ali. He stated that Mr. Babu Ali not only entered the said sealed property but also carried out construction of third, fourth and fifth floors. It was further stated that even the ground and the first floor of the said property were illegal and unauthorised as the land in question belonged to DDA. He had further stated that substantial demolition had been carried out by the MCD on the third, fourth and fifth floors of the subject property. Learned counsel for the DDA had stated that the subject property falls in Khasra No. 556 Min. of Aliganj Revenue Estate, which is government land placed at the disposal of the DDA pursuant to the Nazul Agreement dated 31st March, 1937.
4. Learned counsel for the Delhi Police had stated that on 17th January, 2024, it had registered an FIR No.0024 on the basis of a letter dated 2nd January, 2024 received by the SHO from the office of Conservation Assistant, ASI, Humayun’s Tomb.
5. In view of the aforesaid submissions and upon finding encroachment on public land coupled with illegal and unauthorised constructions at such a massive scale had taken place in the heart of Delhi, that too virtually under the nose of officials of the MCD, DDA, ASI and Police, this Court vide order dated 1st February, 2024 had noted that, prima facie, the matter required to be investigated by the Central Bureau of Investigation (CBI).
6. On 7th and 8th February, 2024, the Deputy Commissioner, MCD admitted before the Court that MCD had received written information from Delhi Police as far back as 23rd October, 2023 and 8th November, 2023 about the illegal and unauthorized construction being carried out at Ziyrat Guest House. She had stated that the said information had been marked to the Junior Engineer (JE) who did not take any action. It was further admitted that despite fresh intimation from the Delhi Police on 9th December, 2023 and from the ASI on 11th December, 2023 and on 2nd January, 2024, the new JE and the Assistant Engineer (AE) had not taken any action. No action was taken even on the representation filed by the petitioner dated 3rd November, 2023 to the Commissioner, MCD.
7. Subsequently, an application being C.M. No. 8584/2024 was filed by Mr. Babu Ali in which it was stated that the owner of the land is Delhi Waqf Board, and not the DDA. Though during the hearing, learned counsel for Mr. Babu Ali had admitted
AI
The court mandated CBI investigation into unauthorized constructions due to administrative lapses by statutory authorities, emphasizing accountability and structural reforms.
Point of Law : In light of the recoveries made and statement made by the independent witnesses, it cannot be ruled out that the petitioner has been involved in the commission of Sections 13(2) and 13....
Municipal authorities must act promptly against unauthorized constructions, as they violate planning laws and undermine public interest.
Login now and unlock free premium legal research
Login to SupremeToday AI and access free legal analysis, AI highlights, and smart tools.
Login
now!
India’s Legal research and Law Firm App, Download now!
Copyright © 2023 Vikas Info Solution Pvt Ltd. All Rights Reserved.