IN THE HIGH COURT OF DELHI
G.S. Sistani, Anup Jairam Bhambhani, JJ.
Lion Heart Secure Solution Pvt. Ltd. - Appellant
Versus
Union of India - Respondent
W.P.(C) 4082 of 2019
Decided On : 06-11-2019
Important Points
Subject
Administrative Law - Judicial Review
Headnote
(B) Tendering Process - Grounds for Rejection - The court reiterated that only extreme cases of mala fides, arbitrariness, or irrationality warrant judicial interference in tender decisions. (Paras 14-20)
| Table of Content |
|---|
| 1. petitioner's technical bid rejection (Para 1 , 2 , 3 , 4 , 5 , 6 , 7) |
| 2. arguments regarding bid rejection (Para 8 , 9 , 10 , 11 , 13) |
| 3. judicial review principles in tender matters (Para 12) |
| 4. standards for interference in tender decisions (Para 14 , 15 , 16 , 17) |
| 5. dismissal of the petition (Para 18 , 19) |
JUDGMENT
G.S. Sistani, J. (Oral)--This petition has been filed by the petitioner under Article 226 of the Constitution of India seeking a writ of mandamus against the respondents to quash decision dated 26.03.2019 of respondent No.2, whereby it is contended that the technical bid of the petitioner was rejected without giving justifiable reasons and with the sole motive to favour another bidder.
2. Some necessary facts which are required to be noticed for disposal of this writ petition are that on 11.07.2018, a notice was issued by respondent No. 2 inviting E-tender for setting-up new LPG Bottling facilities at 60 different locations from private bottlers having ready built plant/willing to construct new LPG bottling facility.
3. Accordingly, a common tender for all 60 identified locations was floated. The object was that the successful bidder should be able to create adequate plant and infrastructural facilities and possess competence to engage in the activities required for handling of the LPG bottling operations with caution and safety.
4. The petitioner claims to be a registered company dealing in LPG products and having sound financial track record to carry-out the work of refilling LPG cylinders by establishing a new bottling plant.
5. The petitioner company participated in the E-tender published by respondent No. 2 for one location i.e. Jhansi and submitted the required documents.
6. On 03.12.2018 a techno-commercial query was raised by respondent No. 2 on its e-portal, which was duly replied to by the petitioner company on 10.12.2018. After evaluation of the pre-qualification criteria, eligibility criteria and technical bid documents in Round I, the petitioner was found eligible for Round II; and was interviewed on 24.01.2019, when original digital records were submitted on the e-portal. After the interview, the petitioner was found eligible for Round III and was called for site-inspection.
7. The complaint of the petitioner is that the technical bid of the petitioner has been rejected after site-inspection in Round III without respondent No.2 giving any cogent grounds/reasons for doing so.
8. Mr. Ganda, learned counsel for the petitioner submits that within 24 hours of rejection of the petitioner's technical bid, respondent No. 2 hurriedly fixed the time for opening of financial bid on 27.03.2019 at 4.10 p.m. Mr. Ganda submits that the rejection of the technical bid by respondent No.2 is baseless, mala fide and arbitrary; and has been done with a view to accommodating particular parties, in whose favour respondent No.2 had pre-decided that the tender should be awarded.
Site at Jhansi
9. Mr. Ganda further submits that the purported ground for rejection of the technical bid of the petitioner was that out of three co-owners of the offered plot, lease was executed by the petitioner with only one co-owner. Counsel submits that all three co-owners of the offered plot are members of one family and the lease deed was executed with one of the co-owners after taking No-Objection Certificates (NOCs) from the other two co-owners. Therefore, rejection of the technical bid of the petitioner for Jhansi in Round III on this ground is baseless and arbitrary.
10. Ms. Meenakshi Arora, learned senior counsel for respondent No.2 submits that the rejection of technical bid of the petitioner is on two grounds. The first ground for rejection is that out of 3 co-owners of the offered plot, lease is executed with only one co-owner. She submits that a reading of the lease submitted by the petitioner and letter dated 30.03.2019 sent by the petitioner to respondent No.2 would show that though the proposed land